							                                                  RM.00A
                                      Morgan State University

New Communications Center and Pedestrian Bridge (Baltimore
City)

GO Bonds                   $18,414,000           Recommendation: Defer


Bill Text: Provide funds to construct a new communications center and pedestrian bridge.


Project Description: The proposed communications center will be a new 72,400 gross square foot
building to house the Communications Studies Department, the Media Center, programs for the College
of Arts, and the WEAA radio station. These departments and programs are currently located in Banneker
Hall, which was not designed to house modern communications functions. The facility will include
classrooms, lab space, conference rooms, a resource room, and a lounge. The project also includes a
600-foot pedestrian bridge. The bridge will connect the north campus with the main campus.


Comments: Morgan State University (MSU) is requesting $18.4 million in fiscal 2003 to construct the
new communications center and pedestrian bridge. Last year’s Capital Improvement Plan (CIP)
anticipated $18.2 million in construction funds for fiscal 2003. The increase in construction costs is
attributable to more definitive numbers that are based on the architect’s schematic design. MSU is
reporting a space deficit which comprises 6,000 net square feet (NSF) of media space, 8,196 NSF of lab
space, and 1,028 NSF of classroom space. The current communications facility, Banneker Hall, was
constructed in 1938. MSU is requesting $600,000 in planning funds for fiscal 2003 to renovate Banneker
Hall to house other departments. The renovation request will be discussed in a separate analysis.




For further information contact: Brent Johnson                                    Phone: (410) 946-5530

                                                      1
                                     RM.00A - Morgan State University

Project Data
                                                 ($ in Millions)

                      Prior             2003           2004           2005           2006              2007
   Description     Authorization       Request        Estimate       Estimate       Estimate          Estimate


 Planning                 $1.764         $0.000         $0.000          $0.000         $0.000                $0.000
 Construction               0.000        18.414            1.850         0.000             0.000              0.000
 Equipment                  0.000          0.000           0.000         0.000             0.000              0.000
 Total                    $1.764        $18.414         $1.850          $0.000         $0.000                $0.000

 Total Project Cost:            $22,028,00        Cost Per Square Foot - Base:                                   $156
                                                  With Escalation & Contingencies:                               $184
 Gross Square Footage:                72,400      Net Usable Square Footage:                                 41,371
 Approved Program Plan:                 Yes       Estimated Completion Date:                   September 2004



Recommended Actions
   Defer. Due to the uncertainties of the availability of capacity within the debt limit, as projects
previously funded with PAYGO are moved into the bond program, it is necessary to defer otherwise
meritorious projects until sufficient resources are available to fund them.


Executive’s Operating Budget Impact Statement
                                                 ($ in Millions)

                                    FY 2003        FY 2004         FY 2005       FY 2006           FY 2007


 Estimated Operating Cost             $0.000          $0.000         $3.183         $0.483            $0.483
 Estimated Staffing                        0                 0           2                 2                 2

    The estimated operating budget impact for this project includes a substantial increase in expenditures
in fiscal 2005 to purchase additional equipment and to pay contractual services. Other ongoing costs
include salaries for additional support staff, fuel, and utilities.




                                                       2
                                    RM.00A - Morgan State University


                                                                                                Appendix 1

                                      C apital Project C ost E stim ate W orksheet

D epartm en t:                  M organ State U niversity
Project N um ber:               R M .00A
Project T itle:                 New C om m unications C enter and P edestrian Bridge
A n alyst:                      B rent Johnson


Structure
New C onstruction:                 72,400 Sq. Ft. X         $156.00   Sq.   Ft.   =            11,294,400
N ew C onstruction:                      0 Sq. Ft. X          $0.00   Sq.   Ft.   =                     0
R enovation:                             0 Sq. Ft. X          $0.00   Sq.   Ft.   =                     0
R enovation:                             0 Sq. Ft. X          $0.00   Sq.   Ft.   =                     0
B uilt-in Equipm ent                                                                              415,000
D em olition                                                                                            0
Inform ation T echnology           72,400 GS F X               $7.50 GS F =                       543,000
Telecom m unications                                                                                    0
M iscellaneous-O ther                                                                                   0
M iscellaneous-O ther                                                                                   0
M iscellaneous-O ther                                                                                   0
SU B T O T A L                                                                                 12,252,400
R egional Factor:                 100.0%                                                                0
SU B T O T A L                                                                                 12,252,400
Escalation to m idpoint:              2.80    Y rs. X          4.4%          =        12.19%    1,494,115
T O T A L C O ST O F ST R U C T U R E (B id C ost)                                             13,746,515


Site W ork and U tilities
Site Im provem ents:              551,358 + regional factor + m id-point escalation               618,593
Pedestrian bridge:              1,047,000 + regional factor + m id-point escalation             1,174,676
U tilities:                     1,432,668 + regional factor + m id-point escalation             1,607,374
PR O JE C T SU B T O T A L (B id C ost)                                                        17,147,158


Fees and M iscellaneous C osts
G reen B uilding Prem ium                                      0.0%                                     0
Total C onstruction C ontingency                               5.0%                               857,358
Inspection C ost:                                              2.2%                               377,237
M iscellaneous:               V E , bid analysis, construction review , etc.                      128,000
M iscellaneous:               C PM /Schedule                                                       32,000
M iscellaneous:               M ovable E quipm ent                                                775,000
M iscellaneous:               Inform ation T echnology E quipm ent                              1,075,000
A /E Fee through construction phase @                          8.9%                             1,636,406
T O T A L C O ST O F PR O JE C T                                                               22,028,159

B ase cost   per new square foot                                                                    $156
A d justed   cost p er n ew square foot (incl. escalation, con tingencies & G reen B ldg.)          $184
B ase cost   per renovated square foot                                                                $0
A d justed   cost p er renovated square foot (in cl. escalation, conting. & G reen B ldg.)            $0



                                                        3
RM.00A - Morgan State University




               4

						