Embed
Email

Presentation-R.D. Varangaonkar

Document Sample
Presentation-R.D. Varangaonkar
Hydropower Development

Problems/Concerns of the

Developers involved

R.D.Varangaonkar

Chief Executive

Gammon India Ltd.

Gammon House,

V. S. Marg,

Prabhadevi,

Mumbai-400025

India Power Scenario

• In India, despite many power projects in operation,

there is still acute power shortage. As on date, the

total installed capacity is 130000MW which is

almost 22% less than the present requirement of

160000MW.



• Government of India has taken decision to develop

the power projects and provide power for all by

2012. the expected requirement for 2012 is

230000MW, that means in five years, in 11th Plan,

the capacity has to be increased by 100000MW. Out

of this, hydro power is almost 50%, i.e. 50000MW.



National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

India Power Scenario

• As India is a developing country, the power

requirement will keep on increasing and it is

estimated that by 2030, the total power required will

be 800000MW.



• India is one of the gifted country having large

network of rivers which estimated hydro potential in

India as approx. 150000MW. However, only

30000MW has been tapped so far.



• It is necessary that the hydro power potential is

tapped to maximum extent which will not only fulfill

the electricity shortage but will also help in irrigation

and in supplying drinking water.

National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

India Power Scenario



• After independence number hydel projects were

taken in hand and the percentage of hydel power

production was about 46% in 1951 which has

dropped down to 26% in 2005. there is need to

develop hydro power.



• It is advantageous not only for power but is also a

clean, renewable, environment-friendly energy (non-

polluting) having lowest cost of production among

all kinds of power projects and the maintenance is

almost negligible.





National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

India Power Scenario







Trend of hydel, thermal, nuclear and non-

conventional powers for last 10 years is given in

the graph here below. All Power sectors

generation have steady increased by 50% to 68%









National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

India Power Scenario

Generation

(Million Units) Generation

700000

617382

587366

600000 558134

531430

499450 515201 497044

480011 486031

500000 448445 466618

448380

420622 408208 422001

394488 386226

400000 353662

336104

316869 Total Thermal

300000 Hydel Nuclear



200000

101325

68609 74476 82703 80533 74346 73922 73796 84497

100000 63773



10042 12015 13252 16896 19278 19212

9010 17720 16838 17248

0

Year 1996-97 1997-98 1998-99 1999- 2000-01 2001-02 2002-03 2003-04 2004-05 2005-06

2000









National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

India Power Scenario

Late in the year 1991 even non-conventional energy

started adding to the power generation and the graph

below shows capacity addition of thermal, hydel,

nuclear and non-conventional energy sources from the

year 1996 to 2005.

Generation

(Million Units)

Capicity Addition.

7000 6361

Total Thermal

Hydel Nuclear 5868

6000

Non.Conv.

4890

5000

4086 4085

4000 3467 3442 3420

3227

2994 2928 2927 2934

3000 2652 2590

2195 2057

1862 2380

2000 1377 1361 1942

1435 1508

1390

1090 1286 1127

1000 682 550 641

233

0 0 130 114 238 229

0 0 134

Year 1996-97 1997-98 1998-99 1999-2000 2000-01 2001-02 2002-03 2003-04 2004-05 2005-06

-1000







National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

India Power Scenario

Generation

Capicity Addition.

(Million Units)

7000

6361

Total Thermal

Hydel Nuclear 5868

6000

Non.Conv.

4890

5000

4086 4085

4000 3467 3442 3420

3227

2994 2928 2927 2934

3000 2652 2590

2195 2057

1862 2380

2000 1377 1361 1942

1435 1508

1390

1090 1286 1127

1000 682 550 641

233

0 0 130 114 238 229

0 0 134

Year 1996-97 1997-98 1998-99 1999-2000 2000-01 2001-02 2002-03 2003-04 2004-05 2005-06

-1000









National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

Future Plan

• Addition of 100000mw in the 11th plan is a tough

target.

• There were only four major players for hydel power

production, viz. NHPC, Neepco, THDC & SJVNL. In

addition to this, most of the electricity Boards were

executing power projects in a smaller scale in their

States.

• In order to achieve the target, the Government of India

wanted private participation in hydel power

production. However, private players were not

coming in a big way.



National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

Future Plan

• It is only after the Electricity Act, 2003 which has very

positive effect because the entire sector was free

from licensing. Techno-economical clearance,

protection of consumers interest, capitalization – this

has encouraged the private participation in a big way.

• Add to that is National Electricity Policy of February

2005, promising power to all by 2012, rural

electrification, reduce the transmission and

distribution losses. With the result the private

participation is encouraged and is increasing to an

acceptable level.



National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

Future Plan





Malana Power Corporation, Tata Powers, Jay

Prakash Associates, were the first to enter into

private hydel power production. Now many big

players are in the field and are showing their

interest in the hydel power production.









National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

Future Plan

Installed Capacity by Sector (Mar 31, 2006)

Central: 39924MW State: 70,224MW



32%

56.50%



11.50%









Private: 14,139MW





National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

Hydel Power



Hydel power can be mainly divided into three

categories –



• Run-off the River (no storage)

• Storage Projects

• Reversible turbine type









National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

Hydel Power



• Hydel power projects can be sequential

as under –

• Conception

• Detail Project Report

• Planning

• Construction

• Operation & Maintenance

• Transmission & Distribution



National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

Hydel Power

1 Conception

2 Detail Project Report

• Field Survey, topographical survey, river cross section,

geophysical investigation, hydrological observations,

land survey – Once these investigations are completed,

detailed project report is to be prepared. Most hydro

projects are in the remote locations. It is often observed

that due to logistics and unapproachable area, the above

surveys and investigations gives lot of problem and

substantial time is lost for preparation of the details

project report. In many of the projects, investigations

were carried out even by approaching the actual site on

elephant back.



National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

Hydel Power



3. Planning



• Medium and large hydro projects require huge

construction equipments.

• Due to present sudden boom in the construction of

hydro power and other infrastructural development

in India. The delivery of the construction equipment

is often having large delivery time.









National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

Hydel Power

3. Planning (Delays in equipment delivery)

• The order books of most of the manufacturing

companies are full causing delay in delivery of

equipment.

• For example, BHEL which is the largest hydel turbine

manufacturing in India. Presently BHEL is having

capacity of 6000mw per year. To meet the demand

of 50000mw, BHEL have to enhance the capacity to

10000mw per year. But still it appears to be difficult

to meet the requirement. Similar is the situation with

most of the construction equipment manufacturers.

Their order books are full and therefore there is

delay in delivery of equipments



National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

Hydel Power

4 Material

• Construction material like cement, steel, structurals,

electrical cables. Due to sudden surge in

construction activities, the construction material

supply is really a big concern. Specially on the

hydro projects, because of the logistics and

unapproachable and bad roads, transportation of

material becomes difficult. Steel prices are

unpredictable and for the past 4-5 years it has been

fluctuation very much. Similarly is the cost of

cement. The rising cost and the transportation

increases the cost of construction.





National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

Hydel Power

5 Manpower

• This is the greatest concern. Presently there is

acute shortage of experienced engineers for hydro

power sector, specially in the middle and senior

management level. This is mainly because in the

last decade there were not many hydro projects

under construction in India and therefore hydro

engineers are in acute shortage. This results in

attrition among major power development

companies and due to this instability does occur.









National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

Hydel Power

5 Manpower

• Shortage of experienced and good engineers also

delays the work and increases the cost. Besides,

there is shortage of fresh graduates/diploma civil

engineers. Because of boom in the IT industries,

most engineers opt for computer and software

subjects and a meager percentage opt for civil

engineering branch. This results in shortage of civil

engineers even at the entry level.

• Similar is the case of good foreman, mechanics,

electricians and heavy equipment operators like

Tamrock operators, heavy excavator operators and

large capacity dumper operators.



National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

Hydel Power



6 Finance

• To meet the power requirement, India needs about

Rs.9000 billion by 2012 for meeting the demand of

100000mw. This huge amount of Finance is a big

concern.

• However, because hydel projects are funded by

bankers debt equity ratio of 70:30, banks like UCO,

Union Bank, ICICI, IDBI, Power Finance Corporation

and other major banks are prepared to finance power

projects at lower rate of interest. Main finance has to

come from Government.





National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

Hydel Power



7 Construction

Construction of hydro projects are in the remote

locations. Therefore, the approach road to the aproject

sites are to be constructed which require lot of time

and money. This adds to the time required for the

construction









National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

Hydel Power



8 Communication

Being the remote location, communication is also not

available. Therefore Developers has to install Vsat &

DTS, which adds to the cost of the project.









National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

Hydel Power





9 Construction Power

In the remote location rarely construction power is

available. The Developers have to generate his own

power by installing DG sets. DG power is almost three

times the cost of commercial power which adds to the

cost.









National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

Hydel Power





10 Land for Construction

For installation of construction plant, labour camp,

officer’s camp, office, stores, etc. require huge land.

Local land-owners often creat problems for providing

land and even if they do, they ask for exhorbitant price.









National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

Hydel Power

11 Law and Order

• Insurgencies, local problem and labour laws/unions –

Speedy construction of hydel project can be done

only when law and order situation and labour work

efficiently without creating problems.

• It is observed that labour union office crate problems

and get their unjustified demands fulfilled by

threatening to go on strike. Some of the projects

under execution in which, though the minimum wage

is Rs.75/- per day but the Developers are paying

about approximately Rs.210 per day which adds to

the cost. Despite this there is no guarantee of

smooth and efficient working of the project.



National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

Hydel Power



11 Law and Order

• Local and influential contractors often dement for the

specialized work. Though they have no such

experience in the past. Despite this because of their

local standing under duress, works are given to them

which often gets delayed.

• Most areas these days are often affected by naxalites

or insurgencies. In northeast States which often

demand unjustified amount otherwise do not allow

the work to proceed.









National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

Hydel Power



12 Environment

• Submergence of forest and inhabitant land and

related environment aspects often delay the project.

Despite the clear guidelines, environment clearance

often gets delayed because of procedural delays and

• Lack of co-ordination between various departments.

Several projects are facing opposition from

Environment Authority. This discourages private

participation.









National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

Hydel Power



13 Geological Surprises

Himalaya is young mountain which does not have

constant geology which leads to surprises like loose

fall, cavity formation, flowing conditions and heavy

seepage of water, etc. This results in time overrun and

cost overrun.









National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

Hydel Power



14 Rehabilitation

Submergence of land due to reservoir resulting into

shifting of people from the affected area. It is really

painful activity to shift affected people. It is difficult to

assess the actual compensation and there is always

dispute regarding compensation amount. This is to be

tackled very carefully and tactfully. This also requires

political support.









National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

Hydel Power

15 Natural Calamities

• In spite of efforts to get data for hydrological &

metrological on many cases correct/accurate datas

are not available.

• For many projects flood warning system does not

exist, which takes construction agency by surprise.

• Floods, heavy rains and unpredictable snowfall often

disturbs the work and Developers have to sustain

very heavy losses due to damage to the plant and

equipment and to the structures constructed,

resulting into time overrun and cost overrun.





National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

Hydel Power





16 Political Issues and Interstate Problems

Leaders of the States are very powerful political figures

and without their interest and backing it is difficult to

execute the projects. Similarly, if the river is running

through number of States, the political problems come

up which affects the Developers.









National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007

Hydel Power

17 Operation, Maintenance, Transmission &

Distribution

• Transmission of power is mainly done by the Government

owned companies. Normally it is not a problem now.

However, the transmission lines are inadequate. For

example, in 1950 the transmission lines installed were

3708 ct.km. In the year 2005, it increased to 264240 ct.km.

This will have to be increased to 350,000 ct.km. So far

only one private transmission company is operating in

this field, i.e. Tata Transmission Project. Looking to the

power development, more private players need to come

into the field to fulfill the transmission demand.

demand





National Seminar on “ Hydropower: Harnessing the Untapped Potential” – January 4, 2007


Related docs
Other docs by kylemangan
European Commission Insurance Solvency II
Views: 32  |  Downloads: 5
Consumer Assistance Training Online
Views: 3  |  Downloads: 0
STATISTICS
Views: 61  |  Downloads: 5
Pivots
Views: 3  |  Downloads: 0
Final2008Summer_SFC Newsletter.indd
Views: 20  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!