Embed
Email

DE0201D - BPW DGS Construction Contingency Fund

Document Sample
DE0201D - BPW DGS Construction Contingency Fund
DE02.01D

General State Facilities

Board of Public Works/Department of General Services



Construction Contingency Fund (Statewide)

GO Bonds $2,250,000 Recommendation: Approve





Bill Text: Bill Text: Provide funds to be credited to the Construction Contingency Fund to be

administered in accordance with Section 3 -609 of the State Finance and Procurement Article.





Project Description: The Construction Contingency Fund (CCF) provides funds for State

construction projects that exceed their previously authorized amounts or to cover change orders

during project construction. These funds may not be used for non-authorized projects.





Comments: The State Finance and Procurement articles allow a maximum of 1.25% of the current

year general obligation bond appropriation to go to the CCF. That maximum comes to

$8.313 million in fiscal 2006. As shown in Exhibit 1, the CCF balance is $3.675 million as of the

end of calendar 2004. The fiscal 2006 allowance brings the fund balance to $5.9 million which

should be sufficient for anticipated needs.



The Department of General Services (DGS) general close-out policy when capital projects are

completed with remaining funds is as follows: any amount between $10,000 and $100,000 is

transferred to the CCF; amounts under $10,000 go to the Bond Annuity Fund, and amounts over

$100,000 are de-authorized by the Department of Budget and Management (DBM). However,

recently DGS and DBM have transferred funds remaining from completed projects in excess of

$100,000 to the CCF rather than deauthorizing these funds. DGS should be prepared to discuss its

close-out policy and the reason why it has chosen to transfer amounts in excess of $100,000 to

the CCF rather than scheduling such funds for deauthorization.









For further information contact: Brian Baugus Phone: (410) 946-5530



Analysis of the FY 2006 Maryland Executive Budget, 2005

1

DE02.01D – BPW/DGS – General State Facilities



Exhibit 1

Calendar 2004 Fund Activity



Beginning Balance (January 2004) $1,403,621

Fund Transfer 950,000

Fiscal 2005 Appropriation 2,000,000

Subtotal Available Funds $4,353,621

Authorized Use in Calendar 2004

Bloomsbury Square Demolition and Parking Lot 198,200

140-bed housing unit at Eastern Correctional Institute 950,000

Total $1,148,200

Year End Balance $3,205,421

Source: Department of General Services









Fund Data

Prior Program Activity – All Fund Sources

($ in Millions)



FY 2001 FY 2002 FY 2003 FY 2004 FY 2005*



Encumbrances n/a $2.216 $2.457 $1.051 $430



Expenditures n/a 2.216 2.457 1.051 0.430

*As of 01/21/05





Authorization Summary

($ in Millions)



Funds Balances

To Be To Be

Fiscal Year Authorization Encumbered Expended Encumbered Expended



Prior Years $8.758 $7.758 $7.750 $1.000 $1.000



2005 2.000 0.000 0.000 2.000 2.000



Total $9.758 $7.758 $7.750 $3.000 $3.000









Analysis of the FY 2006 Maryland Executive Budget, 2005

2

DE02.01D – BPW/DGS – General State Facilities



Authorization Request

($ in Millions)



2004 2005 2006 2007 2008 2009 2010

Description Approp. Approp. Request Estimate Estimate Estimate Estimate



GO Bonds $1.000 $2.000 $2.225 $2.500 $2.500 $2.500 $2.500







Issues

1. Global Construction Costs Are Rising

World prices for construction materials have increased significantly in the past year. More

specifically there is a severe shortage of scrap metal which has caused a sharp increase in the cost of

structural steel and reinforcing bar. In the past year, prices for wide-flange structural steel beams

have increased over 7%, while prices for channel beams rose 5%. Rebar prices began climbing in

November 2003 and are now well over 10% above January 2004 prices. Scrap metal is the primary

raw material for “mini-mills” that produce most structural steel and rebar products in the United

States.



In addition to the increased cost of steel products, prices for concrete, lumber, plywood, gypsum

wallboard, copper, stainless steel, pipe, and fuel are all much higher than they were 12 to 18 months

ago. Typically, the cost of materials is calculated at approximately 40% of the overall cost of a

construction project, with the remaining 60% allocated to labor and equipment. This spike in

material costs could effect the 40% application by as much as an additional 15%, depending on the

types of construction materials being applied.



A number of capital projects have been recently bid or are scheduled for bidding in the next fiscal

year that will be affected by the sharp increase in material costs. Since the estimates that support

these projects were prepared prior to the spike in prices, these estimates did not include the impact

from the rising materials prices. DGS responds that projects recently bid, where the prices have

exceeded the estimates, include the Construction of Exhibits at the Banneker Douglas Museum in

Annapolis (a 20% increase), Improvements to the Maryland Dove Waterfront Site at Historic St.

Mary’s City (a 100% increase), and the Hammerman Area Beach Services Building at Gunpowder

State Park (a 50% increase).



DGS should update the committees concerning the current CCF fund balance and the

anticipated need to use the CCF during fiscal 2006 that serves as the basis for the proposed

fiscal 2006 appropriation.









Analysis of the FY 2006 Maryland Executive Budget, 2005

3

DE02.01D – BPW/DGS – General State Facilities



Recommended Actions

Approve.









Analysis of the FY 2006 Maryland Executive Budget, 2005

4


Other docs by winstongamso
2003-2004 Branch Campus (2000 Cohort)
Views: 1  |  Downloads: 0
Subcontractor Material Supplier Declaration
Views: 11  |  Downloads: 0
W10A00 - Maryland State Police[968]
Views: 6  |  Downloads: 0
RA01A - MSDE - State Library Resource Center
Views: 1  |  Downloads: 0
Transportation Trust Fund Overview
Views: 2  |  Downloads: 0
ZA00G - MICUA - Columbia Union College
Views: 2  |  Downloads: 0
Meetings & Minutes Minutes[277]
Views: 4  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!