15.0 Summary of effects of Power Supply
of Power Supply
15.0 Summary of effects
Volume 1 Volume 2 Volume 3 Volume 4 Volume 5 Technical
Project and its Environmental Environmental Environmental Environmental Appendix
Effects Effects of Effects of Effects of Effects of
Marine Structures Desalination Plant Transfer Pipeline Power Supply
Chapter 15
Summary of
effects of the
Power Supply
15 Summary of effects of Power Supply
The Desalination Plant and Transfer Pipeline will require an average electricity
requirement of approximately 92 megawatts for a 150 GL Plant. As the existing
electricity network in the Bass Coast region is unable to meet this demand, a
new power supply is required. The Reference Project includes connection to the
existing transmission network via grid connection infrastructure. This would
include connection to existing 220 kV lines via a new terminal station at Tynong
North, a double circuit 220 kV overhead transmission line approximately 60
kilometres long to a new terminal station in Woolamai and three 66 kV
underground lines approximately 10 kilometres long installed to the Desalination
Plant.
15.1 Assessment methodology
The key effects of the Power Supply were identified taking into account
legislative and policy obligations, community and stakeholder concerns and
guidance from the Scoping Requirements. Environmental effects from
construction and operation of the grid connection were considered through an
environmental impact and risk assessment process.
Chapter 15 Summary of effects of the Power Supply 15-1
Project controls — expressed as Performance Requirements in the
Environmental Management Framework — were developed following a detailed
risk assessment of the effects of the Power Supply on the environment,
community and local economy. The Performance Requirements form an
envelope to guide the Project Company in the design, construction and
operation of the Desalination Plant and its components, including the Power
Supply. This will prevent any adverse impacts to the environment and the
community, whilst allowing the Project Company to create an innovative design
for the Desalination Project.
15.2 Existing environment
The grid connection would cross a range of distinct environments, including the
coastal plain between Kilcunda and Wonthaggi, the Strzelecki foothills, Bass
Valley and the alluvial plain between Nyora and Tynong. The transmission line
alignment has been selected to avoid townships and relevant environmental
constraints as far as possible and therefore land use largely comprises cleared
agricultural land. Beef and dairy are the dominant agricultural land uses along
the alignment. The notable exception to this is the Koo Wee Rup Horticultural
Preservation Area, defined in the Cardinia Planning Scheme as the Special Use
Zone (SUZ1). Within this zone and where irrigation is available, there is heavy
cropping, most notably potatoes. The potato pathogen, the Potato Cyst
Nematode (PCN), is also known in this area. The area has been declared a PCN
Control Area under the Plant Health and Plant Products Act 1995. Within this
Control Area there are strict protocols in place for the movement of soil and
plant materials.
Some indigenous remnant vegetation is present in road reserves, along
waterways and in occasional patches within paddocks or windrows. The
Strzelecki foothills comprise steeply sloping hills as well as stream sides and
soaks, and these areas may provide habitat for the EPBC-listed Giant Gippsland
Earthworm. The EPBC-listed Dwarf Galaxias and Australian Grayling are likely to
be present in waterways crossed by the transmission line, including the Bass
River and Powlett River. Other EPBC-listed fauna species that may occur along
the grid connection corridor include the Powerful Owl, Southern Brown
Bandicoot, Swamp Skink and Growling Grass Frog. Potential habitat for three
EPBC-listed flora species has been identified along the grid connection corridor;
these include River Swamp Wallaby Grass and Strzelecki Gum.
15-2 Chapter 15 Summary of effects of the Power Supply
Aboriginal sites are scattered across the region, with areas of cultural heritage
sensitivity including waterways, the Koo Wee Rup Plain and coastal dunes.
Isolated artefact sites or small scatters are likely to occur in all landforms along
the alignment, but they are more likely to occur where landforms change or
along waterways and the edges of former swamplands or floodplains.
Aboriginal archaeological sites previously recorded, and those recorded during
field investigations to date, consist largely of isolated artefacts or low density
artefact sites of low scientific significance. Post contact historical archaeological
sites within the investigation corridor include the Eastern Railway Like (RNE
103345) and the Woodleigh Hall (H0179). Further sites of historical
archaeological significance within the corridor have also been recorded during
field investigations to date, including former house sites and timber bridges.
Towns in the vicinity of the grid connection corridor include Dalyston, Kilcunda,
Woolamai, Almurta, Glen Forbes and Kernot. A number of community facilities
are present in the region, including the Bass Coast Rail Trail, Williamsons Beach
and Kilcunda Beach, Woolamai Racecourse, recreation reserves, community
halls, schools and a church. The transmission line would also be constructed
near some residential dwellings.
15.3 Construction of the Power Supply
Construction activities for the grid connection would largely include vegetation
clearance, earthworks, trenching, stockpiling, excavation, truck movements, use
of machinery and some chemical storage and hazardous materials handling. The
transmission line would require construction of towers or poles and stringing of
conductors between these structures. The 66 kV lines would be installed as
underground cables between the Woolamai terminal station and the
Desalination Plant site. As well as the Woolamai terminal station, one more
terminal station will be constructed at Tynong North. The Tynong North terminal
station will connect to the existing transmission network and the Woolamai
terminal station will be used to step down the voltage for the Desalination Plant.
Chapter 15 Summary of effects of the Power Supply 15-3
Ground disturbance during construction has the potential to disturb both
Aboriginal and historical cultural heritage sites. A number of previously recorded
and newly discovered Aboriginal and historical sites have been identified along
the grid connection corridor. Further sites are expected to be discovered as part
of detailed surveys for development of the Cultural Heritage Management Plan
(CHMP). Works could potentially disturb a number of these sites.
Firstly, most of the excavation required for the construction of the overhead
transmission line would be restricted to the immediate area for each tower or
pole. With less ground disturbance than trenching, there is the flexibility to
avoid known sites through siting of transmission structures and there is a lower
probability of encountering undiscovered Aboriginal sites. A Cultural Heritage
Management Plant (CHMP) would be developed, in consultation with the
Registered Aboriginal Party (RAP) applicants, to avoid, minimise and manage
impacts to Aboriginal cultural heritage. The CHMP must be submitted to and
approved by Aboriginal Affairs Victoria before works commence. Additionally,
the PRs require protection of sites at risk of accidental damage during
construction and require implementation of design to avoid sites of high
significance. Application of the PRs is expected to minimise any impacts on
Aboriginal cultural heritage sites.
Historical sites are likely to be far fewer in number than Aboriginal sites and are
easier to avoid during construction, as they are typically infrequent, more
discrete entities. As with Aboriginal cultural heritage, impacts to historical sites
will be minimised through application of the PRs, including a requirement to
design the extent of works to avoid known sites and protect sites that are at risk
of accidental damage during construction.
15-4 Chapter 15 Summary of effects of the Power Supply
Similar to other linear infrastructure construction projects, construction of the
grid connection will create some noise, vibration, dust and vehicular emissions.
In general, these emissions are expected to be within the range expected for
construction projects of this scope. Specialist investigations have been
conducted to characterise these emissions and to confirm that these emissions
will be temporary and restricted in extent. For example, modelling of possible
dust emissions during construction of the transmission line shows that dust
levels will be below the critical level for nuisance dust complaints beyond 175
metres from the construction site. Although some emissions would be produced
during construction, these activities will be short-term in any one location (since
construction will move through the corridor) and any effects on people and the
environment will be minimal and temporary. Furthermore, the PRs will be
implemented to minimise the effects of noise, vibration, dust and other air
emissions on all receptors.
During excavation activities, potential acid sulfate soils may be encountered in
limited areas along the grid connection corridor: along the Powlett River and in
areas of drained swamp east of Koo Wee Rup, though this risk is considered to
be unlikely. Management of acid sulfate soils is common for construction
projects of this nature and will be managed through the PRs.
Giant Gippsland Earthworm habitat has been identified along the grid connection
corridor and therefore excavation has potential to directly affect this species.
However, it is considered unlikely that works will impact this species as Giant
Gippsland Earthworm habitat is generally located within 40 metres of streams
and waterways, and the transmission structures would be located to span
waterways and areas of suitable habitat. Since the corridor crosses
predominately agricultural land dominated by introduced vegetation, which is
unlikely to support threatened fauna species, construction is unlikely to affect
other EPBC or FFG listed species. Final design of the grid connection would aim
to avoid impacts to significant species, and any potential impacts would be
managed through the PRs. The PRs require implementation of methods to
manage stormwater, noise, light spill, vehicle movements, dust, and weeds and
open trenching in order to limit impacts on flora and fauna.
Chapter 15 Summary of effects of the Power Supply 15-5
Construction of the grid connection, particularly the underground cables, may
require some interactions with surface waters and groundwaters. Construction
could require some dewatering, but this is likely to be localised and temporary.
As already noted, the transmission line would span waterways with minimal
interactions between transmission line construction and surface water. Poles /
towers will be offset from waterways as agreed with the relevant water
authorities. Pursuant to the Performance Requirements, the Project will develop
and implement construction methods and site rehabilitation plans to the
satisfaction of the relevant water authority that seek to protect habitat values of
designated waterways under the Water Act 1989 and waterways that play an
important role in flood mitigation.
Construction activities for the grid connection could cause a temporary and
localised disruption to some roads and recreational areas. Any interactions will
be minimal since construction would move progressively along the corridor and
rehabilitation would occur in the wake of grid connection installation. Overall,
any impact on facilities and recreational activities is likely to be minor due to the
short time period of construction and since the PRs specify development of a
traffic management strategy, a rehabilitation plan and a construction workforce
accommodation strategy.
The potential impacts of construction on farming activities include temporary
loss of production, severance where the construction corridor isolates an area
for use, capital improvements loss, spread of soil borne pathogens such as the
Potato Cyst Nematode (PCN) and inadequate rehabilitation. Impacts to farming
activities will be managed through implementation of relevant Project
Requirements (PRs) which require design to minimise impact through detailed
siting of infrastructure, compliance with protocols to prevent the spread of PCN
and appropriate site rehabilitation.
15-6 Chapter 15 Summary of effects of the Power Supply
15.4 Operation of the Power Supply
Operational activities for the Power Supply would mainly involve maintenance
activities, which could require some truck and vehicle movements. The terminal
stations for the grid connection will generate some noise and vibration, but
other emissions such as dust are expected to be minimal since truck movements
would be infrequent and any dust would be much less than emissions generated
during construction. The terminal stations would be located and designed to
comply with EPA noise guidelines and modelling already shows that by locating
and designing the stations, operational noise would be below the operational
noise goals for the EPA Victoria guidelines for noise in Country Victoria at all
nearby properties. Therefore, noise and vibration are not expected to be an
ongoing issue for the Power Supply.
Since the environmental disturbance will be mostly restricted to the construction
period, it is expected that there will be no ongoing effects on terrestrial
ecosystems, aquatic ecosystems and cultural heritage during operation.
Maintenance activities will need to be managed to limit the potential impact to
terrestrial flora and fauna, including vehicle movements, dust, noise and the
introduction of weeds and pests. Appropriate management during construction
would minimise any possible impacts on surface water and groundwaters
including a rehabilitation plan to restore the pre-construction landscape.
The transmission line will include permanent infrastructure on the landscape
including poles or towers, powerlines and terminal stations. This will change the
amenity of the area. The alignment has been selected to avoid dense
populations of people and sensitive land uses. A visual impact assessment
concludes that the transmission line would be visible from a number of publicly
accessible viewpoints and residencies along the alignment. The impact on visual
amenity from the transmission line depends on the type of infrastructure and
the adjacent land use. Steel poles have been considered as an alternative to
steel towers which would lower the visual impact in sensitive landscapes. The
assessment of residential properties shows that the grid connection would have
a moderate to high impact on the visual amenity of residents. The PRs address
this possible change in amenity by requiring design and siting of the grid
connection to limit visual impacts on residential properties and publicly
accessible locations.
Chapter 15 Summary of effects of the Power Supply 15-7
An easement will be acquired for the transmission line and subtransmission
cables, and land acquisition will be required for the terminal stations. The
transmission line alignment would intersect some highly productive agricultural
land in the Koo Wee Rup area. The alignment across this area has the potential
to compromise irrigation efficiency as it may restrict irrigation within the
easement. As a result, some land may be removed from irrigation and suffer a
loss in productivity, the potential earning rate and ultimately in land value.
Compensation (including disruption costs) is payable under the Land Acquisition
Compensation Act 1986 (Vic) for acquired easements. Some activities would be
largely unaffected by the easement; livestock grazing and other typical
agricultural activities that do not require irrigation methods discussed above
should be able to resume once construction and rehabilitation have been
completed. Cropping which requires irrigation could still be undertaken, provided
modifications were undertaken to practices and equipment. The PRs require
development of rehabilitation planning with individual private landowners prior
to disturbance of private land. In general, the transmission line corridor will be
progressively rehabilitated and any potential impacts on land use of the
easement after construction will be managed through the PRs and the Land
Acquisition and Compensation Act 1986 (Vic).
15.5 Conclusions
The grid connection would involve construction and operation of infrastructure
that is common in Victoria. Firstly, sites and alignments have been sited and
designed to avoid areas of sensitivity. Construction impacts would be short lived
and similar to those for other linear infrastructure projects. These will be
managed through the PRs and will conform to all applicable policies, legislation
and guidelines, as well as implementing best practice measures to further
reduce the construction impact.
Once constructed, the transmission line corridor would be rehabilitated.
Operational activities would largely be restricted to routine maintenance. Any
potential impacts on land use within the easement will be appropriately
managed through PRs and the Land Acquisition and Compensation Act 1986. As
the Power Supply would be designed in accordance with legislation, and in
particular EPA policies relating to noise, it is expected that there will be minimal
impact on the surrounding environment and community.
15-8 Chapter 15 Summary of effects of the Power Supply