Embed
Email

Cost estimation and cost behaviour

Document Sample

Shared by: cuiliqing
Categories
Tags
Stats
views:
7
posted:
11/10/2011
language:
English
pages:
5
Cost estimation and cost behaviour

Solutions to Chapter 24 questions









Question 24.25 (a) The first stage is to convert all costs to a 2002 basis. The calculations are as follows:

1998 1999 2000 2001

(£000) (£000) (£000) (£000)

Raw materials

Skilled labour 242(1.2)4 344(1.2)3 461(1.2)2 477(1.2)

Unskilled labour

Factory overheads 168(1.15)3(1.2) 206(1.15)2(1.2) 246(1.15)(1.2) 265(1.2)

Power 25(1.1)(1.25)3 33(1.25)3 47(1.25)2 44(1.25)

Raw materials

Skilled labour 500.94 595.12 663.84 572.4

Unskilled labour

Factory overheads 306.432 326.304 339.48 318

Power 53.625 64.35 73.32 55

Total (2002 prices) 861 000 986 000 1 077 000 945 000

Output (units) 160 000 190 000 220 000 180 000



The equation Υ a bx is calculated from the above schedule of total production

costs (2002 prices) and output. The calculations are as follows:



Output Total cost

in units (000) (£000)

x y x2 xy

160 861 25 600 137 760

190 986 36 100 187 340

220 1077 48 400 236 940

180 945 32 400 170 100

––– –––– ––––––– –––––––

Σx 750 Σy 3869 Σx2 142 500 Σxy 732 140

––– –––– ––––––– –––––––

We now solve the following simultaneous equations:

Σy Na bΣx

Σxy Σxa bΣx2

Therefore

3869 4a 750b (1)

732 140 750a 142 500b (2)



Multiply equation (1) by 190 (142 500/750) and equation (2) by 1. Then equation (1)

becomes



735 110 760a 142 500b (3)



Subtract equation (2) from equation (3):



2970 = 10a

a 297



192 COST ESTIMATION AND COST BEHAVIOUR

Substitute for a in equation (1):



3869 4 x 297 750b

2681 750b

b 3.57



The relationship between total production costs and volume for 2002 is:



y £297 000 3.57x



where y total production costs (at 2002 price) and x output level.

(b) See pages 1047–1051 in Chapter 24 for the answer to this question.

(c) General company overheads will still continue whether or not product LT is

produced. Therefore the output of LT will not affect general production

overheads. Consequently, the regression equation should not be calculated from

cost data that includes general company overheads. General company overheads

will not increase with increments in output of product LT. Hence short-term

decisions and cost control should focus on those costs that are relevant to

production of LTs. Common and unavoidable general fixed costs are not relevant

to the production of LT, and should not be included in the regression equation.





(a) Question 24.26

Y1000 = 18 × 1000 – 0.1520

Y1000 = 18 × 0.3499

Y1000 = 6.2990 minutes

The cumulative average time taken to produce 1000 units is 6.2990 minutes and

the time taken to produce a total of 1000 units will therefore be 629.9 minutes

(i.e. 104.98 hours).

(£)

Standard cost of 1000 units:

Materials (£28/0.95 × 1000) 29 474

Processing cost (104.98 hours at £25) 2625

––––––

32 099

––––––

(b)

Y5000 = 18 × 5000 – 0.1520

Y5000 = 18 × 0.274

Y5000 = 4.9321 minutes

Therefore the estimated time taken to produce 5000 units is 24 660 minutes

(5000 × 4.9321 minutes)

Y6000 = 18 × 6000 – 0.1520

Y6000 = 18 × 0.2665

Y6000 = 4.7973 minutes

Therefore the estimated time taken to produce 6000 units is 28 784 minutes

(6000 × 4.7973 minutes) so the 1000 units has taken an additional 68.73 hours

(28 784 minutes – 24 660 minutes) giving a standard variable processing cost of

£1718 (68.73 hours × £25). Adding the direct material cost of £29 474 gives a

total standard variable cost of £31 192.

(c) Revised learning curve effect:

Y1000 = 18 × 1000 – 0.320

Y1000 = 18 × 0.1096

Y1000 = 1.9737 minutes





COST ESTIMATION AND COST BEHAVIOUR 193

The estimated total time to produce 1000 units in April is 32.89 hours (1973.7

minutes/60) giving a total standard variable processing cost of £822 (32.89 hours ×

£25). The standard direct material cost will remain unchanged at £29 474 giving a

total standard cost of £30 296.

Original budgeted profit

(£)

Sales 60 000

Variable costs 32 099

––––––

Contribution 27 901

Fixed costs 20 000

––––––

Profit 7 901

––––––



Actual profit

(£) (£)

Sales (900 × £62) 55 800

Production costs: Direct materials 31 870

Variable processing 1 070

Fixed costs 24 840

––––––

57 780

Closing stock (100 units at revised standard cost of

£30.296 per unit) 3 030 54 750

–––––– ––––––

Profit 1 050

––––––

Variance calculations

Processing usage/efficiency variance (original standard of £2625 –

revised standard of £822) £1803F

Selling price variance (£62 actual price – £60 budgeted price) ×

900 units £1800F

Sales volume (900 actual volume – 1000 budgeted volume) × revised

stand. contrib. margina £2970A

Direct material cost (standard cost of 1000 × £29.474 – Actual cost

of £31 870) £2396A

Variable processing expenditure (Flexed budget of 2425 minutes ×

£25/60 – actual cost) £60A

Variable processing efficiency (1.9737 minutes revised standard ×

1000 units – actual time of 2 425 minutes) × stand. rate (£25 per hour) £188A

Fixed cost expenditure (Budgeted cost of £20 000 – Actual cost of

£24 840) £4840A

–––––––

Total variances £6851A

–––––––

Notes

a revised standard contribution margin = £60 selling price – revised variable cost



(£29.474 + £822/1000) = £29.704

Reconciliation statement

Original budgeted profit £7901

Less net variances as shown above £6851A

Actual profit £1050



(d) If budgets and standards are set without considering the learning effect, mean-

ingless standards are likely to be set that are easy to attain. Therefore favourable

variances would be reported that are not due to operational efficiency. Where

learning effects are expected, management should create an environment where

improvements are expected.







194 COST ESTIMATION AND COST BEHAVIOUR

(a) (i) The learning curve is expressed as: Question 24.27

yx axb



The exponent b is defined as the ratio of the logarithm of the learning curve

improvement rate divided by the logarithm of 2. For an 80% learning curve:



b log 0.8/log 2 0.322



For an output of 14 units:



y14 40 14 0.322 17.1 hours per unit

Time taken for 14 units 14 17.1 239.4 hrs

Actual hours 240



It would therefore appear that an 80% learning effect is a reasonable

assumption.

(ii) For an output of 50 units:



y50 40 50 0.322 11.35 hours per unit



Hours required for 50 units: 50 11.35 = 567.5 hrs

For an output of 30 units:



y30 40 30 0.322 13.38 hours per unit



Hours required for 30 units 30 13.38 401.4 hours

The time required for the additional 20 units 166.1 hours (567.5 401.4)

(iii) Estimated cost for an order of 30 units

(£)

Direct materials (30 £30) 900.00

Direct labour (401.4 hrs £6) 2408.40

Variable overhead (401.4 hrs £0.50) 200.70

Fixed overhead (401.4 £5)a 2007.00

–––––––

5516.10

–––––––



The above product cost has been calculated on an absorption costing basis in

accordance with the current standard absorption costing system.



Note

aFixed

overhead for the period £6000

Direct labour hours for the period 1200 (75% 40 hrs 10 employees

4 weeks)

Fixed overhead hourly rate £5 (£6000/1200)

Where the learning effect is present, unit product costs and labour hours will

not be constant per unit of output. Significant variations in product costs and

labour hours per unit of output are likely to occur at lower output levels. It is

therefore necessary to estimate the extent of the learning effect for standard

settings, budgeting and selling price quotations. Failure to take into account

the presence of the learning effect can result in significant errors in cost esti-

mates and planned labour requirements. If standards are not adjusted, they

will cease to represent meaningful targets and lead to the reporting of erro-

neous favourable variances.

(b) The statement refers to the fact that, with modern technology, there is a dramatic

decrease in the direct labour content of most goods and services. Recent studies

suggest that direct labour represents less than 10% of manufacturing cost and that



COST ESTIMATION AND COST BEHAVIOUR 195

overheads are more closely related to machine hours than direct labour hours.

With modern technology, output tends to be determined by machine speeds

rather than changes in labour efficiency. Consequently, the presence of the

learning effect as workers become more familiar with new operating procedures

is of considerably less importance.

The question implies that the learning curve is being replaced by an experience

curve. The experience curve relates to the fact that output and efficiency are

determined by manufacturing technologists such as engineers and production

planners. As these groups of individuals gain experience from a range of

applications of the new technology, efficiency improves and costs are minimized.

It is therefore claimed that the experience curve has replaced the learning curve.

However, the experience curve is extremely difficult to determine, and its impact

is likely to take place over a much longer time period. It is therefore extremely

difficult to capture the ‘experience effect’ within short-term standard setting,

budgeting and cost estimation activities.









196 COST ESTIMATION AND COST BEHAVIOUR



Related docs
Other docs by cuiliqing
11.1 Exploring Area and Perimeter
Views: 0  |  Downloads: 0
Volusia County
Views: 2  |  Downloads: 0
choosing_topics_and_y10
Views: 0  |  Downloads: 0
CLE Credit - rscrpubs.com
Views: 2  |  Downloads: 0
Meeting Minutes September 8 Final
Views: 0  |  Downloads: 0
nov2411
Views: 3  |  Downloads: 0
EKG Spreadsheet - Geocities.ws
Views: 0  |  Downloads: 0
Gift from Christ to the Church
Views: 0  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!