GO Bonds                            $1,250,000        Recommendation:        Approve

Bill Text: Provide a portion of the funds to upgrade campus and telecommunications and information
technology.


Project Description: Replace the campus telephone system and upgrade the information technology
system campuswide. The project is being designed in-house and funded in several phases. It includes
installation of the new telephone system, a network infrastructure for the information technology
system, and video and data capabilities in all classrooms. Nine new computer labs will also be
created. The fiscal 2004 budget includes $1.25 million in general obligation (GO) bonds for the third
of four requested funding phases.

Comments: The Department of Budget and Management approved a program plan in December
2001 that outlined the full capital expenditure of $7.25 million over three years, as shown in the fiscal
2003 Capital Improvement Program (CIP). The estimated total project cost of the upgrades increases
by $2.5 million over last year’s CIP. These additional funds will be needed in a future year to
complete all phases. The additional costs are due to revised cost estimates. The current and next
phases are planned as follows:


            Fiscal 2003 ($2.5 million)                     Fiscal 2004 ($1.25 million)

            Network Infrastructure                         One “smart” classroom
            One “smart” classroom                          Wire 30 rooms
            Wire 43 rooms                                  Three computer labs




For further information contact: Jessica E. Jordan                                       Phone: (410) 946-5530

                                                       1
                                  RB27A – USM – Coppin State College

Project Data
                                              ($ in Millions)

                         Prior            2004               2005              2006          2007         2008
  Description
                      Authorization      Request            Estimate          Estimate      Estimate     Estimate


Construction                 $6.000         $1.250             $2.500            $0.000        $0.000      $0.000


Total Project Cost:                   $9,750,000
Approved Program Plan:                      Yes        Estimated Completion Date:                  December 2004



Recommended Actions
Approve.


Executive’s Operating Budget Impact Statement
                                              ($ in Millions)

                                             FY 2004          FY 2005           FY 2006      FY 2007     FY 2008


Estimated Operating Cost                           $0.111        $0.111            $0.111      $0.111      $0.111

Estimated Staffing                                   2.00              2.00          2.00         2.00       2.00

   Coppin will hire two staff members to provide maintenance support for the information
technology upgrades.




                                                       2
                             RB27A – USM – Coppin State College

                                                                                             Appendix 1


                              Capital Project Cost Estimate Worksheet

Department:                 Coppin State College
Project Number:             RB27A
Project Title:              Telecommunications/Info. Technology Upgrade
Analyst:                    Jessica E. Jordan

Structure
New Construction:                 0 Sq. Ft. X         $0.00    Sq. Ft. =                     0
New Construction:                 0 Sq. Ft. X         $0.00    Sq. Ft. =                     0
Renovation:                       0 Sq. Ft. X         $0.00    Sq. Ft. =                     0
Renovation:                       0 Sq. Ft. X         $0.00    Sq. Ft. =                     0
Built-in Equipment                                                                           0
Demolition                                                                                   0
Information Technology            0 GSF X             $0.00    GSF =                         0
Telecommunications                                                                   1,500,000
Miscellaneous-Other     Construction of smart classrooms                             3,000,000
Miscellaneous-Other     Campus-wide cabling plant                                    3,500,000
Miscellaneous-Other     Upgrades to data center                                        750,000
Miscellaneous-Other     Construction of computer labs                                1,000,000
SUBTOTAL                                                                             9,750,000
Regional Factor:           100.0%                                                            0
SUBTOTAL                                                                             9,750,000
Escalation to midpoint:       0.00 Yrs. X         #DIV/0!           =                        0
TOTAL COST OF STRUCTURE (Bid Cost)                                                   9,750,000

Site Work and Utilities
Site Improvements:          0 + regional factor + mid-point escalation                       0
Utilities:                    + regional factor + mid-point escalation                       0
PROJECT SUBTOTAL (Bid Cost)                                                          9,750,000

Fees and Miscellaneous Costs
Green Building Premium                                  0.0%                                 0
Total Construction Contingency                          0.0%                                 0
Inspection Cost:                                        0.0%                                 0
Miscellaneous:              CPM/Schedule                                                     0
Miscellaneous:                                                                               0
Miscellaneous:                                                                               0
A/E Fee through construction phase @                    0.0%                                 0
TOTAL COST OF PROJECT                                                                9,750,000

Base cost per new square foot                                                              $0
Adjusted cost per new square foot (incl. escalation, contingencies & Green Bldg.)          $0
Base cost per renovated square foot                                                        $0