BANNER STUDENT IMPLEMENTATION PROJECT

MONTHLY UPDATE: JUNE, 2006





Progress Report: A short description of team progress during this

reporting period.



Admission: The Admission team is fully staffed and making very good progress on its

schedule. Task initiation and completion rates are excellent. The Admission module is

currently on track to meet the September go-live target. While the Admissions module is

currently on track, we recognize that there are some legitimate concerns related to interfaces

and reports being fully completed on time.



Financial Aid: Financial Aid team is fully staffed and making very good progress on its

schedule. Task initiation and completion rates are excellent. However, in June we learned of

the departure of two key project members (Team Lead Paul Langhammer and Director Mike

Bartini), so there is concern about the team’s ability to sustain its progress.



Registration and Records: The R&R team made considerable progress in June.

Identification of staff for backfill positions was almost completed, with the report writer

scheduled to begin 7/3, the system support position to start 7/26 and a probably candidate for

the assistant registrar identified. Future additional SunGard resources have been identified as

well. Increased support from the project management team has produced a more refined and

articulated schedule, and the team’s task initiation and completion show a corresponding

improvement. The most immediate challenge is completion of the data conversion milestone,

which we expect will be August 14, 2006.



Accounts Receivable: The AR team is fully staffed and making very good progress. Task

initiation and completion rates are excellent. The AR team currently is on track to meet the

2007 go-live.



Technical Team and CIS Banner Implementation Support Team: The project is fully

staffed in terms of technical resources with a combination of temporary and consulting

positions. The Tech Team is making good progress on task initiation and completion. Given

the demand for technical resources, however, we believe it is likely that additional technical

resources will be needed on an ad-hoc basis. In particular for the short-term, an area of

concern is the development work needed for the Admission go-live, including an interface for

BASC, interfaces for loading applications, and a modification to calculate the Academic

Index.





Milestones Completed: List milestones that were completed during this

reporting period.



Milestone Date Due Comments

Completed Date

ADM-Complete BPR Review 06/09/06 06/09/06

for Grad School

ADM-Complete UG 06/23/06 06/23/06

Configuration

ADM-Complete Grad School 06/09/06 06/09/06

Configuration





Banner Student Implementation Project Monthly Update Page 1 of 3

ADM-Complete 7.3 UPGR 06/30/06 06/30/06

Testing

ADM-Complete School data 06/30/06 06/30/06

to scanner Functional Spec

FIN-Complete FA BPR Work 06/09/06 06/09/06

FIN-Complete FA 7.3 Testing 06/30/06 06/30/06

FIN-Complete Defining Grad 06/19/06 06/19/06

training needs

FIN-Complete FA Module 06/04/06 06/04/06

Prep









Issues Resolved: The following issues were resolved during this

reporting period.



Issue Resolved by Date

Resolved

Summer Studies/Banner relationship Nancy Dunbar / 06/30/06

PMT



Data conversion issues PMT 06/30/06

Financial aid – returning students

Inaccurate test scores/historical data



Freshman Questionnaire data entry Nancy Dunbar/PMT 06/30/06









Unresolved Issues: The following issues are unresolved and require

attention. Additional detail is contained in the Project

Issue Log.



Issue Assigned to Date

Resolution

Required

Load Testing – Investigating vendors Terri-Lynn Thayer / 07/31/06

PMT

Concentration advisor shared ID Nancy Dunbar / 07/31/06

PMT

Data conversion issues PMT 07/31/06

Panorama database (med)



Ethnicity Codes – Anything except blank Nancy Dunbar/PMT 07/31/06









Banner Student Implementation Project Monthly Update Page 2 of 3

Risk Factors Identified: The following risks to the project have been identified

during this reporting period. Additional detail is

contained in the Project Risk Log.



Risk Description Probability of Severity of Recommended Response/Risk

Occurrence Impact Mitigation Strategy

7.3 upgrade Low Low Continue to work with SunGard to

mitigate risk.

R&R staffing Medium Medium Seek SunGard resources

Add PMT support

Consider personnel reassignment

Succession Planning High Medium Meet with functional leads to

consider alternatives;

Pre-screen SunGard possibilities

Financial Aid personnel High High Preliminary discussion: investigate

SunGard resources; consider

banner-experienced replacement;

add resources from PMT or shift

resources from other teams







Work Projected for Next Period



Description Owner Planned

Completion

Date

ADM-Complete Security Configuration Admissions 07/27/06

ADM-Complete Self Service Configuration Admissions 07/17/06

ADM-Complete BPR Review for UG Admissions Admissions 07/18/06

FIN-Complete Complete Admission Work Financial Aid 07/28/06

FIN-Complete Basic FA Configuration Financial Aid 07/31/06

Prepare for Integration Testing PMT 07/26/06









Banner Student Implementation Project Monthly Update Page 3 of 3


Related docs
Other docs by ChrisCaflish
美国•布朗大学
Views: 14  |  Downloads: 0
IXION IN HEAVEN
Views: 54  |  Downloads: 0
Dear Rep
Views: 16  |  Downloads: 0
52 PORCH CEILING FAN
Views: 91  |  Downloads: 0
Shepherd 210 Installation Manual
Views: 2  |  Downloads: 0
RUSSIA IN THE 20TH CENTURY
Views: 153  |  Downloads: 1
第一章
Views: 94  |  Downloads: 0
Verb Forms
Views: 63  |  Downloads: 3
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!