LP formulation for Pottery Problem



Resource Requirements

Labor Clay Revenue

Product (hr/unit) (lb/unit) ($/unit)

Bowl 1 4 40

Mug 2 3 50



There are 40 hours of labor available per day

There are 120 pounds of clay available per day



How many bowls and how many mugs to make daily to maximize revenue?



The optimization model:



B M

Units made: 24 8

MAX 40 50 1360 Total Revenue

Total

subject to Usage Available

1 2 40 40 labor

4 3 120 120 clay

Microsoft Excel 10.0 Answer Report

Worksheet: [In-Class LP Examples.xls]Pottery Problem

Report Created: 10/30/2002 10:01:46 AM





Target Cell (Max)

Cell Name Original Value Final Value

$F$17 MAX 1360 1360





Adjustable Cells

Cell Name Original Value Final Value

$D$16 Units made: B 24 24

$E$16 Units made: M 8 8





Constraints

Cell Name Cell Value Formula Status Slack

$F$19 Total Usage 40 $F$19<=$G$19 Binding 0

$F$20 Total Usage 120 $F$20<=$G$20 Binding 0

Microsoft Excel 10.0 Sensitivity Report

Worksheet: [In-Class LP Examples.xls]Pottery Problem

Report Created: 10/30/2002 10:01:47 AM





Adjustable Cells

Final Reduced Objective Allowable Allowable

Cell Name Value Cost Coefficient Increase Decrease

$D$16 Units made: B 24 0 40 26.66666667 15

$E$16 Units made: M 8 0 50 30 20



Constraints

Final Shadow Constraint Allowable Allowable

Cell Name Value Price R.H. Side Increase Decrease

$F$19 Total Usage 40 16 40 40 10

$F$20 Total Usage 120 6 120 40 60

LP Lego Problem Formulation



Resource Requirements

Large Small Revenue

Product Legos Legos ($/unit)

Table 2 2 16

Chair 1 2 10



There are 6 large legos available

There are 8 small legos available



How many tables and how many chairs to make daily to maximize revenue?



The optimization model:



T C

Units made: 3 0

MAX 10 10 30 Total Revenue

Total

subject to Usage Available

2 1 6 6 Large Legos

2 2 6 8 Small Legos

Microsoft Excel 10.0 Answer Report

Worksheet: [In-Class LP Examples.xls]Lego Problem

Report Created: 10/30/2002 10:02:38 AM





Target Cell (Max)

Cell Name Original Value Final Value

$F$17 MAX 52 52





Adjustable Cells

Cell Name Original Value Final Value

$D$16 Units made: T 2 2

$E$16 Units made: C 2 2





Constraints

Cell Name Cell Value Formula Status Slack

$F$19 Total Usage 6 $F$19<=$G$19 Binding 0

$F$20 Total Usage 8 $F$20<=$G$20 Binding 0

Microsoft Excel 10.0 Sensitivity Report

Worksheet: [In-Class LP Examples.xls]Lego Problem

Report Created: 10/30/2002 10:02:38 AM





Adjustable Cells

Final Reduced Objective Allowable Allowable

Cell Name Value Cost Coefficient Increase Decrease

$D$16 Units made: T 2 0 16 4 6

$E$16 Units made: C 2 0 10 6 2



Constraints

Final Shadow Constraint Allowable Allowable

Cell Name Value Price R.H. Side Increase Decrease

$F$19 Total Usage 6 6 6 2 2

$F$20 Total Usage 8 2 8 4 2



Related docs
Other docs by linzhengnd
i-Health
Views: 0  |  Downloads: 0
State employees recall events of September 11
Views: 7  |  Downloads: 0
0804050421330_2110
Views: 4  |  Downloads: 0
Listino2009 - Meetup
Views: 0  |  Downloads: 0
TwoSurveyCalculator
Views: 0  |  Downloads: 0
Guidelines.xlsx
Views: 0  |  Downloads: 0
APPALACHIA AND THE OZARKS
Views: 2  |  Downloads: 0
Proliferation Studies
Views: 0  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!