GO Bonds $18,414,000 Recommendation: Defer
Bill Text: Provide funds to construct a new communications center and pedestrian bridge.
Project Description: The proposed communications center will be a new 72,400 gross square foot
building to house the Communications Studies Department, the Media Center, programs for the College
of Arts, and the WEAA radio station. These departments and programs are currently located in Banneker
Hall, which was not designed to house modern communications functions. The facility will include
classrooms, lab space, conference rooms, a resource room, and a lounge. The project also includes a
600-foot pedestrian bridge. The bridge will connect the north campus with the main campus.
Comments: Morgan State University (MSU) is requesting $18.4 million in fiscal 2003 to construct the
new communications center and pedestrian bridge. Last year’s Capital Improvement Plan (CIP)
anticipated $18.2 million in construction funds for fiscal 2003. The increase in construction costs is
attributable to more definitive numbers that are based on the architect’s schematic design. MSU is
reporting a space deficit which comprises 6,000 net square feet (NSF) of media space, 8,196 NSF of lab
space, and 1,028 NSF of classroom space. The current communications facility, Banneker Hall, was
constructed in 1938. MSU is requesting $600,000 in planning funds for fiscal 2003 to renovate Banneker
Hall to house other departments. The renovation request will be discussed in a separate analysis.
For further information contact: Brent Johnson Phone: (410) 946-5530
1
RM.00A - Morgan State University
Project Data
($ in Millions)
Prior 2003 2004 2005 2006 2007
Description Authorization Request Estimate Estimate Estimate Estimate
Planning $1.764 $0.000 $0.000 $0.000 $0.000 $0.000
Construction 0.000 18.414 1.850 0.000 0.000 0.000
Equipment 0.000 0.000 0.000 0.000 0.000 0.000
Total $1.764 $18.414 $1.850 $0.000 $0.000 $0.000
Total Project Cost: $22,028,00 Cost Per Square Foot - Base: $156
With Escalation & Contingencies: $184
Gross Square Footage: 72,400 Net Usable Square Footage: 41,371
Approved Program Plan: Yes Estimated Completion Date: September 2004
Recommended Actions
Defer. Due to the uncertainties of the availability of capacity within the debt limit, as projects
previously funded with PAYGO are moved into the bond program, it is necessary to defer otherwise
meritorious projects until sufficient resources are available to fund them.
Executive’s Operating Budget Impact Statement
($ in Millions)
FY 2003 FY 2004 FY 2005 FY 2006 FY 2007
Estimated Operating Cost $0.000 $0.000 $3.183 $0.483 $0.483
Estimated Staffing 0 0 2 2 2
The estimated operating budget impact for this project includes a substantial increase in expenditures
in fiscal 2005 to purchase additional equipment and to pay contractual services. Other ongoing costs
include salaries for additional support staff, fuel, and utilities.
2
RM.00A - Morgan State University
Appendix 1
C apital Project C ost E stim ate W orksheet
D epartm en t: M organ State U niversity
Project N um ber: R M .00A
Project T itle: New C om m unications C enter and P edestrian Bridge
A n alyst: B rent Johnson
Structure
New C onstruction: 72,400 Sq. Ft. X $156.00 Sq. Ft. = 11,294,400
N ew C onstruction: 0 Sq. Ft. X $0.00 Sq. Ft. = 0
R enovation: 0 Sq. Ft. X $0.00 Sq. Ft. = 0
R enovation: 0 Sq. Ft. X $0.00 Sq. Ft. = 0
B uilt-in Equipm ent 415,000
D em olition 0
Inform ation T echnology 72,400 GS F X $7.50 GS F = 543,000
Telecom m unications 0
M iscellaneous-O ther 0
M iscellaneous-O ther 0
M iscellaneous-O ther 0
SU B T O T A L 12,252,400
R egional Factor: 100.0% 0
SU B T O T A L 12,252,400
Escalation to m idpoint: 2.80 Y rs. X 4.4% = 12.19% 1,494,115
T O T A L C O ST O F ST R U C T U R E (B id C ost) 13,746,515
Site W ork and U tilities
Site Im provem ents: 551,358 + regional factor + m id-point escalation 618,593
Pedestrian bridge: 1,047,000 + regional factor + m id-point escalation 1,174,676
U tilities: 1,432,668 + regional factor + m id-point escalation 1,607,374
PR O JE C T SU B T O T A L (B id C ost) 17,147,158
Fees and M iscellaneous C osts
G reen B uilding Prem ium 0.0% 0
Total C onstruction C ontingency 5.0% 857,358
Inspection C ost: 2.2% 377,237
M iscellaneous: V E , bid analysis, construction review , etc. 128,000
M iscellaneous: C PM /Schedule 32,000
M iscellaneous: M ovable E quipm ent 775,000
M iscellaneous: Inform ation T echnology E quipm ent 1,075,000
A /E Fee through construction phase @ 8.9% 1,636,406
T O T A L C O ST O F PR O JE C T 22,028,159
B ase cost per new square foot $156
A d justed cost p er n ew square foot (incl. escalation, con tingencies & G reen B ldg.) $184
B ase cost per renovated square foot $0
A d justed cost p er renovated square foot (in cl. escalation, conting. & G reen B ldg.) $0