26/03/09
City Development Directorate
Regeneration Services
Operational Plan 2009/10
April 2009
1
CONTENTS PAGE
economic downturn, and ensuring that the benefits
are felt in even the most deprived neighbourhoods
Summary of service objectives 3
Service Objective 5: Identify, secure and manage
58
funding resources for regeneration
Introduction and purpose 10
Service Objective 6: Continually seek to improve
63
our services and develop our workforce
About the service 12
Value for Money self Assessment 14
Key strategic issues to be addressed in 2009/10 17
Cross cutting themes and other key Issues 20
Resources and improvements to deliver plan 25
Service Objective 1: Influence, lead and support
strategic regeneration, working with partners 29
locally, sub-regionally, regionally and nationally
Service Objective 2: Contribute to the city centre's
35
transformation
Service Objective 3: Transform Coventry's physical
environment in an environmentally sustainable way 42
to benefit all of the city
Service Objective 4: Improve Coventry's economy
through enterprise, skills and employment 48
opportunities, minimising the impact of the
2
Summary of Regeneration Services Objectives
SCS Theme/ SCS Priority/
Service Objective Cabinet Portfolio Priority
Management Theme Management Objective
A prosperous Attract inward investing businesses to open in the Transform Coventry through a 15-20 year
1. Influence, lead and
Coventry with a good city, at least one of these each year should be a sustainable growth programme
support strategic
choice of jobs and major new investment
regeneration, working Focus growth on transforming the city
business
with partners locally, Increase entrepreneurship by expanding and centre to create a vibrant and successful
opportunities for all
sub-regionally, developing the Local Enterprise Growth Initiative sub-regional centre for Coventry and
the city's residents
regionally, nationally model Warwickshire
3
and internationally Create new jobs for local people by encouraging Create change and develop sustainable
the growth of businesses in the city communities through multi-faceted urban
regeneration projects, including New Deal
Reduce the number of people claiming JobSeekers
for Communities, The Swanswell
Allowance and other worklessness benefits
Initiative, Canley Regeneration
Reduce the number of school leavers who are not
Maximise property assets, income and
in education, employment or training (NEETs)
external funding to finance corporate
Increase the proportion of school leavers who priorities, specifically the growth
complete a first year of further education, programme
employment or training (EETs) and continue into a
Champion the city and create
second year
employment, enterprise and investment
Increase achievement of Level 2 qualifications and opportunities for everyone
above
Develop a programme to help retain new
graduates within the city by providing appropriate
jobs and housing
Continue the transformation and extension of the
city centre
A good choice of Planning to achieve a balance of housing type –
housing to meet the mixed developments/ communities
needs and
Ensure the planned growth of the city's housing
aspirations of the
stock contributes towards sustainability, meets
people of Coventry
future housing targets and provides affordable
homes for local people
A creative, active and Make the city centre a vibrant cultural centre and
vibrant Coventry connect the city's culture to local neighbourhoods
A more equal Improve community engagement and meet local
Coventry with and national government requirements to involve
cohesive local communities in partnership working and
communities and decision making
neighbourhoods
Ensure that equality of opportunity and community
4
cohesion are embedded throughout Coventry's
Sustainable Community Strategy and the Local
Area Agreement
Improve neighbourhood planning to involve local
communities in addressing local issues and
improve local service delivery
Develop a better understanding of the changing
demographics and future needs of people in
Coventry, including the effects of migration into and
out of the city on local communities and the
delivery of services
2. Contribute to the A prosperous Attract inward investing businesses to open in the
Transform Coventry through a 15-20 year
city centre's Coventry with a good city, at least one of these each year should be a
sustainable growth programme
transformation choice of jobs and major new investment
programme business Focus growth on transforming the city
Create new jobs for local people by encouraging
opportunities for all centre to create a vibrant and successful
the growth of businesses in the city
the city's residents sub-regional centre for Coventry and
Develop a programme to help retain new
Warwickshire
graduates within the city by providing appropriate
jobs and housing Create change and develop sustainable
Continue the transformation and extension of the communities through multi-faceted urban
city centre regeneration projects, including New Deal
for Communities, The Swanswell
A good choice of Planning to achieve a balance of housing type – Initiative, Canley Regeneration
housing to meet the mixed developments/ communities
needs and Maximise property assets, income and
Ensure the planned growth of the city's housing external funding to finance corporate
aspirations of the
stock contributes towards sustainability, meets priorities, specifically the growth
people of Coventry
future housing targets and provides affordable programme
homes for local people
A more equal Improve community engagement and meet local Champion the city and create
Coventry with and national government requirements to involve employment, enterprise and investment
cohesive local communities in partnership working and opportunities for everyone
communities and decision making
5
neighbourhoods Ensure that equality of opportunity and community
cohesion are embedded throughout Coventry's
Sustainable Community Strategy and the Local
Area Agreement
Improve neighbourhood planning to involve local
communities in addressing local issues and
improve local service delivery
Develop a better understanding of the changing
demographics and future needs of people in
Coventry, including the effects of migration into and
out of the city on local communities and the
delivery of services
3. Transform A prosperous Develop a programme to help retain new
Transform Coventry through a 15-20 year
Coventry's physical Coventry with a good graduates within the city by providing appropriate
sustainable growth programme
environment in an choice of jobs and jobs and housing
environmentally business
Continue the transformation and extension of the Focus growth on transforming the city
sustainable way to opportunities for all centre to create a vibrant and successful
city centre
benefit all the city the city's residents sub-regional centre for Coventry and
Warwickshire
Create change and develop sustainable
communities through multi-faceted urban
regeneration projects, including New Deal
for Communities, The Swanswell
Initiative, Canley Regeneration
Maximise property assets, income and
external funding to finance corporate
priorities, specifically the growth
programme
Champion the city and create
employment, enterprise and investment
opportunities for everyone
6
A more equal Improve community engagement and meet local
Coventry with and national government requirements to involve
cohesive local communities in partnership working and
communities and decision making
neighbourhoods
Ensure that equality of opportunity and community
cohesion are embedded throughout Coventry's
Sustainable Community Strategy and the Local
Area Agreement
Improve neighbourhood planning to involve local
communities in addressing local issues and
improve local service delivery
Develop a better understanding of the changing
demographics and future needs of people in
Coventry, including the effects of migration into and
out of the city on local communities and the
delivery of services
4. Improve Coventry's A prosperous Attract inward investing businesses to open in the Transform Coventry through a 15-20 year
economy through Coventry with a good city, at least one of these each year should be a sustainable growth programme
enterprise, skills and choice of jobs and major new investment
Focus growth on transforming the city
employment business
Increase entrepreneurship by expanding and centre to create a vibrant and successful
opportunities, opportunities for all
developing the Local Enterprise Growth Initiative sub-regional centre for Coventry and
minimising the impact the city's residents
model Warwickshire
of the economic
downturn and Create new jobs for local people by encouraging Create change and develop sustainable
ensuring that the the growth of businesses in the city communities through multi-faceted urban
benefits are felt in regeneration projects, including New Deal
Reduce the number of people claiming JobSeekers
even the most for Communities, The Swanswell
Allowance and other worklessness benefits
deprived Initiative, Canley Regeneration
neighbourhoods Reduce the number of school leavers who are not
Maximise property assets, income and
in education, employment or training (NEETs)
external funding to finance corporate
Increase the proportion of school leavers who priorities, specifically the growth
complete a first year of further education, programme
employment or training (EETs) and continue into a
7
second year Champion the city and create
employment, enterprise and investment
Increase achievement of Level 2 qualifications and
opportunities for everyone
above
Develop a programme to help retain new
graduates within the city by providing appropriate
jobs and housing
Continue the transformation and extension of the
city centre
A more equal Improve community engagement and meet local
Coventry with and national government requirements to involve
cohesive local communities in partnership working and
communities and decision making
neighbourhoods
Ensure that equality of opportunity and community
cohesion are embedded throughout Coventry's
Sustainable Community Strategy and the Local
Area Agreement
Improve neighbourhood planning to involve local
communities in addressing local issues and
improve local service delivery
Develop a better understanding of the changing
demographics and future needs of people in
Coventry, including the effects of migration into and
out of the city on local communities and the
delivery of services
5. Identify, secure and Money Ensure sound management of the Council's Transform Coventry through a 15-20 year
manage funding financial resources sustainable growth programme
resources for
Deliver the Council's Medium Term Financial Focus growth on transforming the city
regeneration
Strategy to meet corporate objectives and balance centre to create a vibrant and successful
the budget sub-regional centre for Coventry and
Warwickshire
Maximise resources
Create change and develop sustainable
8
communities through multi-faceted urban
regeneration projects, including New Deal
for Communities, The Swanswell
Initiative, Canley Regeneration
Maximise property assets, income and
external funding to finance corporate
priorities, specifically the growth
programme
Champion the city and create
employment, enterprise and investment
opportunities for everyone
6. Continually seek to A more equal Improve community engagement and meet local Transform Coventry through a 15-20 year
improve our services Coventry with and national government requirements to involve sustainable growth programme
and develop the cohesive local communities in partnership working and
Focus growth on transforming the city
workforce communities and decision making
centre to create a vibrant and successful
neighbourhoods
Ensure that equality of opportunity and community sub-regional centre for Coventry and
cohesion are embedded throughout Coventry's Warwickshire
Sustainable Community Strategy and the Local
Create change and develop sustainable
Area Agreement
communities through multi-faceted urban
Improve neighbourhood planning to involve local regeneration projects, including New Deal
communities in addressing local issues and for Communities, The Swanswell
improve local service delivery Initiative, Canley Regeneration
Develop a better understanding of the changing Maximise property assets, income and
demographics and future needs of people in external funding to finance corporate
Coventry, including the effects of migration into and priorities, specifically the growth
out of the city on local communities and the programme
delivery of services
Champion the city and create
Improving the way Continue to improve the quality of our services employment, enterprise and investment
we work and deliver opportunities for everyone
Continue to improve access to services
value for money
Continue to improve the efficiency and
9
effectiveness of services
People Develop the skills, competences and motivation of
our workforce
Build a workforce that is representative of the local
community
Maintain the health, safety and welfare of our
workforce
Improve attendance at work
Introduction and purpose
Purpose of The Regeneration Services Operational Plan (RSOP) provides a strategic overview to the key objectives and actions that will be
the Plan delivered in the 2009/10 financial year.
The RSOP reflects the priorities agreed in the Sustainable Communities Strategy/ Coventry City Council Corporate Plan
particularly around the theme of 'A prosperous Coventry with a good choice of jobs and business opportunities for all the city's
residents.' The plan has also been developed to support the delivery of the City Development Cabinet Portfolio Plan.
The RSOP also delivers Coventry City Council's commitments in the Coventry Economic Development Strategy 2008-11.
The delivery of short term priorities to meet the aims of the Sustainable Communities Strategy is through the Coventry Local
Area Agreement (LAA). The RSOP contributes to the delivery of targets within the LAA through the following LAA Delivery Plans:
NI 152 – Working age people on out of work benefits
NI 165 – Proportion of population aged 19-64 for males and 19-59 for females qualified to at least Level 4 or higher
NI 171 New business registration (planned for implementation in 2010).
Regeneration Services also supports the delivery of the following National Indicators through the Economy, Learning, Skills and
Employment Theme Group of Coventry Partnership.
NI 117 – 16 to 18 year olds who are not in education, training or employment (NEET)
NI 79 – Percentage of young people attaining Level 2 by age 19 in a Local Authority Area
NI 164 – Proportion of population aged 19-64 for males and 19-59 for females qualified to at least Level 3 or higher
10
Introduction and purpose
Regeneration Services will be incorporating the NI4 '% of people who feel they can influence decisions in their locality' into our
work. We will also evidence how we inform, consult and involve public in commissioning and decision making about our services,
as part of the new duty being introduced to local authorities in April 2009.
Across Regeneration Services, Team Leaders and Managers have been meeting with their teams to discuss the challenges
facing us and the key tasks for next year. This has led to Team Leaders and Managers being able to agree actions for each of
the Division's objectives relevant to their area of work.
The Employment & Enterprise Review being carried out within Regeneration Services will see whole aspects of service delivery
redesigned to meet the identified needs of our customers. This ongoing review will lead to further versions of this plan being
required to reflect any changes that take place.
Part of the Employment & Enterprise Review will also be identifying and implementing improvements to the Division's Support
Services. A Service Improvement Group (SIG4) has been set up to take this priority forward. Areas that the SIG4 are focusing on
include:
Service Co-ordination
Policy
Evaluation
Performance Management
Partnerships
Communications
External Funding
Funding Assurance
The Operational Plan is monitored and reported on quarterly at Regeneration Services Management Team meetings. The
quarterly report is also disseminated to all Regeneration Services Team Leaders. The Plan is the basis for the preparation of
Team Action Plans, which set out detailed actions for individual staff. We are currently reviewing our performance management
culture to identify areas of continuous service improvement.
11
About the service
Services The service areas within Regeneration Services Division:
covered by
Development Projects
the plan
Undertaking and leading new development and environmental enhancement projects on behalf of the City Council,
preserving the City's heritage and conservation, archaeology and promoting urban design and landscape design principles to
improve the quality of the environment
o Property Development
o Conservation and Archaeology
o Environmental Regeneration
o Urban and Landscape Design
Employment and Community Regeneration
Working with individuals, local people and local companies, attracting new businesses, supporting investment an d renewal in
major regeneration project areas
o Community Employment & Skills
o Client Support Unit
o Neighbourhood Renewal
o Investment & Business Services
Project Champions
Bringing forward, "Championing" and delivering major regeneration programmes and projects particularly in partnership with
external stakeholders
o Swanswell – as part of the wider City Centre Programme
o Canley
o NDC Masterplan
Regeneration Strategy & Resources
Creating a strategic approach to the organisation and delivery of regeneration, economic development and business support
across the city, sub-region and city region
o Programme Management
o External Funding Support including European, National & Regional funds
o Policy and Performance
o International Strategy
o LEGI Partnership Programme Co-ordination
12
About the service
New Deal for Communities
Community-led partnership to regenerate the Wood End, Henley Green, Manor Farm and Deedmore areas of the city
o New Deal for Communities (NDC)
Cabinet CABINET MEMBER
Members, Councillor Gary Ridley, Cabinet Member City Development (as at March 2009)
Management DIRECTOR – City Development Directorate/ Management Board Member
Board John McGuigan
Member Head
Of Service DEPUTY DIRECTOR – City Development Directorate/ Management Board Member
Martin Yardley
HEAD OF SERVICE
Carl Pearson, Head of Regeneration Services
SERVICE MANAGERS
Tony Auty Development Projects Manager
Trevor Howard Employment & Community Regeneration Manager
Duncan Elliott Project Champion (Swanswell)
Tim Jones Project Champion (Canley), NDC
Paula Deas, Rebecca Young Regeneration Strategy & Resources Manager (Job-share)
Afzal Hussain Director, New Deal for Communities (NDC)
13
Value for Money Self Assessment
Baseline Data - Last year Employment and Enterprise was the subject of a Value for Money review.
What information LEGI Evaluation work in has provided a range of baseline data on cost per output and value for money for several
do you already projects within the programme. This has included some evaluation of value for money compared with both
have about the comparable providers in the city and nationally, where possible.
value for money Regeneration and development projects are subject to a project review and evaluation on completion.
being achieved by
your main service
areas?
Gap Analysis Core Versus External Funding for Regeneration Services
Fund Year Core Funded Externally Funded Total Cost %age core %age external Cost per person external funding per person
PK 2007/2008 1,377,449.77 665,110.18 2,042,559.95 67 33 £4.56 £2.20
PF 2007/2008 240,460.75 5,552,436.37 5,792,897.12 4 96 £0.80 £18.39
PB 2007/2008 3,379,460.09 8,729,725.35 12,109,185.44 28 72 £11.19 £28.91
Total 2007/2008 4,997,370.61 14,947,271.90 19,944,642.51 33 67 £16.55 £49.49
PK 2008/2009 1,552,759.64 227,303.00 1,780,062.64 87 13 £5.14 £0.75
PF 2008/2009 342,816.00 5,339,504.00 5,682,320.00 6 94 £1.14 £17.68
PB 2008/2009 3,119,381.08 7,165,901.00 10,285,282.08 30 70 £10.33 £23.73
Total 2008/2009 5,014,956.72 12,732,708.00 17,747,664.72 41 59 £16.61 £42.16
PK 2009/2010 1537699 125000 1,662,699.00 92 8 £5.09 £0.41
PF 2009/2010 0 5628432 5,628,432.00 0 100 £0.00 £18.64
PB 2009/2010 2668309 4106627 6,774,936.00 39 61 £8.84 £13.60
Total 2009/2010 4,206,008.00 9,860,059.00 14,066,067.00 44 56 £13.93 £32.65
For April 2009/10 the percentage of core funding for Regeneration Services is 44% compared to 56% being funded
through external funding.
LEGI Programme cost per output values where available have been found to compare favourably to appropriate
benchmarks of providers across the city. However, the current review of employment and enterprise services is
ensuring that value for money is a key driver in how services are redesigned moving forward. It is recognised that
staffing is a main cost driver for this area and so redesign is focusing on ensuring that job roles are fit for purpose
and that service delivery is designed to be 'lean'.
14
Planned actions in Development Projects have had a budget cut of £25k pa imposed for 2008/09 and 2009/10, which is being achieved
2009/10? by a combination of reducing staffing levels and cutting service budgets, on top of the annual efficiency savings
targets. Investment and Business have had a cut of 325k for 2008/09 and £35k for 2009/10. The Community
Employment and Skills team have a cut of £50k for 2009/10.
Social Return on Investment has been utilised to understand fully the value for money and impact of spending in two
projects of the LEGI programme. In 2009/10 it is planned that Social Return on Investment will be embedded into
several employment and enterprise services. This provides comprehensive understanding of the value and impact of
these services to the state, individuals and a variety of organisations across the city, such as the PCT.
Broad reaching service redesign is focusing on streamlining and refocusing service delivery, rationalisation of
delivery partners and maximising value for money across employment and enterprise services.
15
Base Budget Reviews
Regeneration Summary of PPR Savings 2008/09 and 2009/10
PPR Savings identified from 2007/08 exercise
PPR
PPR Savings
Savings Action
Action 2009/10
2008/09 £ £
Development Projects -25,000 -25,000
Business Investment Team -25,000 -35,000
Employment -50,000
NDC Masterplanning (Project Management) 80,000
-50,000 -30,000
PPR Savings identified from 2008/09 exercise
PPR PPR
Savings PPR Savings to
Action Savings to be actioned
2009/10 be actioned 11/12
£ 10/11 £ £
Client Support Unit -23,000 -48,000 -48,000
Groundwork -48,000 -48,000 -48,000
Clothing Centre -43,000 -82,000 -82,000
CVOne -150,000 -150,000 -150,000
Car Parking Fee Increase -380,000 -380,000 -380,000
Third Party Payment 3% efficiency Savings
Credit Union -1,438
Support in to Employment -1,038
Employment and Skills Team -902
-646,476 -708,000 -708,000
16
Planned It is expected that employment and enterprise services will be more effectively delivered through simplified and
outcomes/benefits streamlined service model, supported by lean and continuously improving support services. This will be delivered
despite LEGI funding being reduced by £1.3m for 2009/10.
Development Projects has a £25k savings target
How will these As part of the Employment and Enterprise Review a subgroup has been set up to identify and implement improvements
service to the Division's Support Services. Known as Service Improvement Group (SIG4) the areas that this group are focusing
improvements be on include:
measured? Service Co-ordination
Policy
Evaluation
Performance Management
Partnerships
Communications
External Funding
Funding Assurance
In measuring service improvements, a working group is looking at performance management in detail. This includes
reviewing the performance management systems in place e.g. how we collect management information and the need to
improve the speed and quality of information. It encompasses work around Social Return on Investment (SROI),
including the possible implementation of a system that will enable the Division to measure softer regeneration outcomes,
such as distance travelled. The working group is also reviewing the performance management culture within the
Division, and how managers use performance management information with their teams e.g. an Operational Plan Survey
has been carried out and the results are informing how we will improve the use of the Operational Plan within the
Division.
Key strategic issues to be addressed in 2009/10
Reference to service
Key strategic issue objective, action(s) and
success criteria in plan
17
The economic downturn and its adverse impact on the property market is likely to continue throughout the Objectives 2,3,4 & 5
year. This will inevitably mean that developers and investors will be much more cautious about progressing
projects and purchasing sites
The reduced level of expenditure on public services will impact upon Regeneration Services. This will in turn Objectives 1,2,3,4,5 & 6
impact upon the availability of jobs and on unemployment figures. Strategically our work will be more
reactively driven to deal with immediate issues in the economy, and the focus will be upon stabilising
Coventry's economy within the economic recession. At the same time we need ensure that the City is
positioned to take advantages of opportunities during the recession and also be ready to respond when
economic recovery happens.
Multi-Area Agreements - At present we are cooperating on a multi-area agreement on Employment and Skills Objective 1
for the City Region. This will only be signed off if we gain level 3 powers over DWP funding in the City Region
and section 4 powers over DIUS funding. We will be signing up to employment and skills targets for the City
region, however, these will be in line with local targets. We will need to review local targets in the light of a
sign off to this. If there is an acceptance of this agreement the City Strategy Management board will be
subsumed within it and they will be run together. This should streamline our approach to Worklessness and
skills in the City Region this would also be part of the City Region Pilot.
Pilot City Region Status - What we seek from Pilot City-Region status is the ability to achieve a step change Objective 1
in the quality and quantity of the infrastructure that will enable us to achieve this goal – by stimulating
investment, growth, jobs and competitiveness. We want to achieve this step change in infrastructure by
having:
1. the power to co-ordinate and align the existing investment made in our City-Region by ourselves,
Government departments, and national and regional agencies;
2. the power to raise additional resources, particularly for capital investment in infrastructure, through
innovative funding mechanisms;
3. the power for member local authorities to pool resources and risk, and to invest anywhere in the City-
Region.
Regeneration Services' investment and business strategy will focus on strategic business sectors that are Objectives 2, 3 & 4
vital to employment, prosperity and reputation of the city. These sectors will be targeted to attract investment
to the city and we will work with AWM and other local partners to develop sector programmes and flagship
projects to make the city even more attractive for investment. We will also work collaboratively with
businesses in these sectors to support their growth. Targeted sectors include retail, public sector relocations,
18
office and professional, automotive, aerospace, creative and design, medical and environmental.
Strategic Housing Investment and sustainability - The merger of the Housing Corporation and English Objectives 1, 2 & 3
Partnerships into the Homes and Communities Agency (HCA) will require a change in how Housing
Investment is allocated. Tim Jones is leading on discussions with HCA to develop a Strategic Partnership with
HCA for Housing Investment that includes for Investment and Grant allocations linked to Growth, Affordability
and Regeneration. This fits in with the City's Core Strategy for growth.
HCA are also now leading on sustainability funding for Growth related projects and programmes. Investment
proposals are lodged with HCA for investment in Canley and NDC to improve the sustainability of those
projects. In addition Advantage West Midlands are also looking to invest in sustainable/Climate Change
developments. This links into the City's Strategy for Climate Change.
Securing the progression of the development of the City Centre during the current economic recession Objectives 1, 2 & 4
Growth Point – housing numbers, traffic infrastructure Objectives 1, 2, 3, 4, 5
The Regeneration Services Division has been carrying out an Employment and Enterprise (E&E) Review, Objectives 1, 4, 5 & 6
looking at the redesign of delivery and services in this area. The purpose of the review is to ensure that we
keep abreast of developments particularly in the fast paced changing economic climate. We will be
evaluating the way we deliver, manage, and source our services. Integral to this will be ensuring that the
service is clear. Alongside this the service needs to be clear about its role in the field of Employment and
Enterprise alongside that of our partners i.e. JobCentre Plus, LSC, Chamber, Third Sector.
Four service improvement groups have been established and are responsible for creating and delivering
action plans, specifically focusing on:
o Employer Engagement, led by Geoff Hyde and Stan Aldridge
o Individual Clients/Client Journey's, led by Priti Bharadwa and Trevor Howard
o Business, Investment and Enterprise, led by Andy Williams and Stan Aldridge
o Support Services (to include service coordination, policy and partnerships, performance
management, communications, external funding, funding assurance and evaluation) led by
Rebecca Young and Trevor Howard
19
This work is overseen by the Programme Board which consists of Carl Pearson, Trevor Howard, Rebecca
Young and Paula Deas. Priti Bharadwa provides support to the Programme Board in moving
recommendations forward.
Development Projects: Three actions came from the Equality Impact Assessment undertaken in 2008/09 Objectives 2,3 & 6
Managing the impact on service delivery of the PPR cuts (5 posts across the City Development Directorate), Objectives 1,2,3,4,5,& 6
the details of which are still to be confirmed.
Managing the outcome of Senior Management Team's (SMT) deliberations on the Directorate structure. Objectives 1,2,3,4,5,6
Cross cutting themes and other key issues
What is planned for 2009/10? Action reference
Equalities and Community Equality actions can be
The work of Regeneration Services is built around delivering the following
Cohesion found in the following
themes of the Sustainable Community Strategy:
service objectives:
A prosperous Coventry with a good choice of jobs and business opportunities SO2 - Contribute to
for all the city's residents, the city centre's
A good choice of housing to meet the needs and aspirations of people of transformation
Coventry program
A creative, active and vibrant Coventry SO3 – Transform
A more equal Coventry with cohesive communities and neighbourhoods. Coventry's physical
environment in an
Inevitably this means our work is wide ranging encompassing jobs, poverty, environmentally
neighbourhood renewal, business and investment. Therefore, equalities is sustainable way to
fundamental to everything we do. benefit all the city
Part of our work involves working closely with Communities. Engaging and SO 4 – Improve
20
consulting them is vital and plays a major part in shaping and redesigning our Coventry's economy
services as well as the information received from Equality Impact Assessments. through enterprise,
skill and
For example, the review of the consultation undertaken on the City Centre employment
Masterplanning exercise shows it managed to capture a representative cross of opportunities
people. Comments from non white British groups were on the low side and
consideration needs to be given as to how to engage more effectively in the
future.
Following the Employment and Enterprise review of our services, we will
continue developing our partnership working across organisations and agencies
to address the social inclusion and equality agenda.
We also, currently work with the Equalities and Cohesion Theme Group of
Coventry Partnership, specifically to identify Equalities and Cohesion issues
which will, this year, contribute towards the development of the new Equalities
and Cohesion Strategy for Coventry City Council.
Furthermore, each year, Regeneration Services is required to undertake an
Equality Impact Assessment on all our services. Last year, a total of two
assessments were undertaken, involving the Investment & Business Team and
Development Projects team and produced a number of outcomes which have
been incorporated in this years plan.
For example, the Equalities Impact Assessment undertaken in respect of
development project activities produced three main actions which are listed
below:
Ensure post scheme analysis/ evaluations are undertaken on projects e.g.
Far Gosford Street
Ensure ethnic minority data is collected and analysed for all consultation
events
Investigate more effective methods of reaching certain groups e.g. young
people 16-24 and the new European communities
This year, the key actions and activities relating to equalities and community
21
cohesion and the common themes arising from Equality Impact Assessments
are listed below:
Ensure ethnic minority data is collected and analysed
Ensure post scheme analysis/evaluations are undertaken on all projects
Investigate more effective methods of reaching certain groups such as
young people and the new European communities
Investigate and encourage service users to complete ethnic monitoring
forms
This year, we plan to undertake assessments in the following service areas:
The Client Support Unit
The External Funding Helpdesk
The outcome from those assessments will be used to inform service delivery for
2010-11.
22
Sustainability The council wants to improve Coventry's environment by making a positive Actions can be found in
contribution and tackling climate change. Part of what we do is about ensuring the following service
that all regeneration is sustainable and contributes to the aims of tackling climate objectives:
change. Some of the ways in which we do this is by:
SO3 – Transform
Protecting the city's heritage and natural resources Coventry's physical
environment in an
Maximising our resources to manage green spaces, natural habitats, environmentally
public art and other environmental improvement assets sustainable way to
Last year, we also began work on developing a strategy and action plan for the benefit all the city
Environmental sector. This year, we will continue to further develop that strategy
and in doing so, will enable us to attract future investment.
Within Regeneration Services there is very little we can do if it does not meet the
sustainability test/ criteria. For example the City Centre Transformation is
predicated on addressing significant market failures in the city centre. The
funding invested by AWM will help improve the cultural, leisure and business
offer in Coventry City Centre and stimulate investment in Coventry. This will in
turn create the employment required to sustain the housing growth targets that
have been set for Coventry in the Regional Spatial Strategy. These actions aim
to enable Coventry become a vibrant and sustainable city for the 21st Century.
Duty to Inform, Consult and As previously mentioned (See Equalities and Community Cohesion section), our Actions involving
Involve work involves working closely with local Communities, ordinary Members of the consultations can be
Public, Businesses, Partners and Stakeholders; obtaining their comments is vital found in the following
and plays a crucial part in shaping and redesigning our services. service objectives:
SO2 - Contribute to
We regularly consult on our physical major Regeneration projects such as the
the city centre's
Canley Regeneration Scheme and Swanswell Regeneration Project. Further
transformation
consultations are also undertaken on areas such as the City Centre Masterplan,
program
Far Gosford Street and new service delivery programmes such as Local
Economic Growth Initiative (LEGI) and the recent Deprived Area Fund project. SO3 – Transform
Analysis of the data shows that we engage widely with members of the Coventry's physical
community from elderly persons to young people such as school children and environment in an
where a specific need has been identified as a result of consultation, we have environmentally
redesigned our services accordingly; However and especially with the City sustainable way to
Centre Masterplan, there is still further work to be done and we recognise that benefit all the city
23
we will need to engage more effectively with Black and Minority Ethnic groups,
SO 6 – Continually
young people and New European communities.
seek to improve our
services and develop
During the coming year, we will:
our workforce
Continue involvement in developing Coventry City Council's "Inform, Consult,
and Involve" Strategy
Continue our involvement in developing the LAA Delivery Plan for the
National Performance Indicator No: 4 on the " % of people who feel they can
influence decisions in their locality"
Continue consulting but will seek to engage more effectively with Black and
Minority Ethnic Groups, Young People and New European communities
Widen Public involvement in our major regeneration projects as well as within
service delivery
Continue consultation activities around the projects the Development
Projects team is facilitating and implementing. Stakeholders, residents and
local businesses are consulted in the design and planning stages to ensure
their requirements are taken into account.
Implement Community Involvement and Communications Plan at Swanswell
to widen public involvement
Sustain public involvement in Canley Regeneration Programme and the NDC
programme.
Customer Services Throughout the year, customer feedback is received via a variety of methods Actions involving
such as consultations, surveys, customer impact reviews, commissioned surveys consultations can be
and focus groups. Employee briefings are also held with staff to further capture found in the following
information. This feedback is used to inform the overall strategy and help to service objectives:
shape service delivery.
SO2 - Contribute to
the city centre's
We recognise that Customer feedback is crucial and therefore work is ongoing to
transformation
capture feedback throughout the year.
program
Parts of our service (the Investment and Business Team) have achieved the ISO SO3 – Transform
9001 Quality Accreditation Standard, which is about knowing and understanding Coventry's physical
customer needs including obtaining regular feedback. To complement this work environment in an
and for the year ahead, our focus for the rest of the division will be to build on the environmentally
24
review of our Employment and Enterprise work and continue developing sustainable way to
improvements to our service delivery. benefit all the city
SO 6 – Continually
During the coming year, we will:
seek to improve our
services and
Continue to implement the actions from the review of our Employment and
develop our
Enterprise Services
workforce
Continue to listen to our customers and analyse feedback to inform service
deliver
Maintain the ISO 9001 quality accreditation for the Investment and Business
team
Resources and improvements to deliver the plan
Regeneration Services is affected by the context of the overall budgetary position in Coventry City
Money
Council.
Narrative to describe the position and potential to be secured – not guaranteed – lots of opportunity. City
Centre £40 million, NDC £15 m, ERDF, Other bids
Service specific constraints include the inability to be able to fill vacant positions or recruit to new
positions.
Swanswell Learning Quarter CPO – three outstanding compensation claims. Current worst case
estimates indicate possible £1.1m budget overspend. Timing of claims and outcome may not be known
for several years. Cases being overseen by Duncan Elliott. On Corporate Risk Register: Finance Special
Projects part of project team.
Improving the way we work See VFM Section
and deliver Value for Money
The Employment & Enterprise Review will fundamentally redesign service delivery for Employment &
Enterprise elements of Regeneration Services.
For key major physical schemes there is a dedicated corporate and directorate risk register which is
reviewed quarterly.
25
Our staff have always been and remain our biggest asset. The redesign of services (arising from the review
People
of our Employment and Enterprise services), means that our services may be delivered in a different way,
which will mean doing things differently in the future. Therefore, we will need to ensure that staff are trained
and have the necessary skills to deliver the objectives of this plan and in so doing achieve the objectives of
the City Council.
This year in particular, will be particularly challenging for us; we no longer have the Deprived Area Fund
project and the Local Economic Growth Initiative (LEGI) project is being reviewed and revised as a result of
the review of our Employment and Enterprise services. Part of the E&E Review includes reviewing and
revising the structure of Employment and Enterprise delivery. There are around fifty people within
Regeneration Services on temporary contracts who are awaiting the outcome of the review as to what the
structure will look like progressing forward. The council's vacancy freeze is also impacting on all our services
and poses a real threat to vital services.
Regeneration Services Division is committed to the Personal Development Review process. The Division
believes strongly in the value of investing in its employees. This commitment is demonstrated through the
target of ensuring each employee receives an average of three days training per year. The Division is also
committed to maximising the potential of individuals, as demonstrated through its continued investment in the
Pacific Institute's 'Investment in Excellence' training course for employees.
Last year, (figures taken from qtr 3 performance report, correct as at December 2008)
83% of staff received some form of training and development
6.4 days on training and development per employee (exceeding corporate target of 3 days training
per employee)
96% of staff had received a PDR
Middle and Senior Managers undertook further recruitment and selection training
This year, we intend to maintain our targets:
3 days training and development per employee
Improve the % number of staff trained
Improve the % number of staff achieving 3 days training per employee
Improve the % number of PDRs carried out for staff
Improve the % number of staff attending equality and diversity training
Continue to train Staff in Health and Safety
26
Health and safety is of utmost importance, and training will continue for staff who have particular
responsibilities for these areas.
Key 'people issues' from service areas:
The central administrative support team for West Orchard House has been actively encouraging work
experience placements to compliment their current skill base and provide a live proactive work
environment in which individuals can gain valuable current support, guidance and motivation in their
journey back into or starting work.
One young lady, who completed three weeks work experience from City College, has opted to come
back in her own time, one day a week to improve her skills and abilities.
A recent design graduate is currently producing a professional standard of design products for
Regeneration Services events and for the Hillfields Action Plan.
One young man, registered disabled and previously out of work for five years, has just completed a
fantastic three month placement with the admin team and will be now be joining the team in a
paid administrative support role to the International Team through the Aspire Programme.
With a French International Student coming for a two month placement, a sixth form student due to start
a Degree in Regeneration in September with us now and throughout the summer the administration
team's "open house" policy is proving rewarding for the team and most importantly for the individual
concerned. It is envisaged that the team will continue along the same pattern and although it will not be
possible to offer all individuals the possibility of paid employment at the end of their placement, the skills,
confidence and friends they gain make them so much better placed to seek out new opportunities of their
own.
In Development Projects there are several vacant posts which at present cannot be filled because of the
overall financial position. If this continues into 2009/10, or the posts are cut as part of the PPR proposals,
Also if no alternative funding is found to replace the PDG (Planning Delivery Grant) then the landscape
and tree protection services will be adversely affected.
Since the end of the previous ERDF programme in Dec 2008, the Environmental Regeneration team's
budget no longer not covers all salary & running costs and a further shortfall will occur at the end of the
Liveability programme. This could impact on staff contracts and on the ability to continue with Far
Gosford Street regeneration and the Neglected Property Initiative. Alternative internal and external
revenue and capital (fee) sources are being investigated
In Development Projects training in relation to Health & Safety e.g. Risk Assessments and Fire Safety will
27
continue for staff that have particular responsibilities for these areas.
The Project Champions base budget does not fully cover staff salary and office running costs. The two
Project Champions will continue to seek out and identify gap-funding for the total budget required from
capital projects, and external funding sources (e.g. Growth Monies). Any shortfall could impact on the
ability to continue to take on new project work.
Within the Regeneration Strategy & Resources Team there are currently vacancies being held due to the
recruitment freeze, and because we are awaiting the outcome of the E&E Review in terms of any
structural changes that need to take place. This is having an adverse effect on the capacity of the team.
28
Service Objective 1
Service Objective: 1. Influence, lead and support strategic regeneration, working with partners locally, sub-regionally, regionally, nationally
and internationally
Purpose Success Criteria
A co-ordinated approach to regeneration strategy to ensure the most Partnerships are recognised as strong and successful, and are achieving
effective targeting of resources and actions to deliver against identified regeneration outcomes to benefit all of the city.
aims. Resources are targeted efficiently and making a difference in the areas that have
Building upon our reputation for successful partnership working and been identified as priorities.
relationships and continuing to ensure that they add value to the work Coventry has a strong voice and the capacity to work strategically at a local, sub-
of Regeneration Services. regional, regional, national and international level.
Ensuring Coventry has the right capacity and a strong voice at all People feel that they have an influence on decisions relating to regeneration in
strategic levels. their locality.
Fulfilling our duty to inform, consult and involve others in the delivery
and design of our services.
Performance Summary
This section should be left blank – used for quarterly review
Action Actions Timescale Lead Links to other Progress
Number /Milestones Officer(s) plans achievements/concerns &
actions to be taken
International
Support the Lord Mayor's office to Co-ordination of international Paula Deas Coventry
carry out a programme of activities via monthly Lord Juliette Verdier- International
international activities with our twin Mayor liaison meeting and Scott Strategy
towns and international partners communication with
1.1 international steering group
Officer support for international
delegations as required (6-8
delegations anticipated per
29
Action Actions Timescale Lead Links to other Progress
Number /Milestones Officer(s) plans achievements/concerns &
actions to be taken
year)
Write and performance manage Refreshed International Paula Deas
Coventry's International Strategy Strategy for 09/10 – 12/13
Juliette Verdier-
written and approved in May
Scott
1.2 2009
Six monthly reporting process
on the strategy
Conference for Atlantic Cities Explore funding opportunities Paula Deas
Network and gather information about
Juliette Verdier-
upcoming EU policies via AGM
Scott
attendance once a year
Share best practice and
develop funded projects where
appropriate via attendance at
CAAC sustainable urban
1.3 regeneration working group
(aprox. 2-3 times per year)
Begin delivery of three year
transnational INTERREG
project with 15 CAAC partners
Ongoing input to policy
lobbying initiatives by the
network
National
New "single conversation" with the Continued dialogue with HCA Carl Pearson
1.4
Homes and Communities Agency at via sub-regional partnerships –
Paula Deas
30
Action Actions Timescale Lead Links to other Progress
Number /Milestones Officer(s) plans achievements/concerns &
actions to be taken
a Regional Level monitored quarterly
Regional
Work with regional partners on the Negotiations with ministers Trevor Howard City Strategy
development of a Multi Area through to June 09.
Geoff Hyde
1.5 Agreement for Skills and
Employment in the West Midlands If agreed on freedoms and
Region flexibilities LA sign off July 09
Develop the City Strategy model to Reviewed at local Trevor Howard City Strategy
1.6 ensure Coventry has a voice within management board bi-monthly Geoff Hyde
the wider partnership
Rebecca Young
Maintain involvement in regional Meetings every quarter (June, ESF Regional
Amanda Hume
European networks in order to September, December, March) Framework
influence policy and identify funding
opportunities i.e. Regional Work with the WMLGA to
1.7 Trevor Howard
European and International Officers ensure local authorities have a
Geoff Hyde
Group (REIOG), Regional voice in the changes to ESF
Rebecca Young
INTERREG Network Group (RING). post 2010 - Reviewed at ESF
Amanda Hume
Officers Group monthly
Maintain relationship with AWM to Quarterly report to Paula Deas
1.8 optimise their policy & funding Management Team Rebecca Young
support for projects
Sub-regional
Paula Deas
Taking forward actions from the Cabinet Briefing May 2009
1.9 Sarah Powell
Sub-national Review
Paula Deas
Regeneration Services contribution LEAs will become a statutory
Sarah Powell
to the development of Local duty in 2010 – in the interim
1.10
Economic Assessments via updates on progress will be
representation on the LEA working provided quarterly.
31
Action Actions Timescale Lead Links to other Progress
Number /Milestones Officer(s) plans achievements/concerns &
actions to be taken
group
Paula Deas
Contribute to the development of a (Awaiting steer from CSWP)
Sarah Powell
1.11 CSW sub-regional economic
development strategy
Rebecca Young
Provide secretariat to Coventry and Meetings every 2 months
Amanda Hume
Warwickshire Sub-Regional Group
1.12 (SRG) through the 2007 – 2013 Review purpose of SRG with
Programme Warwickshire County Council-
Sep 2009
Local
Development of an integrated Ensure the LEGI Partnership Rebecca Young Sustainable
business and enterprise strategy for Board meets to provide Communities
Andy Williams
Coventry, with LEGI at the heart of accountability and governance Strategy
future service delivery across the of the programme – Quarterly
city Coventry
Development of an integrated Economic
LEGI Strategy for 2009-11 Development
Strategy
Under the banner of
'Enterprising Coventry' Coventry City
1.13
implement a core Council Corporate
communications strategy for Plan
2009-11 across the LEGI
partnership that raises the LAA Delivery
profile of Coventry's LEGI Plans
programme locally, regionally
and nationally – Quarterly
report to the LEGI Board
Continue involvement in the
National LEGI Forum and
32
Action Actions Timescale Lead Links to other Progress
Number /Milestones Officer(s) plans achievements/concerns &
actions to be taken
provide representation and
input into the National agenda
of LEGI moving forward –
Quarterly report to Board
Support the work of Coventry Sustainable
Partnership through leading the Community
Meetings held once a quarter Carl Pearson
work of the Economy, Learning, Strategy
Rebecca Young
Skills and Employment (ELSE)
Paula Deas
Strategic Group in delivering the Coventry
Sustainable Community Strategy, Economic
the Local Area Agreement, the Development
1.14 Economic Development Strategy Strategy
and LAA Delivery Plan goals
Coventry City
Council Corporate
Plan
LAA Delivery
Plans
To attend Quarterly meetings Carl Pearson
Attend the City Council's Coventry City
and provide reports to Trevor Howard
Neighbourhood Ward Forums Council Corporate
Members and Residents Tim Jones
1.15 and provide support to Elected Plan
Duncan Elliott
Members: (Foleshill, Radford,
Westwood and St Michaels Ward
Forums)
Improving the way we work and deliver Value for
Money People
Money
Government resources will become more The Regeneration Services Employment & Enterprise The vacancy freeze on employing staff could
limited due to the economic downturn. It is Review includes a review of our representation across detrimentally impact on the ability of Regeneration
essential that we work in partnership to ensure partnerships in relation to the Employment and Services to have sufficient representation and
that available resources are maximised and Enterprise element of Regeneration Services. capacity at all strategic levels.
targeted efficiently.
33
Improving the way we work and deliver Value for
Money People
Money
Lack of financial resources is impacting upon
our people resources.
Update: This section should be left blank – Update: This section should be left blank – used for Update: This section should be left blank – used
used for quarterly review quarterly review for quarterly review
34
Service Objective 2
Service Objective: 2. Contribute to the city centre's transformation programme
Purpose Success Criteria
The transformation of the city centre is key to a successful growth A successful and vibrant city centre at the heart of the sub-region.
strategy for Coventry. In order to increase the economic performance The city centre is a destination of choice to live, work and visit.
of the city we need to develop the city centre’s physical environment,
People feel that they have an influence on decisions relating to regeneration in
retail offer, job opportunities, and visitor offer.
their locality.
Fulfilling our duty to inform, consult and involve others in the delivery
and design of our services.
Performance Summary
This section should be left blank – used for quarterly review
Action Actions Timescale Lead Links to other Progress achievements/concerns &
Number /Milestones Officer(s) plans actions to be taken
City Centre
Tony Auty City Centre
City Centre Transformation - City Centre Programme
Andy Telford Transformation
Support the Deputy Director to Board: provide monthly up to
Paul Beesley
progress, including the date information to Service
2.1 formulation and delivery of the Board meetings
policy/ strategy and action plan
for the regeneration of the City Continue to approval of the
Centre Implementation Plan Oct 09
Public Sector Relocation and Run a prestige network event Trevor Howard City Centre
HQ Functions – promote the city in London Spring/ Summer Framework
Stan Aldridge
as a location for business 2009
2.2 investments with a specific Public Sector
aspiration to attract them to the Continue to build enquiry Relocation
city centre specific business cases by Strategy (Lyons
March 2010 Review)
35
Action Actions Timescale Lead Links to other Progress achievements/concerns &
Number /Milestones Officer(s) plans actions to be taken
City Centre
Retail – Encourage the By 31 March 2010 Trevor Howard
Framework
development of the city centre
Tony Auty
retail offer in the short/ medium
Stan Aldridge LEGI
term by highlighting the
2.3 opportunities to investors, Paul Beesley
developers and end users whilst
continuing to target aspirational
retail/leisure brands to the
existing and future city centre
City Centre
St. Johns: manage relationship Regular liaison meetings Tony Auty
Transformation
with developer and Severn Trent
Water to ensure construction Start on site July 2009
2.4 progresses on schedule and
ensure the refurbishment of Complete by the end of Sep
Manor Road Bridge is completed 2009
by October 2009
City Centre
Friargate: As part of project By March 2010 Tony Auty
Transformation
team liaise with developer to Andy Telford
2.5 secure outline planning
Paul Beesley
permission and provide property
advice
City Centre
Design Manuals: Prepare draft By March 2010 Tony Auty
Transformation
Streetscape Design Guide, Andy Telford
2.6 Urban Design Framework: Tall
Buildings Guide and consult with
stakeholders and public
City Centre
Heritage Buildings e.g. St By 31 January 2010 Tony Auty
Transformation
Mary's Hall Kitchens, Drapers Paul Beesley
2.7 Hall, Whitefriars Monastery –
George Asset
work with Property colleagues to
Demidowicz Management
develop an interim management
Plan
36
Action Actions Timescale Lead Links to other Progress achievements/concerns &
Number /Milestones Officer(s) plans actions to be taken
and marketing strategy
Development sites: Tony Auty Financial
Identify and develop Three development Paul Beesley Strategy
proposals for future opportunities
opportunities
2.8
Market and achieve disposals Complete two disposals
necessary to support the
capital receipts target and
create job opportunities
Far Gosford Street Area
Regeneration
Lead the development of Far Set up and service a Far Tony Auty Cultural
Gosford Street as Coventry’s Gosford Street business forum Strategy
Andy Duncan
creative business quarter, with – April 09 onwards
CDP Ltd and AWM Nicola Poole Coventry
Prepare, update and deliver
Cultural
FGS communication and
Partnership
events strategy – April 09
onwards
Preparation of business plan
and submission of full AWM
bid May 09
2.9
Start implementing creative
quarter business plan at Far
Gosford Street Industrial
estate – June 09
Start Sky Blue Way access
remodelling to prepare for Site
1 landmark development –
November 09
10 Townscape Heritage
Initiative grant projects
37
Action Actions Timescale Lead Links to other Progress achievements/concerns &
Number /Milestones Officer(s) plans actions to be taken
completed – March 2010
Swanswell
Progress with the physical Central Depot- Completion of Duncan Elliott Sustainable
development of the Swanswell marketing brief. Note: Keeping Communities
Initiative marketing of site for Strategy
development under review – 1
May 2009 Coventry City
Council
Corporate Plan
Coventry and Warwickshire Duncan Elliott See above
Hospital site – Completion of
Acquisition agreements and
agreement and
commencement of demolition
works programme – By
August 2009
2.10
New City Centre Health Duncan Elliott See above
Centre (LIFT) – Agree design,
gap funding and complete car LIFT
park disposal – 1 July 2009 Programme
Ring Road Junction 2 – Duncan Elliott Sustainable
(Note this work has yet to be Communities
formally commissioned) – Strategy
Initial detailed design, cost
and programme feasibility Coventry City
study – Sep 2009 Council
Corporate Plan
New Salvation Army Hostel Duncan Elliott Supporting
– relocation to Harnall Lane People and
Tim Wright
West site. Resolve local Homeless
38
Action Actions Timescale Lead Links to other Progress achievements/concerns &
Number /Milestones Officer(s) plans actions to be taken
consultations, car park Services
relocation, design and
complete property deal – By
September 2009
Swanswell Academy School Duncan Elliott Sustainable
– Agreement of scheme Communities
design, site issues and land Strategy
disposals – By 31 September
2009 Coventry City
Council
Corporate Plan
Influence design and Duncan Elliott See above
development of private
sector schemes (i.e. Canal
Basin area, Godiva Place, bus
garage and Phoenix 2 areas)
– By 31 March 2010
Lead and strengthen public Duncan Elliott See above
sector stakeholder groups,
and co-ordinate their
investment plans – by March
2010
Progress the Swanswell Duncan Elliott
Initiative Masterplan through
to Local Development
Framework approval – by
March 2010
Ensure the regeneration and Trevor Howard
Lead the development of a Local
renewal of Swanswell meets the Duncan Elliott
2.11 Swanswell Benefits Plan – By Development
needs of the community and March 2010 Margaret Framework
supports delivery Dieterman
39
Action Actions Timescale Lead Links to other Progress achievements/concerns &
Number /Milestones Officer(s) plans actions to be taken
Devise, develop and lead a Statement of
Community Involvement & Community
Communications Plan at Involvement
Swanswell – by October 31st
2009
Deliver a public consultation
exercise and Statement of
Community Involvement to
inform the Swanswell element
of the LDF planning
application - By 31st March
2010
Improving the way we work and deliver Value
Money People
for Money
The Project Champions base budget does not Continued regular dialogue between Project Project Champion Team staff are on permanent
fully cover staff salary and office running costs. Champions and the Finance Team contracts. Therefore need to continue successfully
The two Project Champions will continue to seek resolving gap-funding issue on an ongoing basis.
out and identify gap-funding for the total budget
required from capital projects, and external
funding sources (e.g. Growth Monies). Any
shortfall could impact on the ability to continue to
take on new project work.
Update: This section should be left blank – used Update: This section should be left blank – used Update: This section should be left blank – used for
for quarterly review for quarterly review quarterly review
40
Service Objective 3
Service Objective: 3. Transform Coventry's physical environment in an environmentally sustainable way to benefit all of the city
Purpose Success Criteria
Regeneration projects outside of the city centre contribute to meeting Local people gain the benefits of regeneration.
regeneration aims and the needs of local residents. The sustainable regeneration of the city, featuring high quality design in all new
Ensuring all regeneration is sustainable and contributes to the aims of developments.
tackling climate change. The city's heritage and natural resources are retained.
The protection of the city’s heritage and natural resources. People feel that they have an influence on decisions relating to regeneration in
Fulfilling our duty to inform, consult and involve others in the delivery their locality.
and design of our services.
Performance Summary
This section should be left blank – used for quarterly review
Progress
Action Timescale Lead Links to other
Actions achievements/concerns &
Number /Milestones Officer(s) plans
actions to be taken
Planning Permissions or
Influence the Masterplanning, Tony Auty
Masterplans approved
design, development and
by 31 March 2010 for: Paul Beesley
implementation of major
redevelopment projects Browns lane Andy Telford
Paragon Park
3.1
Bell Green Goods Yard
AGCO
Accordis
Canley
NDC
Influence the Local Prepare the: Tony Auty
Development Framework Core
3.2 City Centre Urban Design Andy Telford
Strategy
Framework SPD
Streetscape Design SPD
41
Progress
Action Timescale Lead Links to other
Actions achievements/concerns &
Number /Milestones Officer(s) plans
actions to be taken
Tall Buildings SPD
Landscape Design Guidance
Tree Guidelines for Developers
Publication of three policy papers
or contributions to them by 31
March 2010
Ongoing: No. of Design Forums Tony Auty
Ensure all major developments
held/ Design Awards competition Andy Telford
are completed to a high design
standard helping to generate a
3.3
distinctive 'Coventry style' in
accordance with the Coventry
Urban Design Guidance
Support the development of the Identify how asset transfer can be Trevor Howard Sustainable
Council's Community Owned factored into planning, existing and Communities
Paula Deas
Assets policy new facilities, and services in ways Strategy
that support community need and Margaret
Coventry’s Growth Agenda by Dieterman Council
March 2010 Support to
3.4
Community
Policy drafted by April 2010 Associations
Community
Centres
Strategy
By 31 March 2010 Tony Auty
Ensure that development takes
George
place that respects the historic
Demidowicz
environment preserving and
3.5 enhancing conservation areas,
conserving historic buildings and
recording and/or preserving
archaeological remains.
42
Progress
Action Timescale Lead Links to other
Actions achievements/concerns &
Number /Milestones Officer(s) plans
actions to be taken
Work with Strategic Deliver measures to promote Social Tony Auty Local
Transportation to maximise Inclusion LTP programme – March Transport Plan
Andy Duncan
Local Transport Plan & SUD 2010
3.6
resources to regenerate local
communities and improve
transport to employment sites
Carl Pearson Sustainable
New Deal for Communities Rebecca/ Carl to input into the
Rebecca Young Communities
(NDC) – Regeneration Services NDC Succession Strategy and sign
Strategy
input into the Succession it off from a Regeneration Services
3.7 Strategy perspective – by August 2009
Coventry City
(Succession strategy for the NDC Council
needs to be signed off by Corporate Plan
September 2009 )
Canley Regeneration
3.8
Programme
Carl Pearson
Continue to progress the Planning Application by 31 July Sustainable
Trevor Howard
development of the Canley 2009 Communities
Tim Jones
Regeneration Masterplan in Strategy
Margaret
3.9 consultation with the local
Dieterman
community
Trevor Howard
Ensure the regeneration and Lead, sustain and evaluate the Sustainable
Tim Jones
renewal of Canley meets the Canley Community Involvement Communities
Margaret
needs of the community and and Communications framework - Strategy
Dieterman
3.10 supports delivery Review progress with Canley
Delivery Team every quarter – up Canley
to March 2010 Masterplan
Deliver a programme of
43
Progress
Action Timescale Lead Links to other
Actions achievements/concerns &
Number /Milestones Officer(s) plans
actions to be taken
consultation and involvement that
shapes and supports delivery of
Canley Benefits Plan
Lead, deliver and evaluate Canley
Regeneration Programme’s
Benefits Plan - Programme in place
by December 2010
Complete the delivery of physical
Continue to implement the Tony Auty Sustainable
projects - March 2010
Liveability Programme Communities
Andy Duncan
Strategy
Chair and support the inter-agency
Tony Auty AIMS
Neglected Property Initiative and
Steering Group – March 2010 Andy Duncan
Community
Safety Strategy
Chair and support the inter-
3.11 Tony Auty
departmental Section 215 group –
March 2010 Andy Duncan
Complete and evaluate Coventry’s
Tony Auty CSD Cabinet
DIY Streets’ national pilot, with
Member Plan
Sustrans – March 2010 Andy Duncan
Maximise resources to manage and
CSD, Parks
maintain public spaces, green
spaces, natural habitats, public art
and other environmental
improvement assets – March 2010
Prepare action plans for other
Regenerating Neighbourhood Tony Auty SUD
3.12 target centres to include in SUD
Centres
ERDF bid – June 2009 Andy Duncan
Lead the preparation and
Tony Auty
implementation of a Riley
44
Progress
Action Timescale Lead Links to other
Actions achievements/concerns &
Number /Milestones Officer(s) plans
actions to be taken
Square regeneration action plan
Andy Duncan
– March 2010
Swanswell – see 2.
Contribution to the City
3.13
Centre's transformation
programme
Far Gosford Street – see 2.
Contribution to the City
3.14
Centre’s transformation
programme
Improving the way we work and deliver Value
Money People
for Money
The Project Champions base budget does not Continued regular dialogue between Project Project Champion Team staff are on permanent
fully cover staff salary and office running costs. Champions and the Finance Team contracts. Therefore need to continue successfully
The two Project Champions will continue to seek resolving gap-funding issue on an ongoing basis.
out and identify gap-funding for the total budget
required from capital projects, and external
funding sources (e.g. Growth Monies). Any
shortfall could impact on the ability to continue to
take on new project work.
Update: This section should be left blank – used Update: This section should be left blank – used Update: This section should be left blank – used for
for quarterly review for quarterly review quarterly review
45
Service Objective 4
Service Objective: 4. Improve Coventry's economy through enterprise, skills and employment opportunities, minimising the impact of the
economic downturn, and ensuring that the benefits are felt in even the most deprived neighbourhoods
Purpose Success Criteria
Enterprise, skills and employment opportunities improve the economy. Residents are enabled to reach their potential in skills, employment and
To tackle worklessness, employment is viewed as the route out of enterprise.
poverty.
Performance Summary
This section should be left blank – used for quarterly review
Action Actions Timescale Lead Links to other Progress
Number /Milestones Officer(s) plans achievements/concerns &
actions to be taken
Responding to Redundancy and
Economic Recovery
A co-ordinated response and approach to Work with sub-regional Carl Pearson National priorities
redundancies to deliver adequate help to partners through the
Trevor Howard
people and businesses affected Coventry and Regional
Warwickshire Economic Geoff Hyde priorities
Recovery Partnership Stan Aldridge
(CWERP)
4.1 Work with JobCentre Plus
and other agencies
Work with partners to
engage early with
businesses contemplating
redundancies to provide
advice and support in
order to minimise effects
46
Action Actions Timescale Lead Links to other Progress
Number /Milestones Officer(s) plans achievements/concerns &
actions to be taken
Provide strategic financial
and investment support to
businesses in difficulty
Investment
An integrated business investment and Alignment to Business Trevor Howard Regional
enterprise strategy for the City Support Simplification by Stan Aldridge Economic
March 2010 Strategy
Memorandum of AWM sector
understanding with strategies
Business Link working
4.2
effectively September Business Support
2009 Simplification
Sub regional sector Sub National
networks established Review
Business Link
Check dates in timelines/
For business sectors key to future Complete individual sector Trevor Howard AWM Cluster
milestones as moved an
employment and prosperity, develop strategies by June 2009 Stan Aldridge Plans
action from another section.
business sector programmes and flagship
projects to increase the city’s AWM Sector resources European
attractiveness to investors. For the flowing to city’s key initiatives
following Technology Sectors work with business sectors
4.3 Warwickshire and Solihull to attract December 2009 Technology
investment, particularly through the Corridor
anticipated approval of AWM Technology Implement sector
Corridor funding for sector marketing marketing, programmes
and flagship projects for
Automotive each sector by March
Aerospace 2010
Creative
47
Action Actions Timescale Lead Links to other Progress
Number /Milestones Officer(s) plans achievements/concerns &
actions to be taken
Environmental
Medical
Work with developers, intermediaries and Coventry Networking Trevor Howard City Image, City
the press to promote the city as a location event Summer or Autumn Centre
Stan Aldridge
for business investment – events, 2009 Framework
conferences and MIPIM) Deirdre Fitzhugh
Birmingham Event Spring
Jacqui Staunton
2010
MIPIM 10 – March 2010
Work closely with property
developers to market their
sites and bring occupiers
4.4 by March 2010. Notably:
St Modwens/ Savils for
Whitley
Highbridge/ Cushman
Wakefield for Ansty
Cannon Kirk for
Friargate
By March 2010
Achieve investment
targets by 31st March 2010
Provide a first class relocation service to Working with QCA Trevor Howard
the city throughout the year taking
Stan Aldridge
up occupation Autumn 09
4.5
– but continue to
encourage staff to ‘use’
the city centre
48
Action Actions Timescale Lead Links to other Progress
Number /Milestones Officer(s) plans achievements/concerns &
actions to be taken
Working with Severn Trent
throughout the year
Achieve investment
targets by 31 March 2010
Timing to late in terms of E&E
Implement and deliver the 'Attracting Review delivery Trevor Howard LEGI Strategy
review – are we renaming
Investment to the LEGI Area project mechanisms to ensure we
Stan Aldridge LEGI strategy going forward
4.6 are optimising advantage Regional
for hard to reach residents Economic
- By March 2010 Strategy
Continue to work with Coventry and Continued success and Trevor Howard
Warwickshire First as Board Members and hopefully grow the
4.7 Stan Aldridge
corporate sponsors to ensure continued organisation and the
success sector by March 2010
Work with developers to bring difficult Recruit member of staff Trevor Howard Regional
sites within the regeneration zone to the June 09 Economic
Stan Aldridge
market (depending on funding approval) Strategy
4.8
through the SUD programme Full listings of sites and
opportunities December AWM Investment
2009 Sector Strategy
Maximise public sector financial support By 31 March 2010 Trevor Howard Regional
4.9 for investment projects Economic
Stan Aldridge
Strategy
Business Support
Date for the strategy?
Manage and deliver a flexible, responsive, Development of an Carl Pearson LEGI, NDC,
innovative and sustainable business integrated business and Objective 2
4.10 Rebecca Young
support and enterprise service across enterprise strategy for
Coventry, focused on the most Coventry -? Trevor Howard
49
Action Actions Timescale Lead Links to other Progress
Number /Milestones Officer(s) plans achievements/concerns &
actions to be taken
disadvantaged and ensuring continual
Develop partnership Andy Williams
review and development takes place.
working and collaboration
Stan Aldridge
across organisations and
agencies who deliver Tony Auty
business and enterprise Andy Duncan
support across Coventry –
Quarterly report to LEGI
Board
Align additional resources
including ERDF Priority 2
to the delivery of intensive
enterprise and business
support offered through
the LEGI programme – 31
March 2009
Deliver business support
for the benefit of priority
neighbourhoods with
partners utilising NDC,
LEGI and other resources
– by 31 March 2010
Is this repeat of above one on
Secure and co-ordinate Tony Auty LEGI
delivering business support
resources to support
businesses in Andy Duncan SUD
Neighbourhood Centres
targeted for action in the
ERDF SUD – August 2009
Work with the Chamber of Commerce to Delivery Plan agreed June Rebecca Young Sustainable
4.11 develop and implement the LAA Delivery 2009 Communities
Plan for LAA NI 171 – New Business Andy Williams Strategy
50
Action Actions Timescale Lead Links to other Progress
Number /Milestones Officer(s) plans achievements/concerns &
actions to be taken
Registration rate
Stan Aldridge
Employment & Skills
Rebecca Young
Work with partners to progress against Half yearly report on
Paula Deas
4.12 actions in the Local Area Agreement progress of the Delivery
Trevor Howard
Delivery Plan 152 on Worklessness Plan
Sarah Powell
Monitor and deliver the outputs for NI165 Monthly review Carl Pearson
in partnership with Warwickshire and
Trevor Howard
4.13 Solihull through CSWP Half yearly report on
progress of the delivery Geoff Hyde
plan
Sarah Powell
Oversee progress on LAA Delivery Plans: Half yearly report on Rebecca Young
progress of delivery plans
Sarah Powell
NI 79 - % of young people attaining Level by indicator owners
2 by age 19 in a Local Authority Area
NI 117 – 16 to 18 year olds who are not
4.14
in education , training or employment
(NEET)
NI 164 – Proportion of population aged
19-64 for males and 19-59 for females
qualified to at least Level 3 or higher
Trevor Howard
Design and deliver support to assist Implementation of the National,
Geoff Hyde
client groups identified through the integrated client pathway Regional
Kim Tierney
Employment and Enterprise Review into developed through the E& Priorities
4.15 Stan Aldridge
sustainable employment, including: E&E Review
Supporting people with disabilities, Work with Local
mental health and learning disabilities Employment Partnership
51
Action Actions Timescale Lead Links to other Progress
Number /Milestones Officer(s) plans achievements/concerns &
actions to be taken
to gain access to employment Opportunities through
opportunities with adequate support networks – By 31st March
2010
Offenders
NEET progress through
Progression of NEET through quarterly report from CEU
construction opportunities Board
Trevor Howard Date needed for E&E Review
Design and deliver support for people in Implementation of the City Strategy
Geoff Hyde
priority neighbourhoods into work integrated client pathway
Kim Tierney
developed through the E& Economic
Stan Aldridge Development
E&E Review
Margaret Dieterman Strategy
Further develop the
Canley Employment Canley and
Model with partners Swanswell
Regeneration
Swanswell Employment Programmes
Strategy implemented by
31 March 2010 LEGI
4.16 Review employment ESF and ERDF
facilities in priority programmes
neighbourhoods
Community
LEGI employment and Services Plan
barrier breaking services
Review Employment and
Skills Plan within City
Strategy wards by April
2009
Work with third sector to
deliver ESF outputs March
52
Action Actions Timescale Lead Links to other Progress
Number /Milestones Officer(s) plans achievements/concerns &
actions to be taken
2010
Build on existing networks and Work with partners to Trevor Howard National,
partnerships to co-ordinate, lead and deliver community based Regional
support initiatives to design and deliver employment support and Geoff Hyde Priorities
new employment support initiatives and local job opportunities
job opportunities, training and skills through City Strategy and
LEGI Boards
4.17
Work with Sector Skills
Council to ensure
residents have the skills
and training to progress
within work
By 31 March 2010
Work with partners through the Local Review quarterly with Job Trevor Howard City Strategy
Jobs Group to ensure local people have Centre Plus
Geoff Hyde
4.18 access to local employment opportunities LSE Agenda
(LEPS)
DWP policy
Lead and strengthen the recruitment Regular review meetings Trevor Howard LSE Agenda
4.19 network to help ensure local community to share good practice, at
Geoff Hyde
organisations have a chance to access least 6 times per year
prime contracts for the delivery of
53
Action Actions Timescale Lead Links to other Progress
Number /Milestones Officer(s) plans achievements/concerns &
actions to be taken
employment outputs.
Employer Engagement
Geoff Hyde
Implement an employer engagement Throughout 2009/10 Regional ESF
model to ensure vacancies with Framework
4.20
employers are serviced for the good of
workless clients.
Trevor Howard
Work with existing business in the most Continue to develop the LEGI Strategy
Stan Aldridge
disadvantaged areas of the city to nature of business support
4.21 develop their competitiveness and sustain to respond to the NDC
their role as an employer within the local economic downturn during
economy 2009/10 Canley
Trevor Howard
Develop the employer engagement forum Bi monthly forum to share
Geoff Hyde
4.22 and ensure sector account management information
Stan Aldridge
information is shared across partnerships
Trevor Howard
Ensure those gaining employment have Quarterly Review of
Geoff Hyde
access to in work training especially provision
4.23 through Train to Gain
Improving the way we work and deliver Value
Money People
for Money
What budget constraints are there in relation to Identify any improvements to systems and What people issues are there that might affect
delivering this service objective and what are you processes needed to deliver the service objective delivery of this service objective and what are you
planning to do to address these? doing to address these?
54
Improving the way we work and deliver Value
Money People
for Money
Update: This section should be left blank – used Update: This section should be left blank – used Update: This section should be left blank – used for
for quarterly review for quarterly review quarterly review
55
Service Objective 5
Service Objective: 5. Identify, secure and manage funding resources for regeneration
Purpose Success Criteria
To ensure that resources are well managed, maximised and spent No grant money is clawed back by external funders
effectively. No significant issues are raised in internal or external audits of our programmes
and projects
All grant payments are made within 28 days of receipt of completed grant claims
To secure future funding to enable the delivery of regeneration. The External Funding Team accesses (directly or indirectly) at least £10m
of Regeneration resource in 2009/10
Performance Summary
This section should be left blank – used for quarterly review
Progress
Action Timescale Lead Links to other
Actions achievements/concerns
Number /Milestones Officer(s) plans
& actions to be taken
Identify and Secure New External Funds
Rebecca Young
Fully implement Regeneration Services By 31 April 2009
5.1 External Funding Bid Framework (so that all
external funding bids follow this framework)
Rebecca Young AC comment - Funding
Finalise the Employment, Learning, Skills By 30 September 2009 Strategy (ELSE and
Amanda Hume
and Economy and City Development CDD). We haven't quite got
External Funding Strategies an External Funding strategy
and I think that this is an
5.2 important block of work for
2009/10. This echoes a bit of
the Jon Bloomfield work
done a couple of years back.
However, it could be that this
is done collaboratively
56
Progress
Action Timescale Lead Links to other
Actions achievements/concerns
Number /Milestones Officer(s) plans
& actions to be taken
between Juliette, Steve,
Amanda but maybe with
some "consultant" or
external/ peer input. This
would map out more
systematically what the
overall funding opportunities
are and our tactics for
getting the money in. Paula -
do you have any further
thoughts on this please
Secure at least £5m of new Rebecca Young AWM
Identify and exploit regional, national and
external funding resource Paula Deas
European funding opportunities to secure
(e.g. INTERREG, Lifelong Trevor Howard European
future resources for the work of the
Learning and URBACT, Andy Williams Funding
Regeneration Services Division
Sustrans, Connect2, AWM, Stan Aldridge
SUD, Arts Council, and Geoff Hyde Regional
Local Transport Plan – Kim Tierney Economic
Home Zones) Margaret Dieterman Strategy
5.3 Tony Auty
The individual timescales
Andy Duncan Sustainable
and milestones will be
Urban
included in each of the
Development
external resource streams
and bid deadlines
Quarterly reports
to Management Team
Management of External Funds
Design and set up new Regeneration 30 June 2009 Rebecca Young
5.4 Services Commissioning and Contract
Management Framework
5.5 Allocate and manage new resources (such Key markers: Rebecca Young
as Connecting to Opportunities etc) through
57
Progress
Action Timescale Lead Links to other
Actions achievements/concerns
Number /Milestones Officer(s) plans
& actions to be taken
new Regeneration Services Commissioning
30 September 2009
and Contract Management Framework
31 March 2010
Advantage West Midlands bid for city centre: By 31 March 2010 Paula Deas
5.6 agree and manage the bidding process to Tony Auty
draw down £40m of grant Duncan Elliott
Paul Beesley
Andy Williams
Ensure LEGI resources are maximised, well Quarterly report to LEGI
managed and spent effectively, focused on Board
5.7 the most disadvantaged people and
businesses of Coventry
Ensure that the New Deal for Communities By 31 March 2010 Rebecca Young
5.8 (NDC) Programme is well managed so that
resource is spent effectively
Work in partnership with Warwickshire Key markers: Rebecca Young
County Council to develop five projects
30 September 2009
5.9 through the Sustainable Urban Development
(SUD)package and then manage these 31 March 2010
effectively so the resource is spent effectively
Monitor the delivery and allocation of By 31 March 2010 Trevor Howard
European Social Fund (ESF) funding Geoff Hyde
5.10 through the regional co-financing board to
ensure Coventry is not disadvantaged by
regional allocations
Effectively closedown the Hillfields Action By June 2009 Rebecca Young
Plan, WEHM Action Plan and Priority 2
5.11 European Regional Development Fund
(ERDF) Package for the 2000-2006
Programmes
58
Progress
Action Timescale Lead Links to other
Actions achievements/concerns
Number /Milestones Officer(s) plans
& actions to be taken
Paula Deas
Project manage the Growth Fund allocation Monthly programme
Tim Jones
5.12 for 2009/10 and 2010/11. reports to the Corporate
Alf Tipper
Growth Group
Far Gosford
Manage Lottery Townscape Heritage Quarterly reports to Tony Auty
5.13 Street
Initiative programme Heritage Lottery Fund
Andy Duncan regeneration
Swanswell: Agreement and completion of By 30 September 2009 Duncan Elliott
Joint Investment Funding Agreement with
5.14
AWM and HCA (inc. resolving ring-fencing
issue)
Improving the way we work and deliver Value
Money People
for Money
What budget constraints are there in relation to Identify any improvements to systems and What people issues are there that might affect
delivering this service objective and what are you processes needed to deliver the service objective delivery of this service objective and what are you
planning to do to address these? The proposed implementation of an External doing to address these?
Funding Bid Framework will ensure a better co- There are issues caused by the inability to recruit to
ordination of bidding activity to identify and secure vacant posts due to the budgetary position of
funding. Coventry City Council.
Update: This section should be left blank – used Update: This section should be left blank – used Update: This section should be left blank – used for
for quarterly review for quarterly review quarterly review
59
Service Objective 6
Service Objective: 6. Continually seek to improve our services and develop our workforce
Purpose Success Criteria
Continual improvement to Regeneration Services A good quality value for money service to meet the needs of people in Coventry
The need to review service delivery in light of funding available e.g. the A well developed and motivated workforce delivering Regeneration Services
economic recession, PPR, VfM, required efficiency savings
Continual development of the workforce
Performance Summary
This section should be left blank – used for quarterly review
Progress
Action Timescale Lead Links to
Actions achievements/concerns &
Number /Milestones Officer(s) other plans
actions to be taken
Continue to implement actions from the See actions under Carl Pearson
Employment & Enterprise Review previous services
Rebecca Young
objectives - throughout
6.1 2009/10 Trevor Howard
Priti Bharadwa
Implement an universal performance Throughout 2009/10 Rebecca Young
management culture and evaluation
6.2
framework that is integrated to the divisional
wider performance management approach
Continue to offer work placements to help Throughout 2009/10 Rebecca Young Sustainable
individuals in their journey back into or Communities
6.3 Kelly Barnacle
starting employment via the central Strategy
administration team in West Orchard House
60
Progress
Action Timescale Lead Links to
Actions achievements/concerns &
Number /Milestones Officer(s) other plans
actions to be taken
Coventry
City Council
Corporate
Plan
Use the frameworks prepared for Canley Develop performance Trevor Howard Sustainable
and Swanswell to develop an evidence indicators and evaluation Communities
Margaret
based approach to inform major frameworks for community Strategy
Dieterman
regeneration initiatives and service and client centred
developments, for key regeneration projects regeneration by March Local
6.4
in the city 2010 Development
Framework
Design service responses
in Canley by 31 March
2010
Review report to Cabinet
Review, evaluation and dissemination of the Tony Auty City Services
Member (City Services) by
Liveability Programme Directorate
Dec 09 Andy Duncan
6.5 Cabinet
Member
Plan
Undertake Year 1 (09-10) Equality Impact
Report to Management Trevor Howard Equality
Assessments
Team Rebecca Young Strategy
Paula Deas
Race
6.6 Equality
Scheme
DES/GES
Undertake Year 1 (09-12) Equality Impact
Quarterly Reports to Trevor Howard Equality
6.7 Assessments
Management Team Rebecca Young Strategy
Paula Deas
61
Progress
Action Timescale Lead Links to
Actions achievements/concerns &
Number /Milestones Officer(s) other plans
actions to be taken
Tony Auty
Race
Equality
Scheme
DES/GES
Is it for IBTeam?
Maintain ISO 9001 quality accreditation for Continuous improvement Trevor Howard Embedded in
the Investment and Business Team ? by activities to March 2010 Stan Aldridge team (IBT)
6.8 paying particularly attention to client focused service
service improvements delivery
Ensure that Personal Development Reviews Personal Development All Service Corporate
are undertaken for all staff Reviews (PDR) completed Managers Plan
by 30 June 2009
6.9 Team Plans
6 monthly reviews
completed by 31
December 2009
To reduce or maintain sickness absence Quarterly update to All Service Corporate
below the Regeneration Services Division's Regeneration Managers Plan
6.10 target and maintain this level throughout Management Team
2009-10
To continue to review risk assessments, Quarterly update to All Service CDD Health
6.11 carry out floor inspections, staff briefings and Management Team Managers & Safety
training on Health & Safety Plan
Investigate how a higher percentage of our Report by Trevor Howard Equality
investment service users can be encouraged Impact
6.12 Stan Aldridge
to complete client reviews and equalities October 2009 Assessment
information
6.13 Work with our partners to develop strategies April 2009 Trevor Howard Equality
62
Progress
Action Timescale Lead Links to
Actions achievements/concerns &
Number /Milestones Officer(s) other plans
actions to be taken
and deliver services that target issues in the Impact
Stan Aldridge
priority neighbourhoods post April 2009 Assessment
Ensure ethnic monitoring data is collected Systems in place by All Managers Equality
and analysed September 2009 Impact
6.14 Assessment
(Dev project)
Investigate more effective methods of Methods in place by Tony Auty Equality
reaching certain groups such as young September 2009 Impact
6.15 Andy Duncan
people and the new European communities Assessment
(Dev project)
Improving the way we work and deliver Value
Money People
for Money
What budget constraints are there in relation to Identify any improvements to systems and What people issues are there that might affect
delivering this service objective and what are you processes needed to deliver the service objective delivery of this service objective and what are you
planning to do to address these? doing to address these?
Update: This section should be left blank – used Update: This section should be left blank – used Update: This section should be left blank – used for
for quarterly review for quarterly review quarterly review
63