WA01B - DSP Forensic Science Laboratory
Document Sample


WA01B
Forensic Science Laboratory
Department of State Police
Forensic Science Laboratory (Baltimore)
GO Bonds $796,000 Recommendation: Approve
Bill Text: Provide a portion of the funds to equip the new Forensic Science Laboratory.
Project Description: Build a new State Police crime laboratory. The current facilities do not
provide sufficient space or the capacity for expansion. The new lab will meet the needs of the
ballistics, photography, serology, chemistry, toxicology, trace evidence, questioned documents, latent
prints, and vehicular examination departments.
Comments: Construction of the State Police crime laboratory was scheduled to be completed on
September 16, 2005. The project was delayed in November and December 2004 because of delays in
the delivery of structural steel. There is a worldwide shortage of structural steel. This is an item that
affects the critical path of the construction project. The general contractor still hopes to recover from
the delay and is preparing a recovery schedule for the Department of General Services. At this time it
is likely that project completion will be delayed until October 2005. Equipment funds in the amount
of $784,000 were requested in fiscal 2005, but the General Assembly authorized the funds to be used
to cover additional construction related costs because the winning construction bid exceeded the
amount of funds previously authorized for the project. Since the crime laboratory is scheduled to be
completed in fiscal 2006, funds are now needed to equip the laboratory. The original request is now
increased to $796,000. There were price increases in some State Use Industries (SUI) individual
items and on the SUI price proposal for modular workstations.
For further information contact: James L. Stoops Phone: (410) 946-5530
Analysis of the FY 2006 Maryland Executive Budget, 2006
1
WA01B – Department of State Police
Project Data
($ in Millions)
Prior 2006 2007 2008 2009 2010
Description Authorization Request Estimate Estimate Estimate Estimate
Acquisition $2.000 $0.000 $0.000 $0.000 $0.000 $0.000
Planning 2.240 0.000 0.000 0.000 0.000 0.000
Construction 25.017 0.000 0.000 0.000 0.000 0.000
Equipment 0.000 0.796 0.000 0.000 0.000 0.000
Total $29.257 $0.796 $0.000 $0.000 $0.000 $0.000
Total Project Cost: $30,053,000 Cost Per Square Foot – Base: $267
With Escalation & Contingencies: $363.91
Gross Square Footage: 68,700 Net Usable Square Footage: 35,710
Approved Program Plan: Yes Estimated Completion Date: October 2005
Recommended Actions
Approve.
Executive’s Operating Budget Impact Statement
($ in Millions)
FY 2006 FY 2007 FY 2008 FY 2009 FY 2010
Estimated Operating Cost $0.276 $0.210 $0.210 $0.210 $0.210
Estimated Staffing 1 1 1 1 1
Analysis of the FY 2006 Maryland Executive Budget, 2005
2
WA01B – Department of State Police
The Department estimated increased costs of the new larger facility. The fiscal 2006 amount
includes the one-time cost of relocating scientific equipment (and subsequent recalibration), data, and
phone infrastructure. Operating costs include the salaries and fringe benefits of the building
engineer/building manager, building utilities as well as contractual services for HVAC, trash,
grounds, and other maintenance expenses.
Analysis of the FY 2006 Maryland Executive Budget, 2005
3