CONSTRUCTION MEETING MINUTES NO. 42

PROJECT: SLVHD South Main Health Clinic DATE: March 21, 2007

PROJECT NO. NN06102 TIME: 9:30 a.m.

LOCATION: 3690 South Main Street WEATHER: clear

Salt Lake City, Utah 84115 TEMPERATURE: 48EF

OWNER: SLCO

PROJECT MANAGER: Ryan Henrie

CONTRACTOR: Ascent Construction

ARCHITECT: HHY Associates

ATTENDANCE:

Ryan Henrie, SLCO Facilities Management Brandt Knowlton, Ascent Construction

Ricardo Flores, SLVHD Chryshele Cottle, Ascent Construction

Kristy Cottrell, SLVHD South Main Stan Edwards, Ascent Construction

Huina Ho, HHY Associates

1. Revisions to Previous Minutes:



2. Schedule:

A. Project start date: June 15, 2006

Substantial completion date: March 29, 2007

Number of contract days: 284 calendar days



B. Upcoming scheduled events:



C. Estimated % of work completed: 67%



D. Work not on schedule and reason(s): 8x20 steel tubes are not available.



E. Recovery plan to bring the project back on schedule:



F. Work progress during the past week:

• Erosion control maintained.



G. Work planned for the coming week:

• One more big load of roll beams is scheduled to be delivered tomorrow, Thursday,

March 22. All rolled beams are available with exception of rolled fascia beams.

Started steel erection last week with 7 iron workers. Rolled beams at Main Waiting

area on grid D, D.1, E, E.1, and E.2 are in place. Continue welding purlins between

the in-place beams. Some purlins are shorter need to be fill-in with shim pieces, some

purlins need to be trimmed. Fill-in are structurally fine. Will be ready for installing

curved deck by the end of next week.

• Continue rough in plumbing, copper line, insulation pipes, and VAV at the south side.

• Continue ductwork rough in at center and west areas toward the south side.

• Will start installing fire sprinkler next week.

• In process of installing sheet rock hard lids and soffits. Continue taping at the low roof

areas, second coats at Examine Rooms.

• Aluminum windows and glazing were completed. Replacements of broken glass will

be here with aluminum storefronts next week.

• Start installing exterior hollow metal door hardware.

• Emergency generator and MC panel were bumped to Friday, March 23 due to

needing to work on the concrete (stair, landing) at the northwest corner of the

building

• Stan Edwards talked to Mark of Questar Gas to bring the line to the meter, Ascent will

pour the meter pad next week. Ryan Henrie has a check to pay Questar; Questar will

release the work order.

• Americom (cables/wires installer) has caught up with installing cables.

• SLVHD will need to contact Quest for phone lines installation.

• Site concrete (walkway, pads) for the south side will be completed next week. Start

grading the north side.

• Start landscape irrigation.

• Sign contractor will put the footing for the monument sign.

• Continue maintaining dust and erosion control. Patched silt fence.



3. Shop Drawings, Product Data, & Samples Submittals

Shop drawings Submitted by Returned by Resubmitted Returned by A/E

Contractor A/E by Contractor



Finish Hardware & 6/14/2006 6/26/2006

Door Schedule



Traffic coatings 11/1/2006 rejected 11/13/2006

11/3/2006 get lower VOC



paint 3/14/2007



4. Request for Information

Request for First discussed Submitted by Returned by Notes

Information Contractor A/E



54 3/13/2007 R-7 quantity counts



5. Modifications

A. Supplemental Instructions

Supplemental First discussed SLCO Issued by A/E Returned by

Instructions approved Contractor



JI #14 - Automatic 2/12/2007

push plate, WIC

classroom door



JI #15 - Door 2/14/2007 2/23/2007 3/2/2007

hardware



B. CCDs

CCDs First discussed SLCO Issued by A/E Returned by

approved Contractor



C.O.A. #2 Misc. elec. and Feb. 6, 2007

LED sign



C. RFPs







2

RFPs First discussed SLCO Issued by A/E Returned by

approved Contractor







D. Change Orders

Change Order # Architect Contractor SLCO Notes







6. Pay Requests

Pay Request # Submitted by Certified by Signed by Notes

Contractor Architect SLCO



10 3/9/2007 3/14/2007



7. Action Items

1. Unresolved Items from Previous Meetings:

11-15-1 Issue: Ascent emailed the update overall construction schedule to Huina Ho with Substantial

Completion Date on April 17, 2007. Brandt Knowlton explained that due to the bad

weather and change orders which have put the Substantial Completion in April, but

he thought that March 30, 2007 is a workable date. Ascent will rework on the overall

construction schedule and make the Substantial Completion Date on March 30, 2007,

so South Main can move in April 2007.

Update 11-22-2006: The updated overall construction was emailed to Huina Ho. The revised

Substantial Completion Date is April 3, 2007.

Update 11-29-2006: Ryan Henrie indicated 15 days extension will put the Substantial Completion

Date on March 29, 2007. Ascent will work toward this date.

Update 12-6-2006: Brandt Knowlton confirmed that there are only one 24' and one 20'

TS8x20x1/2 beam are available. There are only 2 mills in the north America

can roll the TS8x20. The mill will roll every 90 days. The steel submittal were

ready on August 8. The TS8x20 will be in production on December 22. After

TS being fabricated in Albana, they will be shipped to the roll shop at

Portland, Oregon. After being rolled, they will be shipped to the Utah Steel

Ornamental for preparation and then delivered to South Main job site. Ascent

will check and follow the dates of progress of curved beams process. Ascent

will look into different scenarios of construction schedule. (i.e., to isolate the

curved beams areas, work in the closed areas not to slow down by the curved

beams).

Update 12-13-2006: Brandt Knowlton is waiting for a letter from the mill to confirm the date to

update the schedule. Brandt said that there is one production date prior to

December 22 but we’ll not make the date when the submittal was ready on

August 8. Ascent will follow the steel tube progress then will know how this

will impact the overall schedule. Kristy Cottrell needs to know the Substantial

Completion Date in January 2007 in order to schedule patients for April

month.

Update 12-20-2006: Steel mill is scheduled to roll the steel tubes on Dec. 22. The Substantial

Completion Date has been changed to April 27, 2007 on the updated

schedule. Ryan Henrie asked if the updated schedule includes overtime and

double crews. Although the steel tube availability problem, this will not

change the Contractual Substantial Date.





3

Update 1-3-2007: a. Albina Mill at Oregon will spend 450 hours to roll and shape the tube

steel beams; the rolled beams are in the process of being shaped. The

rolled beams are scheduled to arrive in Salt Lake on the third week of

January.

d. Ascent needs to update the overall construction schedule to reflect the

delay of rolled steel beams. Ascent will add the high metal roof to the

schedule and change the date of low membrane roof.

e. Ricardo Flores said that SLCO Real Estate is checking possibility extend

one more month lease for the existing South Main building.

Update 1-10-2007: Ascent prepared a revised overall schedule. The revised schedule has April

27, 2007 as the Substantial Completion date. The schedule is contingent on

the rolled steel tube beams.

Update 1-17-2007: Furniture coordination meeting was scheduled on Wednesday, 10:00 a.m.,

Jan. 24. South Main can only close one week and not see patients. Thus, we

need to confirm the date for South Main to move.

Update 1-24-2007: a. Artwork Coordination (Day Christensen, Foundry) -

1. Artworks are completed and ready to be installed.

2. The date will be before flooring is in place to install artwork.

Day Christensen and Foundry will follow up the date with Stan

Edwards.

3. A push plate is on the entry walkway block wall and interfere

with the artwork. Nancy McKendrick will coordinate with Day

Christensen to either split 8 panels or install 6 panels at entry

walkway and 2 panels inside of bldg. Otherwise, a push plate

on a post will be added to the opposite side of CMU wall.

b. Furniture Coordination (Carmelle Jensen of CCG and Source One

furniture installer) -

1. CCG ordered the furniture to avoid the price increase, so the

furniture are manufactured and stored in Salt Lake.

2. When the furniture arrive in a trailer, it’s everything and not

by areas.

3. CCG will start installing furniture on April 2. It will take 2

weeks to install and 1 week to do the punch list. CCG will

follow up the date with Stan Edwards.

c. Phone/Data Coordination (Mark Monson of Americom) -

1. 3/4"i conduit can fit 4 wires. SLCO’s standard is one voice

plug and one data plug for phone/data outlet shown on the

E3.1. South Main will mark up the needs for terminations, so

Americom can revise the bid and give to Dave Hatt.

2. Americom wants to start pulling cables when ceiling grids are

in, and no ceiling tiles.

d. South Main moving date - South Main can start moving at the end of

April. South Main can close existing facility and move the computers

and equipment on May 14, 2007.

Update 1-31-2007: Day Christensen wanted the 8-panel artwork connected and centered to the

entry walkway CMU wall. Thus, the push plate will need to be mounted on a

pole.

Update 2-14-2007: a. Push plate will be mounted on a galvanized post, a detail is needed.

b. South Main schedules patients’ appointments 3 months in advance,

and South Main can only block out one week. Thus, Kristy Cottrell

needs to confirm the moving days either the week of May 14 or 21.

Ascent will update the overall construction schedule when the upper

roof beams are installed.



4

Update 2-21-2007: a. Ascent updated the overall construction schedule based on the upper

roof beams will be completed on March 16. Building will be

substantial completed on May 18. South Main may start move-in on

May 21. Ryan Henrie will talk to Kristy Cottrell to see if South Main

can move-in a week after May 21.

b. Ryan Henrie indicated that CCG & Howell charged $900 for storing

furniture until the middle of April, since the Substantial Completion

Date was moved to May 21; SLCO may have additional charge again,

Ryan will find out from CCG & Howell.

c. Installation of cable/wire will remain un-changed. Furniture and

Artwork installation date will be moved accordingly.

Update 2-28-2007: a. South Main will start moving at May 25, Memorial Day week, and

open on June 4.

b. Ascent wrote a letter to request a 90-day extension for 8x20 steel tube

delay and bad weather. Ryan Henrie stated that the bad weather (6.5

days), change orders (14 days), and steel tube delay (24.5 day) will

add up to 45 days, and he did not see a 90-day extension. He’ll be ok

to prepare a Change Order for 45 days time extension to put the

Substantial Completion Date on May 18.

Update 3-7-2007: Steve Forbes, commissioning agent, indicated that building will need to be

purged two weeks after Substantial Completion on May 18. Thus it’s better for

South Main to move-in on June 4. Kristy Cottrell will free up the appointments

on the week of May 21 and 28.

Update 3-21-2007: South Main will start move-in on June 11. Ricardo Flores will give a letter to

SLCO Real Estate to explain the extension of existing building lease from May

to July.



12-20-3 Issue: The smooth form finishes (exposed aggregates and honey combs) on the concrete

archway columns are not acceptable. Cement plaster patches will not be accepted.

Update 1-3-2007: the installer wants to try to patch honey combs on the archway columns when

the weather is not too cold.

Update 1-10-2007: The concrete installer used adhesive as bonding agent to patch the

honeycombs. The team will wait until the concrete cure next week to review

the patched columns.

Update 1-17-2007: Nothing has been done due to the cold temperature. Ascent will get the patch

material info for review.

Update 2-28-2007: Architectural Concrete started concrete column patch and repair yesterday.

The patch and repair work look very patchy and is not acceptable at this

stage.

Update 3-7-2007: Architectural Concrete indicated that they should use concrete pump not

bucket to pour concrete columns, that caused the aggregates separation.

Architectural Concrete will try to fix the uneven concrete finish by Monday,

March 12.

Update 3-14-2007: Stan Edwards said that Architectural Concrete has worked on patching and

repairing columns last week, they need one more week to complete the

patching and repairing.

Update 3-21-2007: Concrete patch and repair for the second column from north looks good.

Ascent will provide a warranty to ensure the patch will stay bond to the

concrete.



2-28-3 Issue: a. JI#15 - Since we cannot lock the egress Door No. 53 and 57 (install key pad).

Kristy Cottrell may want to re-evaluate the key pad control from public to

employee sides.



5

b. Ascent prepared a C.O.P. for $3,883.59 for JI #15.

Update 3-7-2007: South Main and Ryan Henrie will review the COP.

Update 3-14-2007: Ryan Henrie indicated that the C.O.P. is acceptable, he’ll add one additional

day for C.O.. King Cobra key pads for Immunization Storage are electronic

hardware and are not returnable. Thus, these two key pads will need to be

given to SLVHD for other use.



3-14-1 Issue: The light fixtures at the high rolling roof area will be hung from unistrut spanned

between the horizontal beams as shown on details.



3-14-2 Issue: The South Main building is Type II-B Construction (non-combustible, non-rated

construction), no fire rated walls are required. The building is setback 10' from the

north property line. Thus, the north wall is a non-rated wall and can have windows.

The CMU and brick wall are 2-4 hour fire-rated and don’t need to have the gypsum

board to be the fire-rated wall. The walls shall be constructed per Wall Types shown

on A1.1.



3-14-3 Issue: The rust metal roof deck at the Check-In area will need to be cleaned and repaired

per section 05310.3.5.



2. New Items:

3-21-1 Issue: a. Electrician wants to use MC cables for the light fixtures at the open area to

minimize the conduit bends.

b. Electrician asked if we need the 1 ½"i conduit for projector screen.

c. Electrician asked if the photo sensor at the open areas can be mounted to the

walls in lieu of ceilings.



3-21-2 Issue: Ricardo Flores asked Ascent to brush paint and not to spray paint for the exterior

steel.



3-21-3 Issue: Steve Forbes, commissioning agent, asked for the following items:

a. Training Syllabus/Outlines needs to be submitted for review.

b. The status of O & M Manual.

c. Proposal for equipment start up.



8. Miscellaneous Items:



9. Next Job Site Meeting: Wednesday, 9:30 a.m., March 28, 2007



MEETING MINUTES BY:Huina Ho









6



Related docs
Other docs by benben zhou
Shopping Shopping for Cosmetics8
Views: 245  |  Downloads: 0
Rejigging the Elephant Dance
Views: 0  |  Downloads: 0
Dell Computer Corp.Micron Electr
Views: 4  |  Downloads: 0
For immediate release moisture
Views: 9  |  Downloads: 0
Dear Colleague
Views: 5  |  Downloads: 0
Seasonal Novel H N Flu A Guide for Parents
Views: 1  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!