                                       Coppin State University
                                        University System of Maryland

New Health and Human Services Building (Baltimore City)
GO Bonds                          $47,587,000              Recommendation:   Approve


Bill Text: Provide funds to complete detailed design and construct the new Health and Human
Services Building.


Project Description: This project involves constructing a new 160,000 gross square foot building to
house 5 academic programs which are among the university’s core programs: nursing, criminal
justice, social work, applied psychology and rehabilitation counseling, and a portion of education.
The building will contain classrooms, laboratories, offices, diagnostic and treatment clinics, and other
necessary spaces to support these programs, and house the Graduate Studies Division. The fiscal
2006 budget includes additional design funds and construction funds.


Comments: Coppin has not had a major new building in over 25 years. The institution was planned
in the 1970s to accommodate 1,500 full-time day-equivalent students. Enrollment has increased by
over 40% to 2,151 since the 1970s, and another 20% increase is anticipated by 2013. Space deficits
in classrooms and laboratories constitute a significant percentage (over 50%) of existing space.

    Coppin specializes in fields such as teaching, nursing, law enforcement, and counseling that
require significant hands-on training. The nursing center, for example, is located in a row-house that
was not designed for the purpose. Moreover, Coppin’s facilities do not meet the “comparable and
competitive” standard prescribed in the partnership agreement between the State and the U.S.
Department of Education’s Office for Civil Rights. This project will help address parity between
historically black and traditionally white higher education institutions. The total cost of the project
includes a 9.8% A/E fee attributable to complexities in the project related to site work and
architecture. Specifically, this includes site master planning for 3 – 4 buildings and consolidating
properties, demolition of existing buildings, and a forensic specialty consultant.




For further information contact: Danielle M. Prendergast                               Phone: (410) 946-5530

                        Analysis of the FY 2006 Maryland Executive Budget, 2005
                                                   1
                                 RB27A – USM – Coppin State University

Project Data
                                               ($ in Millions)

                         Prior             2006          2007         2008            2009        2010
  Description         Authorization       Request       Estimate     Estimate        Estimate    Estimate


Acquisition                  $0.400          $0.000         $0.000      $0.000          $0.000      $0.000

Planning                       4.450          0.087          0.000       0.000           0.000       0.000
Construction                   0.000         45.500          0.000       0.000           0.000       0.000

Equipment                      0.000          0.000          4.500       0.000           0.000       0.000

Total                        $4.850         $47.587         $4.500      $0.000          $0.000      $0.000


Total Project Cost:                   $56,937,000     Cost Per Square Foot – Base:                    $165
                                                      With Escalation & Contingencies:                $202
Gross Square Footage:                    160,000      Net Usable Square Footage:                    89,800
Approved Program Plan:                       Yes      Estimated Completion Date:                 April 2008



Recommended Actions
   Approve.




                      Analysis of the FY 2006 Maryland Executive Budget, 2005
                                                 2
                               RB27A – USM – Coppin State University

Executive’s Operating Budget Impact Statement
                                            ($ in Millions)

                                          FY 2006       FY 2007        FY 2008    FY 2009    FY 2010



Estimated Operating Cost                     $1.000           $1.833     $1.894     $1.943     $1.999

Estimated Staffing                                  0            25          18        18          18

    Coppin estimates that operating costs will be primarily related to salary and wages for additional
staff, fuel and utility, and additional equipment costs.




                     Analysis of the FY 2006 Maryland Executive Budget, 2005
                                                3
                             RB27A – USM – Coppin State University

                                                                                          Appendix

                              Capital Project Cost Estimate Worksheet

Department:                 Coppin State University
Project Number:             RB27A
Project Title:              New Health and Human Services Building
Analyst:                    Danielle Prendergast

Structure
New Construction:         160,000 Sq. Ft. X           $165.00   Sq. Ft.   =            26,400,000
New Construction:                 0 Sq. Ft. X           $0.00   Sq. Ft.   =                     0
Renovation:                       0 Sq. Ft. X           $0.00   Sq. Ft.   =                     0
Renovation:                       0 Sq. Ft. X           $0.00   Sq. Ft.   =                     0
Built-in Equipment                                                                      1,000,000
Demolition                                                                                      0
Information Technology    160,000 GSF X                 $8.00 GSF =                     1,280,000
Telecommunications                                                                              0
Miscellaneous-Other     Asbestos Removal                                                  300,000
Miscellaneous-Other     Poor Soils                                                        885,000
Miscellaneous-Other                                                                             0
SUBTOTAL                                                                               29,865,000
Regional Factor:           100.0%                                                               0
SUBTOTAL                                                                               29,865,000
Escalation to midpoint:       3.08    Yrs. X             5.3%        =        16.33%    4,877,950
TOTAL COST OF STRUCTURE (Bid Cost)                                                     34,742,950


Site Work and Utilities
Site Improvements:    4,284,675 + regional factor + mid-point escalation                4,984,505
Utilities:            2,837,175 + regional factor + mid-point escalation                3,300,580
PROJECT SUBTOTAL (Bid Cost)                                                            43,028,036


Fees and Miscellaneous Costs
Green Building Premium                                   0.0%                                   0
Total Construction Contingency                           5.0%                           2,151,500
Inspection Cost:                                         2.2%                             946,660
Miscellaneous:               CM Cost Construction Share                                   645,450
Miscellaneous:               Equipment Commissioning                                      645,450
Miscellaneous:               CPM/ Schedule                                                 81,000
Miscellaneous:               Information Technology Equipment                           2,500,000
Miscellaneous:               Movable Equipment                                          2,000,000
A/E Fee through construction phase @                     9.8%                           4,536,364
TOTAL COST OF PROJECT                                                                  56,534,460

Base cost per new square foot                                                               $165
Adjusted cost per new square foot (incl. escalation, contingencies & Green Bldg.)           $202
Base cost per renovated square foot                                                           $0
Adjusted cost per renovated square foot (incl. escalation, conting. & Green Bldg.)            $0



                  Analysis of the FY 2006 Maryland Executive Budget, 2005
                                             4