Embed
Email

DB01A - HSMCC Heritage Project Maryland Dove

Document Sample
DB01A - HSMCC Heritage Project Maryland Dove
DB01A

Historic St. Mary’s City Commission



Waterfront Site Improvements (St. Mary’s County)

Recommendation: Approve with additional

GO Bonds $58,000

funds for construction.





Bill Text: Provide funds to design a new pathway to the Maryland Dove Waterfront Site.





Project Description: Construct a new pathway down a 30-foot steep embankment to the Maryland

Dove, a recreation of a 17th-century square-rigged ship. The new pathway will be an in-grade,

asphalt-surfaced pathway with switchbacks, which will accommodate children’s strollers and

wheelchairs. The project includes removing overgrown vegetation, burying power lines, adding

safety lights and guardrails, and placing interpretive signs along the pathway.





Comments: The Historic St. Mary’s City Commission (HSMCC) is requesting $58,000 in fiscal

2004 for planning that was deferred from fiscal 2003. The Maryland State Highway Administration

(MSHA), Chesapeake Bay Critical Areas Commission, and the Maryland Department of Natural

Resources have selected this site as an environmental wetlands mitigation project. They have

collaborated with HSMCC to provide partial survey of the Maryland Dove Site area and will assist

with site engineering, resulting in a lower construction cost for the pathway. HSMCC expects that

the Maryland State Highway Administration will contribute $40,000 for mitigation and planting.



The Maryland Dove Site is part of the Maryland Heritage Project (MHP), a joint multi-year

capital improvement program between HSMCC and St. Mary’s College of Maryland, adopted in

December 1999. The MHP plan includes projects that benefit both the college and HSMCC. This

project was included in the fiscal 2003 Capital Improvement Program as part of the MHP initiative

but was deferred until fiscal 2004.









For further information contact: Jessica E. Jordan Phone: (410) 946-5530



1

DB01A –Historic St. Mary’s City Commission



Project Data

($ in Millions)



Prior 2004 2005 2006 2007 2008

Description Authorization Request Estimate Estimate Estimate Estimate





Planning $0.000 $0.250 $0.000 $0.000 $0.000 $0.000



Total $0.000 $0.250 $0.000 $0.000 $0.000 $0.000





Total Project Cost: $250,000

Approved Program Plan: Yes Estimated Completion Date: March 2005







Recommended Actions

Approve with additional funds in the amount of $192,000 for constructions costs.



Funding for planning ($12,000) and construction costs ($238,000) is recommended in fiscal 2004

for several reasons. The project is currently ahead of schedule and in the last year’s Capital

Improvement Program (CIP), construction was originally planned for fiscal 2004. If funding is made

available, the project can be completed in fiscal 2004 at a lower cost than originally estimated, at

$250,000 rather than $400,000 later, because of substantial progress that is being made by the MSHA

in clearing the river embankment. The project should continue moving forward due to other available

funds and agency efforts: funds totaling $43,500 are available from previous capital projects that can

be used for archeology and power line burial as part of the construction work. HSMCC also received

a $12,000 grant from the local garden club that they will apply to this project. This path is the only

access to the Maryland Dove site and is host to approximately 40,000 visitors each year.



Appendix 1 and Appendix 2 are the comparison cost estimate worksheets. If the project is fully

funded in fiscal 2004, the costs are shown in Appendix 2.









2

DB01A –Historic St. Mary’s City Commission



Appendix 1

Capital Project Cost Estimate Worksheet



Department: Historic St. Mary’s City Commission

Project Number: DB01A

Project Title: Maryland Dove Waterfront Site Improvements

Analyst: Jessica E. Jordan





Structure

New Construction: 0 Sq. Ft. X $0.00 Sq. Ft. = 0

New Construction: 0 Sq. Ft. X $0.00 Sq. Ft. = 0

Renovation: 0 Sq. Ft. X $0.00 Sq. Ft. = 0

Renovation: 0 Sq. Ft. X $0.00 Sq. Ft. = 0

Built-in Equipment 0

Demolition 0

Information Technology 0 GSF X $0.00 GSF = 0

Telecommunications 0

Miscellaneous-Other Site Preparation and paving 158,000

Miscellaneous-Other Storm Water Management 10,000

Miscellaneous-Other Landscaping/Signage/Guardrails 42,000

SUBTOTAL 210,000

Regional Factor: 110.0% 21,000

SUBTOTAL 231,000

Escalation to midpoint: 2.92 Yrs. X 4.3% = 12.67% 29,260

TOTAL COST OF STRUCTURE (Bid Cost) 260,260



Site Work and Utilities

Site Improvements: 0 + regional factor + mid-point escalation 0

Utilities: 34,000 + regional factor + mid-point escalation 42,137

PROJECT SUBTOTAL (Bid Cost) 302,397



Fees and Miscellaneous Costs

Green Building Premium 0.0% 0

Total Construction Contingency 5.0% 15,090

Inspection Cost: 4.6% 13,890

Miscellaneous: Archeology 15,000

Miscellaneous: CPM/Schedule 9,000

Miscellaneous: 0

A/E Fee through construction phase @ 12.9% 42,790

TOTAL COST OF PROJECT 398,167



Base cost per new square foot $0

Adjusted cost per new square foot (incl. escalation, contingencies & Green Bldg.) $0

Base cost per renovated square foot $0

Adjusted cost per renovated square foot (incl. escalation, conting. & Green Bldg.) $0









3

DB01A –Historic St. Mary’s City Commission



Appendix 2



Capital Project Cost Estimate Worksheet



Department: Historic St. Mary’s City Commission

Project Number: DB01A

Project Title: Waterfront Site Improvements

Analyst: Jessica E. Jordan





Structure

New Construction: 0 Sq. Ft. X $0.00 Sq. Ft. = 0

New Construction: 0 Sq. Ft. X $0.00 Sq. Ft. = 0

Renovation: 0 Sq. Ft. X $0.00 Sq. Ft. = 0

Renovation: 0 Sq. Ft. X $0.00 Sq. Ft. = 0

Built-in Equipment 0

Demolition 0

Information Technology 0 GSF X $0.00 GSF = 0

Telecommunications 0

Miscellaneous-Other Site preparation 38,000

Miscellaneous-Other Paving 105,000

Miscellaneous-Other Storm water management 6,000

SUBTOTAL 149,000

Regional Factor: 110.0% 14,900

SUBTOTAL 163,900

Escalation to midpoint: 2.92 Yrs. X 4.3% = 12.67% 20,761

TOTAL COST OF STRUCTURE (Bid Cost) 184,661



Site Work and Utilities

Site Improvements: 0 + regional factor + mid-point escalation 0

Utilities: 25,000 + regional factor + mid-point escalation 30,983

PROJECT SUBTOTAL (Bid Cost) 215,644



Fees and Miscellaneous Costs

Green Building Premium 0.0% 0

Total Construction Contingency 4.9% 10,475

Inspection Cost: 4.5% 9,637

Miscellaneous: CPM/Schedule 8,000

Miscellaneous: 0

Miscellaneous: 0

A/E Fee through construction phase @ 5.2% 12,151

TOTAL COST OF PROJECT 255,907



Base cost per new square foot $0

Adjusted cost per new square foot (incl. escalation, contingencies & Green Bldg.) $0

Base cost per renovated square foot $0

Adjusted cost per renovated square foot (incl. escalation, conting. & Green Bldg.) $0









4


Related docs
Other docs by winstongamso
2003-2004 Branch Campus (2000 Cohort)
Views: 1  |  Downloads: 0
Subcontractor Material Supplier Declaration
Views: 11  |  Downloads: 0
W10A00 - Maryland State Police[968]
Views: 6  |  Downloads: 0
RA01A - MSDE - State Library Resource Center
Views: 1  |  Downloads: 0
Transportation Trust Fund Overview
Views: 2  |  Downloads: 0
ZA00G - MICUA - Columbia Union College
Views: 2  |  Downloads: 0
Meetings & Minutes Minutes[277]
Views: 4  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!