Embed
Email

WOL 20ESD 20Tool_final_v1_4Sep2006

Document Sample
WOL 20ESD 20Tool_final_v1_4Sep2006
Shared by: HC11111110257
Categories
Tags
Stats
views:
0
posted:
11/11/2011
language:
English
pages:
48
Version No. 1

DEFENCE GREEN BUILDING REQUIREMENTS PART 1 Issue Date: 4 Sep 2006

WOL (WHOLE OF LIFE) COSTING FOR ESD INITIATIVES IN DBC Amendment Dates:

Review Date: Mar 2007





Purpose

The Commonwealth Procurement Guidelines require that value for money should be evaluated on a whole-of-life basis. The WOL

Costing Tool for ESD Initiatives in the Detailed Business Case (DBC) will provide guidance on the appropriate parameters for a WOL

investigation. It will:



n Present key definitions

n Formulate and present an approach which allows for capture of non-financial determinants

n Provide advice for criteria that are relevant for determining WOL for various building and system elements

n Provide a sample WOL calculation for a lighting system





Use

The WOL Costing Tool will be utilised during the DBC stage as a means to provide accurate costings and inform design decision-

making as various options are considered to meet the Defence Green Building Requirements (GBR) Part 1. Note that WOL costing is

synonymous with life cycle costing; however life cycle analysis, which captures extensive non-financial benefits and typically takes a

"cradle to cradle" approach is a separate exercise altogether and the terms should not be confused. Information on life cycle analysis is

presented in the following page.





The Tool will be utilised primarily by quantity surveyors in order to provide accurate cost estimates to Defence and to other project

team members. It can also be utilised by other external project team members as an informal resource to assist in narrowing down

design and system choices as the project moves toward 30% (approximately) design completion. The Tool will also assist Defence

project staff in reviewing design decisions and costings put forward by the project team.



The WOL tool can be used for both minor and major projects.









WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

Terms and Definitions

The following terms and definitions are provided for the benefit of consistency of approach when undertaking a WOL costing.



Item Description

Capital cost All costs associated with the initial procurement including planning, design, construction and commissioning. These cost

are usually non-recurring, though will need to capture replacement costs if the effective life of the element is less than the

effective life of the project. Refer Effective Life below.

Discounted cashflow Presentation of future cash flow cost to a common time base (i.e. present day) using discounting techniques to allow

comparable cost comparisons to be made.

Discount rate The rate reflecting the time value of money that is used to convert benefits and costs occurring at different times to the

equivalent cost at common point in time, and is normally expressed as a percentage per annum.

Effective Life The period of time after which it becomes more economical to replace rather than to maintain a system or component.

Can be referred to as "indicative product life."



In an WOL calculation, if the effective life of the product or element is less than the project effective life, additional

capital expenditure is required to replace the element and needs to be captured as a capital cost.

Elements A portion of the project that fulfils a particular physical purpose.

Net Personnel and Operating NPOC is the difference between future operating costs and current funded operating costs associated with a capability,

Costs (NPOC) facility, system or specific item of equipment. It reflects the net difference between the cost estimates to operate a new,

upgraded or replacement capability offset by the guidance available to operate the current capability, across all affected

Groups.

Net Present Value (NPV) The discounted cost of the flow of all expenses including capital outlay over the evaluation period for the building

component under consideration.

Non-discounted cash flow Presentation of anticipated expenditure over the evaluation period based on current rates.

Recurrent cost Combination of ongoing costs such as operating costs inclusive of energy, water, waste, maintenance costs such as

corrective and replacement, and garrison support costs such as cleaning.

Residual Value The recoverable value of a component at the termination of the evaluation period, expressed as a negative cost.



Value of recoverable materials generally based on quantity of materials involved; it is up to the discretion of the user to

determine of the quantity being considered for the project is viable to cost as a recoverable asset. However, take back

versus materials sent for disposal should be quantified.

Sensitivity Analysis Testing the outcome of an evaluation by altering the values of key factors such as the discount rate, the effective life or

others about which there might be uncertainty.









WOL Costing









WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing can be defined as the total of the direct/indirect, recurring/non-recurring, fixed/variable financial costs to the Commonwealth arising out of, or

in any way in connection with, the Works over the whole life of the Works including the costs of designing and constructing the Works prior to Completion

and operating and maintaining the Works after Completion.



The objective of WOL costing is to assist in decision making by providing a means of comparing different option costs. WOL objectives in a defence project

means balancing:

(a) WOL Cost;

(b) the useful life of the Works;

(c) the reliability and availability for use of the Works throughout their useful life;

(d) the operability and maintainability of the Works throughout their useful life;

(e) the value for money achieved by the Commonwealth from the design, construction, operation and maintenance of the Works;

(f) the achievement of the ESD Principles; and

(g) the achievement of the specific additional matters (if any) relating to WOL specified in the Contract Particulars

Typically WOL option cost data is inputted into a decision model which considers factors such as a discount rate, costs / rates for energy, water charges, cost

escalation (only for items or instances over and above the anticipated rate of inflation), etc. Provided inflation for all costs is approximately equal, the

calculation should exclude cost escalation impacts when undertaking WOL costing.



WOL costing may initially be performed early in the design process when data with limited accuracy is available (though will be updated as more accurate

data becomes available), which may impact on the overall analysis outcome. Sensitivity analysis techniques can be applied to the decision model to

measures how expected values will be affected by variation of critical data inputs. Data points that can be subject to a sensitivity analysis include capital

cost, discount rate and energy rate. The values are chosen to reflect the level of uncertainty for the data. For example the sensitivity analysis may consider the

effects of a +/- 10% variation in capital cost.



WOL cost information and effective product life typically come from various sources such as: historical data, manufacturers’ advice, Defence advice

(including discount rate based on Defence recommended rate), industry cost guides, industry guides (e.g. AIRAH, ASHRAE, CIBSE) and ESD best practice

resources. As the project is developed the WOL costing is refined by reviewing the additional details developed for selected options against previous data

and assumptions.



The flowchart below describes the steps and considerations that are part of a WOL investigation. WOL costing allows for:









Model of discounted WOL Costing









WOL costing for ESD initiatives in DBC v1 4Sep2006

The below flowchart demonstrates the process for evaluating whole of life costs for different building elements / design options, allowing for an equitable

comparison to be made. The chart also demonstrates that, when considering products and elements from an ESD perspective, non-financial determinants

such as ecological and social values can be applied to the decision-making. Examples of ecological and social values might include demonstration of

leadership in sustainable environmental management, water savings, enhancement or protection of flora and fauna, recycled content and recyclability,

improved indoor environmental quality, materials from local sources, 'triple bottom line' record / reporting of suppliers, improved productivity, preserved

cultural and heritage resources, etc. These measures should be brought in as an adjunct to the WOL calculation (as WOL traditionally deals with financial

parameters only). Additionally, different weightings can be applied to the economic, ecological and social measures to ensure that a balance is reached that

suits the needs of the user.



Determine system or

element to be costed





Nominate options to be

compared







Initial

Discount rate

Capital Cost





Component Capital Cost

replacement based on Non-discounted cash Discounted Cash flow NPV Sensitivity Analysis

effective life flow





Recurrent Costs:

Maintenance; Additional Potential Option Costs

Utility Costs; Comparison:

Cleaning; etc Non-financial

Design Reports

determinants

Evaluate and apply:

- ecological values Recommended Option Costing Plan

- social values

NPOC, Maintenance

Plan, Post Occupancy

Review



Further information on Whole of Life or life cycle costing may be found at:

Australian National Audit Office Better Practice Guide:

http://www.anao.gov.au/WebSite.nsf/Publications/4A256AE90015F69B4A256B57001DC439/$file/15543_ANAO+LCC+guide2.pdf

AS3595 - Energy management programs— Guidelines for financial evaluation of a project

Whole Building Design Guide: http://www.wbdg.org/design/lcca.php

US Department of Energy - Building Technologies Toolbox: http://www.eere.energy.gov/buildings/info/design/wholebuilding/costanalysis.html









WOL costing for ESD initiatives in DBC v1 4Sep2006

Life Cycle Assessment



For the purpose of evaluating ESD benefits, it is possible to undertake a life cycle assessment (a k a life cycle analysis, eco-balance). A Life Cycle

Assessment (LCA) systematically describes and assesses all material, energy and ecological flows related to a product or process from a cradle to grave

perspective. There are two main steps in an LCA.



1.) Describe which emissions will occur and which raw materials are used during the life of a product. This is usually referred to as the inventory step.

2.) Assess what the impacts of these emissions and raw material depletions are. This is referred to as the impact assessment step.



A complete life cycle assessment will combine the extensive environmental / ecological analysis with costing information to inform decision-making around

product selection. All stages in the life of a product are analysed: raw material acquisition, manufacture, transportation, installation, use, and recycling and

waste management. Economic performance should be measured using whole of life or life cycle costing methods which covers the costs of initial

investment, replacement, operation, maintenance and repair, and disposal.



Note that a proper LCA is a complex and costly undertaking that requires enormous volumes of data and extensive investigations to be done

objectively. For more information, the following references can be searched:



US Environmental Protection Agency - Systems Analysis Research: http://www.epa.gov/ORD/NRMRL/std/sab/lca/index.html

Ecospecifier: http://www.ecospecifier.org/knowledge_base/downloads/life_cycle_analysis

Life Cycle Assessment links: http://www.life-cycle.org/

American Center for Life Cycle Assessment: http://www.lcacenter.org/









WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL" Rules of Thumb"

The WOL "Rule of Thumb" table below provides a guidance on a range of ESD design considerations and complementary elements. (This table is not an exhaustive list

and there may be other elements to consider.) Effective ESD design usually involve a combination of elements rather than a single element or components in isolation.

Therefore effective WOL option assessment needs to consider the combined effect of an ESD option. For example the assessment of double glazed windows should

consider the reduction in energy used by the mechanical system.



The required effective life of a building is usually defined in the FDB. The WOL options need to consider the relationship between the effective life of the building and

the effective life of the components / complimentary elements being considered in WOL options.



In WOL costing for ESD initiatives, each building will have a number of areas that can be assessed:

o Building fabric,

o Internal finishes,

o Structures,

o Fitments,

o Building Services,

o Sitework



The key to the complimentary elements is found below and is based on the Australian Institute of Quantity Surveyors definition of elements. The column is meant to

indicate that whilst WOL calculations may be performed on individual elements only, it is more likely and necessary that the WOL investigation capture considerations

from other elements. For example, WOL costing of glazing will need to be informed by other building fabric issues and the heating and cooling system.





Note that the effective product life listed is indicative only and confirmation is required for each element / component being considered. Further, indicative product life

(or, the economic life) should not be confused with functional and technological obsolescence. Whilst in reality, many products, systems and finishes will be replaced

before the end of their economic life, there is no consistent nor objective means to cost these considerations into a WOL calculation and therefore they cannot be factored.





ESD Design Description Complimentary Effective Product Recurrent Costs Residual Value

Consideration Elements Life (indicative only)









WOL costing for ESD initiatives in DBC v1 4Sep2006

Structures

Substructure SB, CL, UF, RF 25 + years Protective coatings Material recovery (Timber or

steel framing, floor lining),

recyclable material recovery

(Concrete, Steel

reinforcement)



Upper Floors & SB, CL, UF, RF 25 + years Protective coatings Material recovery (Timber or

Columns steel framing, floor lining),

recyclable material recovery

(Concrete, Steel

reinforcement)



Building Fabric

Glazing WW, EW, AC 25 + years Moving part and seal Framing material recovery

replacement, paint (aluminium, timber)

finishes, energy cost





External Walls WW, AC, WF, CL, 25 - 25 + years Seals, finishes, fixings, Material recovery (metal,

SB energy cost timber)





Roof SB, CL, EW, AC 25 - 25 + years Seals (roof fabric / Material recovery (metal

membrane), landscaping, cladding, steel framing)

energy cost



Internal Finishes

Floor coverings Carpet: 5 - 15 Finishes / re-finishes; Material recovery (timber) ,

Linoleum, vinyl, fixings, cleaning regimes carpet leasing / take-back

rubber: 15 - 20 policies

Timber: 25 +

Tiling, terrazzo - 25 +

Concrete - 25 +









WOL costing for ESD initiatives in DBC v1 4Sep2006

Wall finishes EW, NW Paint: 5 - 10 Material recovery (timber)

Timber panelling: 25

+

Vinyl: 25 +

Wall fabrics: 15

Fitments

Joinery 25 + years Hardware / moving parts, Material recovery (timber)

finishes / re-finishes



Building Services

Hydraulics XR, XK, XW, XD, Pipes 25 + years Fittings and moving Material recovery (copper

PD, WS Fixtures 20 - parts, seals, cleaning pipes)

25 years regimes, pumps

(servicing), water costs

Lighting WW, AC, EW Wires 25 + years Replacement of lamps, Material recovery (metal)

Fixtures 20 - 25 ballasts, covers /

years diffusers, control

component failure /

upgrade, energy costs

HVAC EW, WW, RF, LP, Refrigeration plant: Component Material recovery (metal)

GS, WS, CE 15 - 20 years maintenance, energy

Fans: 20 - 25 years costs, water costs,

Pumps, motors: 20 - cleaning costs, ongoing

25 years operational replacements

Cooling towers: 10 - (filters, belts, lubricants,

25 years etc.)

Packaged air

handling: 15 - 20

years

Radiators: 25 + years

Boilers: 20 - 25 years

Minor plant: 15 - 20

years







Siteworks









WOL costing for ESD initiatives in DBC v1 4Sep2006

Roads and XK, XL, XP 25 + years Landscaping

footpaths, maintenance /

stormwater retention remediation, sealing /

topping, water cost







Definition of Elements



00 PR PRELIMINARIES

SUBSTRUCTURE

01 SB SUBSTRUCTURE

SUPERSTRUCTURE

02 CL COLUMNS

03 UF UPPER FLOOR

04 SC STAIRCASES

05 RF ROOF

EXTERNAL FABRIC AND FINISHES

06 EW EXTERNAL WALLS

07 WW WINDOWS

08 ED EXTERNAL DOORS

INTERNAL FABRIC AND FINISHES

09 NW INTERNAL WALLS

10 NS INTERNAL SCREENS & BORROWED LIGHTS

11 ND INTERNAL DOORS

12 WF WALL FINISHES



13 FF FLOOR FINISHES

14 CF CEILING FINISHES

FITMENTS

15 FT FITMENTS

16 SE SPECIAL EQUIPMENT

SERVICES

17 SF SANITARY FIXTURES

18 SD SANITARY PLUMBING

19 WS WATER SUPPLY

20 GS GAS SERVICE









WOL costing for ESD initiatives in DBC v1 4Sep2006

21 SH SPACE HEATING

22 VE VENTILATION

23 EC EVAPORATIVE COOLING

24 AC AIR CONDITIONING/MECHANICAL SERVICES

25 FP FIRE PROTECTION

26 LP ELECTRIC LIGHT & POWER

27 CM COMMUNICATIONS

28 TS TRANSPORTATION SERVICES

29 SS SPECIAL SERVICES

CENTRALISED ENERGY SYSTEMS

30 CE CENTRALISED ENERGY SYSTEM

ALTERATIONS

31 AR ALTERATIONS

SITEWORKS

32 XP SITE PREPARATION



33 XR ROADS, FOOTPATHS & PAVED AREAS

34 XN BOUNDARY WALLS, FENCING & GATES

35 XB OUTBUILDING

36 XL LANDSCAPING & IMPROVEMENTS

EXTERNAL SERVICES

37 XK EXTERNAL STORMWATER DRAINAGE

38 XD EXTERNAL SEWER DRAINAGE

39 XW EXTERNAL WATER SUPPLY

40 XG EXTERNAL GAS

41 XF EXTERNAL FIRE PROTECTION

42 XE EXTERNAL ELECTRIC LIGHT & POWER

43 XC EXTERNAL COMMUNICATIONS

44 XS EXTERNAL SPECIAL SERVICES

45 XX ALTERATIONS & RENOVATIONS TO EXT WORKS

SPECIAL PROVISIONS

46 YY SPECIAL PROVISIONS (Provisional Sums)









WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

tary elements. (This table is not an exhaustive list

han a single element or components in isolation.

assessment of double glazed windows should







hip between the effective life of the building and









definition of elements. The column is meant to

at the WOL investigation capture considerations

d the heating and cooling system.





being considered. Further, indicative product life

products, systems and finishes will be replaced

L calculation and therefore they cannot be factored.





Related ESD considerations:









WOL costing for ESD initiatives in DBC v1 4Sep2006

Local material sourcing, recycled content









Local material sourcing, recycled content









Daylighting, natural ventilation, thermal

comfort, natural resource extraction, local

material sourcing, PVC minimisation,

greenhouse gas emissions



Natural resource extraction, local material

sourcing, PVC minimisation, thermal

comfort, greenhouse gas emissions



Recycled content, local ecology,

stormwater emissions (site damage and

downstream impacts), greenhouse gas

emissions



Local sourcing, recycled content, PVC

minimisation, use of natural materials /

natural resource management, VOCs /

indoor environmental quality, end of life

provisions / recyclability









WOL costing for ESD initiatives in DBC v1 4Sep2006

Local sourcing, PVC minimisation, use of

natural materials / natural resource

management, VOCs / indoor

environmental quality, end of life

provisions / recyclability



Local sourcing, PVC minimisation, indoor

environmental quality / formaldehyde

minimisation



Natural resource management, emissions

(stormwater and sewage)





Indoor environmental quality, greenhouse

gas emissions









Indoor environmental quality, natural

resource management, greenhouse

emissions









WOL costing for ESD initiatives in DBC v1 4Sep2006

Local ecology, stormwater emissions (site

damage and downstream impacts)









WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

WOL costing for ESD initiatives in DBC v1 4Sep2006

Sample WOL Cost Comparison (simplified format)

Investigation of three lighting system alternatives





ITEM / OPTION: Standard Lighting System

Description: lighting system with minimum specialist switching.







NON-DISCOUNTED CASHFLOW





SECTION Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20 Year 21 Year 22 Year 23 Year 24 Year 25 TOTAL



Capital Cost 100,000 - - - - - - - - - - - - - - - - - - 50,000 - - - - - 150,000

Recurrent 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 250,000

Others (Residual Value) -

NET COST 100,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 60,000 10,000 10,000 10,000 10,000 10,000 400,000







DISCOUNTED CASHFLOW 8% (Discount Rate)

- 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25



SECTION Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20 Year 21 Year 22 Year 23 Year 24 Year 25 TOTAL



Capital Cost 100,000 - - - - - - - - - - - - - - - - - - - 10,727 - - - - - 110,727

Recurrent - 9,259 8,573 7,938 7,350 6,806 6,302 5,835 5,403 5,002 4,632 4,289 3,971 3,677 3,405 3,152 2,919 2,703 2,502 2,317 2,145 1,987 1,839 1,703 1,577 1,460 106,748

Others - - - - - - - - - - - - - - - - - - - - - - - - - - -



NET COST 100,000 9,259 8,573 7,938 7,350 6,806 6,302 5,835 5,403 5,002 4,632 4,289 3,971 3,677 3,405 3,152 2,919 2,703 2,502 2,317 12,873 1,987 1,839 1,703 1,577 1,460 217,475









ITEM / OPTION: Standard lighting system with control switching

Description: lighting system with control switching such as light sensors







NON-DISCOUNTED CASHFLOW





SECTION Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20 Year 21 Year 22 Year 23 Year 24 Year 25 TOTAL



Capital Cost 110,000 - - - - - - - - - - - - - - - - - - - 50,000 - - - - - 160,000

Recurrent - 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 212,500

Others -

NET COST 110,000 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 8,500 58,500 8,500 8,500 8,500 8,500 8,500 372,500





DISCOUNTED CASHFLOW 8% (Discount Rate)

- 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25



SECTION Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20 Year 21 Year 22 Year 23 Year 24 Year 25 TOTAL



Capital Cost 110,000 - - - - - - - - - - - - - - - - - - - 10,727 - - - - - 120,727

Recurrent - 7,870 7,287 6,748 6,248 5,785 5,356 4,960 4,592 4,252 3,937 3,646 3,375 3,125 2,894 2,680 2,481 2,297 2,127 1,970 1,824 1,689 1,563 1,448 1,340 1,241 90,736

Others - - - - - - - - - - - - - - - - - - - - - - - - - - -



NET COST 110,000 7,870 7,287 6,748 6,248 5,785 5,356 4,960 4,592 4,252 3,937 3,646 3,375 3,125 2,894 2,680 2,481 2,297 2,127 1,970 12,551 1,689 1,563 1,448 1,340 1,241 211,463







ITEM / OPTION: High Technology Lighting and Control System

Description: High technology light fitting with special lighting control and auto dimmer system.







NON-DISCOUNTED CASHFLOW





SECTION Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20 Year 21 Year 22 Year 23 Year 24 Year 25 TOTAL

Capital Cost 125,000 - - - - - - - - - - 34,000 - - - - - - - 30,000 - - - - - 189,000

Recurrent - 7,200 7,200 7,200 7,200 7,200 7,200 7,200 7,200 7,200 7,200 7,200 7,200 7,200 7,200 7,200 7,200 7,200 7,200 7,200 7,200 7,200 7,200 7,200 7,200 7,200 180,000

Others -

NET COST 125,000 7,200 7,200 7,200 7,200 7,200 7,200 7,200 7,200 7,200 7,200 41,200 7,200 7,200 7,200 7,200 7,200 7,200 7,200 7,200 37,200 7,200 7,200 7,200 7,200 7,200 369,000





DISCOUNTED CASHFLOW 8% (Discount Rate)

- 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25



SECTION Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20 Year 21 Year 22 Year 23 Year 24 Year 25 TOTAL



Capital Cost 125,000 - - - - - - - - - - 14,582 - - - - - - - - 6,436 - - - - - 146,018

Recurrent - 6,667 6,173 5,716 5,292 4,900 4,537 4,201 3,890 3,602 3,335 3,088 2,859 2,647 2,451 2,270 2,102 1,946 1,802 1,668 1,545 1,430 1,324 1,226 1,135 1,051 76,858

Others - - - - - - - - - - - - - - - - - - - - - - - - - - -



NET COST 125,000 6,667 6,173 5,716 5,292 4,900 4,537 4,201 3,890 3,602 3,335 17,670 2,859 2,647 2,451 2,270 2,102 1,946 1,802 1,668 7,981 1,430 1,324 1,226 1,135 1,051 222,877









Notes:

1. Cost escalation was excluded in this WOL analysis.









WOL costing for ESD initiatives in DBC v1 4Sep2006

Sample WOL Cost Comparison (simplified format)

2. Breakdown of capital costs, recurrent costs and others should be annotated to provide transparency in the assumptions and calculations. Eg. additional capital expenditure is shown in Year 20, reflecting the effective life of the system being considered.



3. Note that the second option provides the best financial benefit; however, in this simplified example, the benefits that may accrue from reduced heat load from the lighting system and its

impact on the HVAC plant should be considered. Additionally, non-financial determinants such as indoor environmental quality and greenhouse gas emissions should be taken into account

when comparing the systems to determine overall benefits of each option.









WOL costing for ESD initiatives in DBC v1 4Sep2006


Related docs
Other docs by HC11111110257
gepart1
Views: 0  |  Downloads: 0
resume_eric_tachibana_09feb09
Views: 0  |  Downloads: 0
225chap12
Views: 0  |  Downloads: 0
Roberts_Environment_Presentation_NABC2009
Views: 0  |  Downloads: 0
Fuels_Case_Study
Views: 0  |  Downloads: 0
E2009 P9 2097049 Presentation LucGagnon 2009
Views: 0  |  Downloads: 0
41534
Views: 0  |  Downloads: 0
green_plants_1
Views: 0  |  Downloads: 0
qanda
Views: 0  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!