CONTINGENCY
Document Sample


CONTINGENCY
AUTHORIZATION
PROJECT: River View High School CONTINGENCY AUTHORIZATION NO.: 09
Kennewick, Washington
OWNER: Finley School District No. 53 DATE OF ISSUANCE: Dec. 10, 2001
TO: Tim Burns ARCHITECT: Design West
KOP Construction
ARCH. PROJECT NO: 9930
The Work, the Contract Documents are hereby amended as described below. Proceed with this work promptly.
This change is approved with no change in the Contract Amount or Contract Time. This change affects the
Contingency Balance Only.
1. Provide additional concrete sidewalk; remove and replace asphalt
patch as indicated in CCA 9/8/01-2. (PR #68) $ 2,560.00
2. Remove two center beams below skylight in Commons as indicated
in CCA 9/8/01-4. (PR #70) $ 903.00
3. Remove abandoned drywell at new flagpole location as indicated in
CCA 9/8/01-5. (PR #71). $ 372.00
4. Provide threshold at Door 405A as indicated in CCA 9/24/01-1 (PR #78). $ 85.00
5. Install 1-hour rated gypsum board ceiling system in rooms Biology 210,
Workroom 212, and Lab 214 as directed in CCA 3/6/01-1.
Provide one additional smoke/fire damper at 36x24 return air in
Biology 210. (PR #53) $ 15,143.00
6. Relocate parking lot light standard in rear lot as directed in
CCA 7/25/01-2. (PR #58) $ 691.00
7. Remove and replace asphalt at NW corner of Gymnasium damaged
by district athletic boosters as indicated in CCA 9/12/01-1. (PR #73) $ 199.00
8. Provide threshold and door sweep at Door 405B as indicated in
CCA 9/12/01-2. (PR #74) $ 355.00
9. Reroute existing conduit in the Gymnasium and Mezzanine as directed
in CCA 4/11/01-1. (PR #79) $ 2,007.00
10. Provide three new exit lights as indicated in CCA 3/13/01-7. (PR #86) $ 1,057.00
TOTAL $ 23,372.00
C:\Docstoc\Working\pdf\53e1a68d-da2a-46de-95ac-666a7a8e573e.DOC
Contingency Authorization No. 09; River View High School
CONTINGENCY SUMMARY:
Starting Balance $ 100,000.00
Contingency Authorization #1 $( 15,120.00)
Contingency Authorization #2 $( 25,589.00)
Contingency Authorization #3 $( 5,036.00)
Contingency Authorization #4 $( 11,321.00)
Contingency Authorization #5 $( 12,030.00)
Contingency Authorization #6 $( 8,768.00)
Contingency Authorization #7 $ 27,042.20
Contingency Authorization #8 $( 3,476.00)
Contingency Authorization #9 $( 23,372.00)
BALANCE $ 22,330.20
ARCHITECT: CONTRACTOR: OWNER:
Design West KOP Construction Finley School District No. 53
9 Twelfth Ave. South 1602 S Chestnut St. 224606 E Game Farm Rd.
Nampa, ID 83651 Spokane, WA 99244 Kennewick, WA 99337
By: By: By:
Date: Date: Date:
C:\Docstoc\Working\pdf\53e1a68d-da2a-46de-95ac-666a7a8e573e.DOC
Get documents about "