Embed
Email

RM00A - MSU New Library

Document Sample
RM00A - MSU New Library
RM00A

Morgan State University



New Library (Baltimore City)



GO Bonds $48,968,000 Recommendation: Approve with additional funds

for project management

services.





Bill Text: Provide funds for additional design and for the construction of a new library.





Project Description: Construct a new 212,997 gross square foot (GSF) library on the site of the

Murphy Fine Arts Building. The university currently has a 25,000 net assignable square foot (NASF)

deficit in library space. Because it is not cost-effective or practical to renovate and expand Soper

Library, the fiscal 2004 budget includes $48.9 million in general obligation bond funds for planning

and construction of a new library building.



Comments: The university requested planning funds of $3 million for fiscal 2003, which was

deferred by the legislature. During the 2002 session, the General Assembly authorized funds totaling

$52 million for fiscal 2004 for the detailed design and construction of the project. The most recent

estimate by the Department of General Services indicates that the remaining amount needed for

design and construction is $48.9 million, a difference of $3 million. Part of the difference in the

revised costs is attributable to the cost estimate prepared by the A/E. It also reflects the reduction due

to the removal of chiller equipment from the library project. The chiller equipment is to be funded

separately as part of the campuswide utility upgrade project.



Because planning funds were deferred in fiscal 2003, the State agreed to reimburse Morgan State

University (MSU) for money it spent to keep the project on schedule during fiscal 2003. MSU

expects the fiscal 2002 planning money to be fully expended by March 2003. The university will

spend approximately $600,000 between March and June 1, 2003, the date fiscal 2004 funds will

become available. Funds to reimburse the university for those additional costs are included in the

fiscal 2004 funds. The university expects to complete planning by September 2003 and will

commence construction at that time.









For further information contact: Jessica E. Jordan Phone: (410) 946-5530

1

RM00A – Morgan State University



Project Data

($ in Millions)



Prior 2004 2005 2006 2007 2008

Description

Authorization Request Estimate Estimate Estimate Estimate





Planning $1.962 $2.526 $0.000 $0.000 $0.000 $0.000



Construction 0.000 46.442 0.000 0.000 0.000 0.000



Equipment 0.000 0.000 5.200 0.000 0.000 0.000



Total $1.962 $48.968 $5.200 $0.000 $0.000 $0.000





Total Project Cost: $56,158,563 Cost Per Square Foot – Base: $151

With Escalation & Contingencies: $178

Gross Square Footage: 212,997 Net Usable Square Footage: 137,916

Approved Program Plan: Yes Estimated Completion Date: September 2005







Issues

1. Should Morgan State University Hire an Outside Construction Management

Firm?

The new library will be MSU’s largest project in over 10 years, both in cost and size. While MSU

has successfully overseen the construction of several renovation and new construction projects, the

magnitude of the library combined with the Banneker Hall renovation in future years will be one of

the heaviest construction loads of any of the higher education institutions in Maryland. The expertise

of a construction management firm would provide MSU with the management necessary to complete

projects successfully – both on time and within budget.



Institutions within the University System of Maryland (USM) regularly use construction

management firms to oversee large projects, and by doing so, have been able to achieve a high degree

of success with those projects. MSU's new library will be a landmark project for the university and

for Maryland's higher education institutions; since the project has already been deferred once by the

General Assembly, it would be to MSU's advantage to seek the expertise of an outside management

firm so that the library can be brought online in the easiest and quickest way possible.



In seven of the past 10 years MSU has received supplemental funding for either planning or

construction costs for various projects. These supplemental funds were unforeseen at the time the



2

RM00A – Morgan State University



spending authority was appropriated but cannot be denied by the legislature once a project is

underway. The supplemental funds represent 7.3% of all of the funding MSU has received since

fiscal 1993 – over $10 million total. With a construction management firm, many of these additional

costs could be accounted for in the planning process or avoided altogether. The typical cost of a

construction management firm, as estimated by the Department of General Services and USM, is 1 to

1.5% for preconstruction services such as design and planning, and 2.5 to 3.5% for construction.



Using those estimates for the management of the library, construction management would cost

between $1.25 and $2.5 million. The original total cost estimate for the library was $59 million, but

the estimate has been revised downward to $56.2 million due to the new A/E cost estimate and the

removal of the chiller replacement from the project. Therefore, the costs of construction management

could be included in this project without increasing the original cost estimate.



In fiscal 2004, including ongoing projects such as utility upgrades and campuswide site

improvements, MSU will be overseeing construction totaling $56.4 million. Between fiscal 2005 and

2008 MSU will manage another $65 million in capital funds. For the new library, the proposed

Banneker Hall renovation, and future projects with a total cost exceeding $25 million, the

Department of Legislative Services recommends MSU take advantage of the professionalism

and expertise of a construction management firm to ensure the timeliness and cost effectiveness

of the projects.





Recommended Actions

Approve with additional funds for project management services estimated at $2.5 million.





Executive’s Operating Budget Impact Statement

($ in Millions)



FY 2004 FY 2005 FY 2006 FY 2007 FY 2008





Estimated Operating Cost $0.000 $0.532 $1.908 $2.367 $2.367



Estimated Staffing 0 0 23.75 23.75 23.75



The personnel increases are for a facilities manager and support workers, as well as positions for

housekeeping, maintenance, and security. The operating costs include utilities, supplies, and wages

and will be fully annualized in fiscal 2007.









3

RM00A – Morgan State University



Appendix 1



Capital Project Cost Estimate Worksheet



Department: Morgan State University

Project Number: RM00A

Project Title: New Library

Analyst: Jessica E. Jordan



Structure

New Construction: 212,997 Sq. Ft. X $151.00 Sq. Ft. = 32,162,547

New Construction: 0 Sq. Ft. X $0.00 Sq. Ft. = 0

Renovation: 0 Sq. Ft. X $0.00 Sq. Ft. = 0

Renovation: 0 Sq. Ft. X $0.00 Sq. Ft. = 0

Built-in Equipment 0

Demolition 0

Information Technology 212,997 GSF X $7.00 GSF = 1,490,979

Telecommunications 0

Miscellaneous-Other Slab underdrain and porous drainage blanket 250,000

Miscellaneous-Other Built-in equipment 1,246,032

Miscellaneous-Other Analyst to fill in description 0

SUBTOTAL 35,149,558

Regional Factor: 100.0% 0

SUBTOTAL 35,149,558

Escalation to midpoint: 2.75 Yrs. X 4.4% = 12.00% 4,217,947

TOTAL COST OF STRUCTURE (Bid Cost) 39,367,505



Site Work and Utilities

Site Improvements: 1,757,478 + regional factor + mid-point escalation 1,968,375

Utilities: 1,757,478 + regional factor + mid-point escalation 1,968,375

PROJECT SUBTOTAL (Bid Cost) 43,304,256



Fees and Miscellaneous Costs

Green Building Premium 0.0% 0

Total Construction Contingency 5.0% 2,164,568

Inspection Cost: 2.2% 952,410

Miscellaneous: V-E, geotech, surveys, etc. 375,649

Miscellaneous: CPM/Schedule 34,000

Miscellaneous: IT equipment 2,825,000

Miscellaneous: Movable equipment 2,390,000

A/E Fee through construction phase @ 8.9% 4,112,680

TOTAL COST OF PROJECT 56,158,563



Base cost per new square foot $151

Adjusted cost per new square foot (incl. escalation, contingencies & Green Bldg.) $178

Base cost per renovated square foot $0

Adjusted cost per renovated square foot (incl. escalation, conting. & Green Bldg.) $0









4


Related docs
Other docs by winstongamso
2003-2004 Branch Campus (2000 Cohort)
Views: 1  |  Downloads: 0
Subcontractor Material Supplier Declaration
Views: 11  |  Downloads: 0
W10A00 - Maryland State Police[968]
Views: 6  |  Downloads: 0
RA01A - MSDE - State Library Resource Center
Views: 1  |  Downloads: 0
Transportation Trust Fund Overview
Views: 2  |  Downloads: 0
ZA00G - MICUA - Columbia Union College
Views: 2  |  Downloads: 0
Meetings & Minutes Minutes[277]
Views: 4  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!