Treasury Board of Canada Secrétariat du Conseil du Trésor

Secretariat du Canada









Enhanced Management Framework



Project Tracking & Oversight Process









Document Revision Draft 1.0

Date of Issue: January 2000



Process Owner: Enhanced Management Framework



PPTO-PS-003









Canada

Table of Contents

1. Introduction ..................................................................................................1



1.1 Purpose ........................................................................................................................... 1

1.2 Scope .............................................................................................................................. 1

1.3 Roles ............................................................................................................................... 1

1.4 Definitions and Acronyms ................................................................................................ 2

1.5 References ...................................................................................................................... 2

1.6 Inquiries ........................................................................................................................... 3

2. Process .........................................................................................................4



2.1 Entry Criteria .................................................................................................................... 4

2.2 Process Map .................................................................................................................... 4

2.3 Inputs ............................................................................................................................... 6

2.4 Activities .......................................................................................................................... 7

2.5 Outputs ............................................................................................................................ 8

2.6 Verification and Validation ............................................................................................... 8

2.7 Exit Criteria ...................................................................................................................... 9

2.8 Metrics ............................................................................................................................. 9

2.9 Records Control Table .................................................................................................... 9

2.10 Controlled Documents Table ........................................................................................... 9

Annex A – Lexicon ............................................................................................10



Annex B – Acronyms ........................................................................................11



Annex C – Flowcharting Symbols....................................................................12



Annex D – Bibliography ....................................................................................13



Annex E – Document Change Control.............................................................14









Organisation Title/Subject Number

TBS/CIOB/EMF Project Tracking and Oversight Process PPTO-PS-003

Owner Approved by Date Version Page i

EMF J. Ginley January 2000 1.0

1. Introduction

1.1 Purpose

The purpose of this document is to describe the process to be followed by a project

manager to track a project.



1.2 Scope

This process is applicable to any Information Management/Information Technology

(IM/IT) project and to any phase of the IM/IT development life cycle.



1.3 Roles

Everyone in the organisation has a role to perform in this process.



Role Description/Responsibilities



Project Leader (PL) This is the person appointed by the sponsoring department to

be accountable for all external and internal aspects of a

capital project.

http://www.publiservice.tbs-sct.gc.ca/pubs_pol/dcgpubs/TB

M_122/ABKGLOS_e.html







Project Manager This is a person formally appointed to manage a project with

(PM) specific accountability for achieving defined project

objectives within allocated resources. A project manager

has access to, and a formally defined relationship with, the

project leader to which the specific project has been

assigned.

http://www.publiservice.tbs-sct.gc.ca/pubs_pol/dcgpubs/TB

M_122/ABKGLOS_e.html



Project Team Software engineer or writer assigned to a project

Member (PTM)

Responsible for completing project tasks, providing input to

plans, and providing status



Project Management This is a distinct and temporary organisational unit led by the

Office (PMO) project manager tasked to administer a project. It consists of

assigned full or part-time members of the sponsoring

department and, when appropriate, representatives of

participating departments working together in accordance

with any interdepartmental agreements or memorandums of

understanding.

http://www.publiservice.tbs-sct.gc.ca/pubs_pol/dcgpubs/TB





Organisation Title/Subject Number

TBS/CIOB/EMF Project Tracking & Oversight Process PPTO-PS-003

Owner Approved by Date Version Page 1

EMF J. Ginley January 2000 1.0

Role Description/Responsibilities



M_122/ABKGLOS_e.html



Quality Assurance Responsible for support of quality assurance activities.

(QA)



Configuration Responsible for support of configuration management

Management (CM) activities.







1.4 Definitions and Acronyms

Refer to Enhanced Management Framework Lexicon.



Refer to Enhanced Management Framework Acronyms.



Refer to Enhanced Management Framework Web Links







1.5 References

1.5.1 Traceability

This process was designed to satisfy the SEI Software Capability Maturity

Model goals for Level 2 Key Practice: Software Project Tracking and

Oversight.



1.5.2 Policies

Treasury Board Secretariat Policies:



 Capital Plans - Glossary



 Management of Major Crown Projects



 Procurement Review Policy



 Project Management



 Project Approval



The policies above are located at the following URL:



http://www.publiservice.tbs-sct.gc.ca/pubs_pol/dcgpubs/TBM_122/siglist_e.ht

ml









Organisation Title/Subject Number

TBS/CIOB/EMF Project Tracking & Oversight Process PPTO-PS-003

Owner Approved by Date Version Page 2

EMF J. Ginley January 2000 1.0

1.5.3 Standards

Annex A – Flowcharting Symbols



1.5.4 Processes

PPTO-PS-001 Project Management Process



PPTO-PS-002 Project Planning Process



PEER-PS-001 Peer Review Process



1.5.5 Procedures

PPTO-PD-001 Estimate Software Product Size Basic Procedure



PPTO-PD-002 Estimate Project Resources/Schedule Basic Procedure



1.5.6 Guidelines

EMF Business Case Guideline



1.5.7 Templates

PPTO-TM-001 Process/Procedure Template



PPTO-TM-002 Project Plan Template



PPTO-TM-003 Project Estimates Template



EMF Project Charter Template



1.5.8 Checklists

PPTO-CK-001 Project Management Checklist



1.5.9 Training

For further information on training:



Go to www.cio-dpi.gc.ca/emf-cag/index_e.asp



1.5.10 Tools

For further information on tools:



Go to

http://www.cio-dpi.gc.ca/emf/Publications/SoftwareToolsReport/stf_e.html



1.6 Inquiries

For further information on this process:



Go to www.cio-dpi.gc.ca/emf-cag/index_e.asp



Organisation Title/Subject Number

TBS/CIOB/EMF Project Tracking & Oversight Process PPTO-PS-003

Owner Approved by Date Version Page 3

EMF J. Ginley January 2000 1.0

2. Process

2.1 Entry Criteria

The following entry criteria describes the input’s state, an event, or an expired amount

of time, which is required before this process can begin.



Details of Entry Criteria

 Approved Business Case

 Approved Project Charter

 Approved Set of Requirements, as required by your IM/IT methodologies

 Approved Project Plan





2.2 Process Map

The overall process flow given below shows the interaction and flow among the

activities. More details about the activities can be found in 2.4 Activities.









Organisation Title/Subject Number

TBS/CIOB/EMF Project Tracking & Oversight Process PPTO-PS-003

Owner Approved by Date Version Page 4

EMF J. Ginley January 2000 1.0

Project Tracking Process

1

Project Planning







2

Obtain Tracking

Requirements





3

Obtain Baseline







4

• Collect Actuals

• Compare Actuals

to Plans





5

• Evaluate Status

and Performance

• Monitor risks





6

• Status Meeting

• Project Review

• Commitment

Review









Yes Re-planning No Project Yes Post

Needed? Complete? Mortem









Organisation Title/Subject Number

TBS/CIOB/EMF Project Planning Process PPTO-PS-002

Owner Approved by Date Version Page 5

EMF J. Ginley January 2000 1.0

2.3 Inputs

The following inputs are used in this process. Where they don’t exist, identify any

associated risks.



Input Detail of Inputs and remarks Ref.

Project Plan  Original or Revised PPTO-TM-002

Project Actuals  The current status of the project









Organisation Title/Subject Number

TBS/CIOB/EMF Project Tracking & Oversight Process PPTO-PS-003

Owner Approved by Date Version Page 6

EMF J. Ginley January 2000 1.0

2.4 Activities

The following activities are performed in this process. Document all assumptions,

risks, constraints etc. in the Project Plan.



No. Activities Action Detail of Activities and Remarks Ref.

by

1  Project PM  Project planning in the context of PPTO-PS-002

Planning overall project management is PPTO-PS-001

documented in the referenced

documents.

2  Obtain PM  Obtain the data collection requirements PPTO-PS-002

Tracking for project tracking from the Project

Plan. PPTO-PS-001

Requirements

PPTO-TM-002



3  Obtain PM  Obtain the baselined estimates from PPTO-PS-002

Baseline the Project Plan. PPTO-PS-001

PPTO-TM-002

4  Collect PM  Collect and store the current actual PPTO-PS-002

Actuals values of the tracking data, and PPTO-PS-001

compare them to the baselined

 Compare PPTO-TM-002

estimates.

Actuals to

Plans  Perform according to Project Plan

Schedule.

5  Evaluate PM  Evaluate the project's performance and PPTO-PS-002

Status and status relative to the plan. Identify the PPTO-PS-001

Performance reasons for deviations from the plan;

identify both delays and accelerations; PPTO-TM-002

 Monitor Risks

and monitor risks.

6  Status  Determine whether the project's PPTO-PS-002

Meeting objectives, plan, or resources need to PPTO-PS-001

be adjusted.

 Project

Review  Re-planning Needed?

 Commitment  [Yes] Go to activity 1.

Review

 [No] Is project completed?

 [Yes] Write postmortem.

 [No] Go to activity 4.









Organisation Title/Subject Number

TBS/CIOB/EMF Project Tracking & Oversight Process PPTO-PS-003

Owner Approved by Date Version Page 7

EMF J. Ginley January 2000 1.0

2.5 Outputs

The following outputs are produced or modified by the activities in this process.



Output Detail of Outputs and Remarks Ref.

Project Logs  Update issue log, decision log, action log and risk

and Status log.

Report

 Document:

 Reasons for deviations from the plan

 Corrective actions taken

 Recommendations for further adjustments



 Track and report on requirement changes, size,

schedule, cost, quality, people and resources such as

equipment, tool, training, development

environments, infrastructure, as defined in the

Project Plan.



 Assess and document status as per the schedule and

reporting requirements defined in the Project Plan.



 Store the logs and status reports in the project’s

quality records to form part of the projects historical

data.



Project  Conduct a postmortem to capture lessons learned.

Postmortem







2.6 Verification and Validation



Output To determine if the outputs are within specification,

Validation

 Use the (PEER-PS-001) Peer Review Process

and any techniques described in your IM/IT

methodology.

 Use validation techniques referred to in your

IM\IT methodology such as testing,

demonstration, analysis and inspection.









Organisation Title/Subject Number

TBS/CIOB/EMF Project Tracking & Oversight Process PPTO-PS-003

Owner Approved by Date Version Page 8

EMF J. Ginley January 2000 1.0

2.7 Exit Criteria



Details of Exit Criteria

 Client approves, revises or terminates the project, product or services.

 Approved postmortem.





2.8 Metrics

Refer to Enhanced Management Framework, Exposure Draft Executive Toolkit,

November 22, 1999 for the Project Health Check Dashboard.



2.9 Records Control Table

Not applicable at this time. Populate table if seeking ISO certification. For more

information, refer to (PPTO-TM-001) Process/Procedure Template.



Description Storage Location Filing / Index Minimum

(no. and name) Storage Period









2.10 Controlled Documents Table

Not applicable at this time. Populate if seeking ISO certification. For more

information, refer to (PPTO-TM-001) Process/Procedure Template.



Number Name Revision Owner

Date

(or version)









Organisation Title/Subject Number

TBS/CIOB/EMF Project Tracking & Oversight Process PPTO-PS-003

Owner Approved by Date Version Page 9

EMF J. Ginley January 2000 1.0

Annex A – Lexicon

Refer to the Enhanced Management Framework Lexicon or insert a reference to your

organisation’s Lexicon.









Organisation Title/Subject Number

TBS/CIOB/EMF Project Tracking & Oversight Process PPTO-PS-003

Owner Approved by Date Version Page 10

EMF J. Ginley January 2000 1.0

Annex B – Acronyms

Refer to the Enhanced Management Framework Acronyms or insert a reference to your

organisation’s Acronyms.









Organisation Title/Subject Number

TBS/CIOB/EMF Project Tracking & Oversight Process PPTO-PS-003

Owner Approved by Date Version Page 11

EMF J. Ginley January 2000 1.0

Annex C – Flowcharting Symbols









Parallelograms represent inputs and outputs

to or from a process/procedure.









Rectangles represent individual Diamonds represent important decision points

process/procedure activities. in the process/procedure.









Lines with arrowheads connect symbols to Circles represent connectors when a

show the progression or direction of the process/procedure flowchart continues on the

activities. next page.









Organisation Title/Subject Number

TBS/CIOB/EMF Project Tracking & Oversight Process PPTO-PS-003

Owner Approved by Date Version Page 12

EMF J. Ginley January 2000 1.0

Annex D – Bibliography

Caputo, Kim, CMM Implementation Guide: Choreographing Software Process Improvement.

Addison Wesley, Reading, Massachusetts, 1998.



Refer to Enhanced Management Framework Web Links.









Organisation Title/Subject Number

TBS/CIOB/EMF Project Tracking & Oversight Process PPTO-PS-003

Owner Approved by Date Version Page 13

EMF J. Ginley January 2000 1.0

Annex E – Document Change Control



Revision Date of Issue Author(s) Brief Description of Change

Number

0.1 1999-09-23 EMF/PPTO Draft 0.1

1.0 1999-11-09 EMF/PPTO First Draft

1.0 2000-01-13 EMF/PPTO Second Draft









Organisation Title/Subject Number

TBS/CIOB/EMF Project Tracking & Oversight Process PPTO-PS-003

Owner Approved by Date Version Page 14

EMF J. Ginley January 2000 1.0


Related docs
Other docs by HC11111003536
ars_cluster_E_1_1
Views: 68  |  Downloads: 0
RClist
Views: 186  |  Downloads: 0
walkon
Views: 0  |  Downloads: 0
Workbook
Views: 3  |  Downloads: 0
part_c
Views: 0  |  Downloads: 0
downloadasset
Views: 0  |  Downloads: 0
Karn 20lesson 202
Views: 0  |  Downloads: 0
MHEOCC
Views: 0  |  Downloads: 0
priusprimer
Views: 0  |  Downloads: 0
CVdesign
Views: 1  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!