Embed
Email

ND East 35k Gated

Document Sample

Shared by: xiaopangnv
Categories
Tags
Stats
views:
1
posted:
11/8/2011
language:
English
pages:
24
BARR ENGINEERING DATE 2/4/2011 SHEET NO.

PROJECT NAME Flood Control ND East (Red River) - Corps Of Engineers

COMPUTED CHECKED SUBMITTED PROJECT NUMBER

PKN PKN SUBJECT Control Structure: ND East 35k s35k

2/4/11





Gravity Dam Structure UNIT TOTAL

ITEM UNIT QUANITY COST Cost Structure Length = 182



FURNISH HP14x73 WALL PILING LF 11,037 0 $0 No. piles = 318

INSTALL HP14x73 WALL PILING LF 11,037 0 $0 Length = 34.71 ft

PILE TEST, 45 ft EA 8 0 $0 ASSUME SPACING: 40 ft 1 test pile along each ftg face TOTAL

Forming L h Area bulkheads W h Area sf

FOOTING CONCRETE CY 2,273 0 $0 364 4 1456.0 2 84.29 4 337.2 1,793

Pier CONCRETE CY 3,759 0 $0 8 78.29 53.61 33576.4 8 8 53.61 3431.0 37,007

DECK CONCRETE CY 128 BOT 150 15 2250.0 5 15 1 75.0

OR SF 2730 0 $0 SIDE 364 1 364.0 2,689





STEEL REINFORCEMENT LB 467,450 0 $0



Tainter Gates (Furnish) EA 3 0 $0 w (ft) h( ft) sf $ / sf $

50 47 2209 400 883600

Gate Hoist EA 3 0 $0 50 42 1764 400 705600 7/9/2010

445

Install Gates EA 3 0 $0





BRIDE RAILING LF 364 0 $0

LENGTH

SHEET PILE CUT-OFF WALL SF 3,640 0 $0 (FRONT FACE ONLY) 10 FT

Native Soil has low permeability assume cut-off

minimal to prevent scour

$0



Unload PZ27 Sheet Piles

Total Wt = 98,280 lbs

Truck Capacity = 40,000 lbs No. of Trucks = 3

Unload HP 14 x73 Piles

Total Wt = 805,701 lbs Drive Pairs of PZ27 Sheet Piles w = 1.5 ft (single)

No. of Trucks = 21 Wall Length = 364 ft

No. Pairs = 121 EA

BARR ENGINEERING DATE 2/4/2011 SHEET NO.

PROJECT NAME Flood Control ND East (Red River) - Corps Of Engineers

COMPUTED CHECKED SUBMITTEDPROJECT NUMBER

PKN PKN SUBJECT Control Structure: ND East 35k s35k

2/4/11 Load Cases: 1 (usual)



Case 1

Event 100 years Provide Round Pier Nose w/Armor R= 4.0 ft



H.W. EL = 922.01 ft No. Gates 3 Number of Piers: 4 Piers between gates & Each Side

T.W. EL. = 902.41 ft Gate Width = 50 ft Pier Width = 8.0 ft EA. / assume

Gate Inv. El. 875.51 ft Total Pier Width = 32.0 ft

500 yr H.W. EL = 922.12 ft Min Gate Ht= 46.61 ft Total Gate Width = 150.0 ft REVISED PER 7/1/10 MEETING WITH CORPS

Actual Ht = 47.00 ft Gated Section Length = 182.0 ft Top of Conc =2 ft beyond Free Board at levee (3 ft) = 5 ft

The skin Plate radius will normally be set

equal to or greater than the height of the gate. For Dam Profiles see EM 1110-2-2200 Gravity Dam Design, 4-3

Rmin = 47.00 ft 39.99' 3.296' 15.0' 8.0'

Actual radius, R = 47.00 ft 500 yr Event H.W. + 5 ft freeboard Bulkhead approx. 3.0' deep (also need BH slot on DS side of trunion)

Trunion Location: 15.67 ft, 1/3 Gate ht El. 927.12

Trial Trunion El = 891.18 7

2 yr T.W. EL = 896.82 Top of Gate El.922.5 1.0'

2 yr Gate ht Ratio = 0.45340426 Slope usually between 0.71 1 H.W. EL. 922.01

0.7H to 0.8 H to 1V 1 or 1.408 ICE = 0 ksf

T.W. El. 902.41 h1 = 28.3'

L4 = 26.20 8

EL. 898.82 11 Ice Loading is for Ice Floe on single Pier Only

REVISED PER 2/1/11 MEETING WITH CORPS

1

h = 53.61'

5 3

2

22.31' 28.90' 10

4 Hw = 52.50'

El. 875.5

12.00' 41.37' HHW = 85.995 k/ft

TW = 32.90'

HTW = 33.771 k/ft 12 2.0' 17.50'

6 El. 873.5

10.97

4.0'

gh = 2.053 ksf 8.23' 38.06' El. 869.5 gh = 3.276 ksf

"B"

34.29' 24.0'

3.0' 46.29' 32.00' 3.00'



See Piling Plan for Vert Loads and Horiz Resistance B = 84.29'









Case 1 or 2: 1

Normal Water Level, El.888.74 ft REVISED PER 7/1/10 MEETING WITH CORPS

Dh normal = 19.2 ft UPLIFT Case 1, Full Hydrostatic Head (Dashed Line)

See Geotechnical seepage Model UB = 2.053 ksf Case 2, Full HW in Front of Upstream sheets

Full TW on down stream of sheets

UA = 3.276 ksf

1.0' 82.29 1.0' enter "0" if no cut-off



Non-Overflow Dam

L W H g shape V arm Mv

Vertical Loads Section ft ft ft kcf K ft ft-k Gate Information wt = 100 psf

Pier Concrete 1 32 8.00 53.61 0.15 rec 2058.6 77.29 159,108 w h Gate Wt

Pier Concrete 2 32 24.00 53.61 0.15 rec 6175.9 61.29 378,510 mono Gate ft ft lbs # of Gates

Back of Pier 3 32 38.06 53.61 0.15 tri 4897.4 36.60 179,247 mono 1 50 2.0 3 Low Flow

Back of Pier 4 32 17.97 25.31 0.15 tri 1091.6 17.22 18,792 2 50 47.0 235000 3

Pier Concrete 5 32 8.23 25.31 0.15 rec 999.3 7.11 7,108

Ftg concrete 6 182 84.29 4.00 0.15 rec 9204.3 42.14 387,909

Bridge Slab 7 182 15.00 0.83 0.15 rec 341.1 65.79 22,441

Bridge Beams 7 364 2.17 1.50 0.15 rec 177.5 65.79 11,676 Bms 2@ 18" x 26"

Tainter Gates 8 3.00 50.00 47.00 0.100 rec 705.0 59.18 41,725 approx arm, 3 gates @ 100 psf

D.L. Concrete SVc = 25650.6 SMV = 1,206,516.0 CONSTANT FOR ALL LOAD CASES



Water I.S. Low Flow 12 150 78.29 2.00 0.0624 rec 1465.6 42.14 61,765



Page 2 of 24

BARR ENGINEERING DATE 2/4/2011 SHEET NO.

PROJECT NAME Flood Control ND East (Red River) - Corps Of Engineers

COMPUTED CHECKED SUBMITTEDPROJECT NUMBER

PKN PKN SUBJECT Control Structure: ND East 35k s35k

2/4/11 Load Cases: 1 (usual)



T.W on ftg 10 182 3.00 28.90 0.0624 rec 984.6 1.50 1,477

TW behind Tainter Gates 1, 2, 3 150 56.18 26.90 0.0624 rec 14146.2 31.09 439,830 above low flow, behind gate…assume rectangular

T.W above Pier 5 32 26.20 3.59 0.0624 rec 187.8 16.10 3,023 above L4

T.W. on Pier Slope 4 32 2.55 3.59 0.0624 tri 9.1 30.05 274 on back slope of pier

H.W. in front of Gates 11 150 22.10 46.50 0.0624 rec 9620.9 70.24 675,735 above low flow

H.W. on Proj. ftg 11 182 3.00 48.50 0.0624 rec 1652.4 82.79 136,801

D.L. Water SVw = 28066.6 SMV = 1,318,906



L W Pressure U arm Mu

Uplift Loads ft ft ksf K ft ft-k

UB 182 84.29 2.053 rec -31493.5 42.14 -1,327,269

UA 182 84.29 1.223 tri -9381.0 56.19 -527,142

SU = -40874.5 SMU = -1,854,412







Horizontal Loads L H Pressure ICE arm Mu

ft ft ksf K ft ft-k Ice Loading is for Ice Floe on single Pier Only

ICE 8.0 ft 1.00 0.00 rec 0.0 52 0 REVISED PER 2/1/11 MEETING WITH CORPS



L Force H arm Mw

Water Loads ft k/ft K ft ft-k

HTW 182 33.771 tri 6146.36 10.97 67405.05

HHW 182 85.995 tri -15651.09 17.50 -273894.08

SW = -9504.73 SMW = -206489.0







Overturning Moments SMOT = MU +MW +MICE = -2060900.64 kip-ft

Resisting Moments SMR = MV = 2,525,422.1 kip-ft





Sum of Moments SMnet = MR + MOT = 464,521 kip-ft

Sum of Vertical Forces P = Conc + Water + Uplift = 12,843 kips

Sum of Horizontal Forces H = Ice + water = -9,505 kips









Location of Resultant Xr = SM / P = 36.17 ft from Toe

e = B/2 - Xr = 5.97 ft

B/6 = 14.04809









Page 3 of 24

BARR ENGINEERING DATE 2/4/2011 SHEET NO.

PROJECT NAME Flood Control ND East (Red River) - Corps Of Engineers

COMPUTED CHECKED SUBMITTEDPROJECT NUMBER

PKN PKN SUBJECT Control Structure: ND East 35k s35k

2/4/11 Load Cases: 1.1 (unsual)



Case 1.1

Event 100 years Provide Round Pier Nose w/Armor R= 4.0 ft



H.W. EL = 922.01 ft No. Gates 3 Number of Piers: 4 Piers between gates & Each Side

T.W. EL. = 902.41 ft Gate Width = 50 ft Pier Width = 8.0 ft EA. / assume

Gate Inv. El. 875.51 ft Total Pier Width = 32.0 ft

500 yr H.W. EL = 922.12 ft Min Gate Ht= 46.61 ft Total Gate Width = 150.0 ft REVISED PER 7/1/10 MEETING WITH CORPS

Actual Ht = 47 ft Gated Section Length = 182.0 ft Top of Conc =2 ft beyond Free Board at levee (3 ft) = 5 ft

The skin Plate radius will normally be set

equal to or greater than the height of the gate. For Dam Profiles see EM 1110-2-2200 Gravity Dam Design, 4-3

Rmin = 47.00 ft 39.99' 3.296' 15.0' 8.0'

Actual radius, R = 47.00 ft 500 yr Event H.W. + 5 ft freeboard Bulkhead approx. 3.0' deep (also need BH slot on DS side of trunion)

Trunion Location: 15.67 ft, 1/3 Gate ht El. 927.12

Trial Trunion El = 891.18 7

2 yr T.W. EL = 896.82 Top of Gate El.922.5 1.0'

2 yr Gate ht Ratio = 0.45340426 Slope usually between 0.71 1 H.W. EL. 922.01

0.7H to 0.8 H to 1V 1 or 1.408 ICE = 8.064 ksf

T.W. El. 902.41 h1 = 28.3'

L4 = 26.20 8

EL. 898.82 11



1

h = 53.61'

5 3

2

22.31' 28.90' 10

4 Hw = 52.50'

El. 875.5

12.00' 41.37' HHW = 85.995 k/ft

TW = 32.90'

HTW = 33.771 k/ft 12 2.0' 17.50'

6 El. 873.5

10.97

4.0'

gh = 2.053 ksf 8.23' 38.06' El. 869.5 gh = 3.276 ksf

"B"

34.29' 24.0'

3.0' 46.29' 32.00' 3.00'



See Piling Plan for Vert Loads and Horiz Resistance B = 84.29'









Case 1 or 2: 1

Normal Water Level, El.888.74 ft REVISED PER 7/1/10 MEETING WITH CORPS

Dh normal = 19.2 ft UPLIFT Case 1, Full Hydrostatic Head (Dashed Line)

See Geotechnical seepage Model UB = 2.053 ksf Case 2, Full HW in Front of Upstream sheets

Full TW on down stream of sheets

UA = 3.276 ksf

1.0' 82.29 1.0' enter "0" if no cut-off



Non-Overflow Dam

L W H g shape V arm Mv

Vertical Loads Section ft ft ft kcf K ft ft-k Gate Information wt = 100 psf

Pier Concrete 1 32 8.00 53.61 0.15 rec 2058.6 77.29 159,108 w h Gate Wt

Pier Concrete 2 32 24.00 53.61 0.15 rec 6175.9 61.29 378,510 mono Gate ft ft lbs # of Gates

Back of Pier 3 32 38.06 53.61 0.15 tri 4897.4 36.60 179,247 mono 1 50 2.0 3 Low Flow

Back of Pier 4 32 17.97 25.31 0.15 tri 1091.6 17.22 18,792 2 50 47.0 235000 3

Pier Concrete 5 32 8.23 25.31 0.15 rec 999.3 7.11 7,108

Ftg concrete 6 182 84.29 4.00 0.15 rec 9204.3 42.14 387,909

Bridge Slab 7 182 15.00 0.83 0.15 rec 341.1 65.79 22,441

Bridge Beams 7 364 2.17 1.50 0.15 rec 177.5 65.79 11,676 Bms 2@ 18" x 26"

Tainter Gates 8 3.00 50.00 47.00 0.100 rec 705.0 59.18 41,725 approx arm, 3 gates @ 100 psf

D.L. Concrete SVc = 25650.6 SMV = 1,206,516.0 CONSTANT FOR ALL LOAD CASES



Water I.S. Low Flow 12 150 78.29 2.00 0.0624 rec 1465.6 42.14 61,765





Page 4 of 24

BARR ENGINEERING DATE 2/4/2011 SHEET NO.

PROJECT NAME Flood Control ND East (Red River) - Corps Of Engineers

COMPUTED CHECKED SUBMITTEDPROJECT NUMBER

PKN PKN SUBJECT Control Structure: ND East 35k s35k

2/4/11 Load Cases: 1.1 (unsual)



T.W on ftg 10 182 3.00 28.90 0.0624 rec 984.6 1.50 1,477

TW behind Tainter Gates 1, 2, 3 150 56.18 26.90 0.0624 rec 14146.2 31.09 439,830 above low flow, behind gate…assume rectangular

T.W above Pier 5 32 26.20 3.59 0.0624 rec 187.8 16.10 3,023 above L4

T.W. on Pier Slope 4 32 2.55 3.59 0.0624 tri 9.1 30.05 274 on back slope of pier

H.W. in front of Gates 11 150 22.10 46.50 0.0624 rec 9620.9 70.24 675,735 above low flow

H.W. on Proj. ftg 11 182 3.00 48.50 0.0624 rec 1652.4 82.79 136,801

D.L. Water SVw = 28066.6 SMV = 1,318,906



L W Pressure U arm Mu

Uplift Loads ft ft ksf K ft ft-k

UB 182 84.29 2.053 rec -31493.5 42.14 -1,327,269

UA 182 84.29 1.223 tri -9381.0 56.19 -527,142

SU = -40874.5 SMU = -1,854,412







Horizontal Loads L H Pressure ICE arm Mu

ft ft ksf Ca K ft ft-k Ice Loading is for Ice Floe on single Pier Only

ICE 8.0 ft 1.00 8.06 1.2748 rec -82.2 52 -4,276 REVISED PER 2/1/11 MEETING WITH CORPS

Ca = (5 t/w +1)0.5

L Force H arm Mw

Water Loads ft k/ft K ft ft-k

HTW 182 33.771 tri 6146.36 10.97 67405.05

HHW 182 85.995 tri -15651.09 17.50 -273894.08

SW = -9504.73 SMW = -206489.0







Overturning Moments SMOT = MU +MW +MICE = -2065176.97 kip-ft

Resisting Moments SMR = MV = 2,525,422.1 kip-ft





Sum of Moments SMnet = MR + MOT = 460,245 kip-ft

Sum of Vertical Forces P = Conc + Water + Uplift = 12,843 kips

Sum of Horizontal Forces H = Ice + water = -9,587 kips









Location of Resultant Xr = SM / P = 35.84 ft from Toe

e = B/2 - Xr = 6.31 ft

B/6 = 14.04809









Page 5 of 24

BARR ENGINEERING DATE 2/4/2011 SHEET NO.

PROJECT NAME Flood Control ND East (Red River) - Corps Of Engineers

COMPUTED CHECKED SUBMITTEDPROJECT NUMBER

PKN PKN SUBJECT Control Structure: ND East 35k s35k

2/4/11 Load Cases: 2 Water at 500 Yr HW



Case 2 Per MW1: Use 500 only 1/21/11

Event 500 years + 0.00 ft (ht of Levees) Provide Round Pier Nose w/Armor R= 4.0 ft



H.W. EL = 922.12 ft No. Gates 3 Number of Piers: 4 Piers between gates & Each Side

T.W. EL. = 914.41 ft Gate Width = 50 ft Pier Width = 8.0 ft EA. / assume

Gate Inv. El. 875.51 ft Total Pier Width = 32.0 ft

500 yr H.W. EL = 922.12 ft Min Gate Ht= 46.61 ft Total Gate Width = 150.0 ft

Actual Ht = 47.00 ft Gated Section Bulkhead approx.

Length = 182.0 ft 3.0' deep (also need BH slot on DS side of trunion)

The skin Plate radius will normally be set

equal to or greater than the height of the gate. For Dam Profiles see EM 1110-2-2200 Gravity Dam Design, 4-3

Rmin = 47.00 ft 39.99' 3.296' 15.0' 8.0'

Actual radius, R = 47.00 ft 500 yr Event H.W. + 5 ft freeboard

Trunion Location: 15.67 ft, 1/3 Gate ht El. 927.12 1.0'

Trial Trunion El = 891.18 7 H.W. EL. 922.12

2 yr T.W. EL = 896.82 Top of Gate El.922.5 ICE = 0 ksf

2 yr Gate ht Ratio = 0.45340426 Slope usually between 0.71 1

0.7H to 0.8 H to 1V 1 or 1.408

T.W. El. 914.41 h1 = 28.3'

L4 = 26.20 8

EL. 898.82 11



1

h = 53.61'

5 3

2

22.31' 40.90' 10

4 Hw = 52.61'

El. 875.5

12.00' 41.37' HHW = 86.356 k/ft

TW = 44.90'

HTW = 62.900 k/ft 12 2.0' 17.54'

6 El. 873.5

14.97

4.0'

gh = 2.802 ksf 8.23' 38.06' El. 869.5 gh = 3.283 ksf

"B"

34.29' 24.0'

3.0' 46.29' 32.00' 3.0'



See Piling Plan for Vert Loads and Horiz Resistance B = 84.29'









Case 1 or 2: 1

Normal Water Level, El.888.74 ft REVISED PER 7/1/10 MEETING WITH CORPS

Dh normal = 19.2 ft UPLIFT Case 1, Full Hydrostatic Head (Dashed Line)

See Geotechnical seepage Model UB = 2.802 ksf Case 2, Full HW in Front of Upstream sheets

Full TW on down stream of sheets

UA = 3.283 ksf

1.0' 82.29 1.0' enter "0" if no cut-off



Non-Overflow Dam

L W H g shape V arm Mv

Vertical Loads Section ft ft ft kcf K ft ft-k Gate Information wt = 100 psf

Pier Concrete 1 32 8.00 53.61 0.15 rec 2058.6 77.29 159,108.1 w h Gate Wt

Pier Concrete 2 32 24.00 53.61 0.15 rec 6175.9 61.29 378,510.2 mono Gate ft ft lbs # of Gates

Back of Pier 3 32 38.06 53.61 0.15 tri 4897.4 36.60 179,247.2 mono 1 50 2.0 3 Low Flow

Back of Pier 4 32 17.97 25.31 0.15 tri 1091.6 17.22 18,792.0 2 50 47.0 235000 3

Pier Concrete 5 32 8.23 25.31 0.15 rec 999.3 7.11 7,107.7

Ftg concrete 6 182 84.29 4.00 0.15 rec 9204.3 42.14 387,908.9

Bridge Slab 7 182 15.00 0.83 0.15 rec 341.1 65.79 22,441.4

Bridge Beams 7 364 2.17 1.50 0.15 rec 177.5 65.79 11,676.0 Bms 2@ 18" x 26"

Tainter Gates 8 3.00 50.00 47.00 0.100 rec 705.0 59.18 41,724.5 approx arm, 3 gates @ 100 psf

D.L. Concrete SVc = 25650.6 SMV = 1,206,516.0 CONSTANT FOR ALL LOAD CASES



Water I.S. Low Flow 12 150 78.29 2.00 0.0624 rec 1465.6 42.14 61,765.0





Page 6 of 24

BARR ENGINEERING DATE 2/4/2011 SHEET NO.

PROJECT NAME Flood Control ND East (Red River) - Corps Of Engineers

COMPUTED CHECKED SUBMITTEDPROJECT NUMBER

PKN PKN SUBJECT Control Structure: ND East 35k s35k

2/4/11 Load Cases: 2 Water at 500 Yr HW



T.W on ftg 10 182 3.00 40.90 0.0624 rec 1393.5 1.50 2,090.2

TW behind Tainter Gates 1, 2, 3 150 56.18 38.90 0.0624 rec 20456.7 31.09 636,037.2 above low flow, behind gate…assume rectangular

T.W above Pier 5 32 26.20 15.59 0.0624 rec 815.5 16.10 13,127.3 above L4

T.W. on Pier Slope 4 32 11.07 15.59 0.0624 tri 172.3 32.89 5,665.7 on back slope of pier

H.W. in front of Gates 11 150 22.10 46.61 0.0624 rec 9643.7 70.24 677,333.9 above low flow

H.W. on Proj. ftg 11 182 3.00 48.61 0.0624 rec 1656.2 82.79 137,111.3

D.L. Water SVw = 35603.3 SMV = 1,533,130.6



L W Pressure U arm Mu

Uplift Loads ft ft ksf K ft ft-k

UB 182 84.29 2.802 rec -42980.4 42.14 -1,811,380

UA 182 84.29 0.481 tri -3690.2 56.19 -207,361

SU = -46670.6 SMU = -2,018,740







Horizontal Loads L H Pressure ICE arm Mu Ice Loading is for Ice Floe on single Pier Only

ft ft ksf K ft ft-k REVISED PER 2/1/11 MEETING WITH CORPS

ICE 8.0 ft 1.00 0.00 rec 0.0 52.11 0.0



L Force H arm Mw

Water Loads ft k/ft K ft ft-k

HTW 182 62.900 tri 11447.71 14.97 171334.08

HHW 182 86.356 tri -15716.74 17.54 -275619.30

SW = -4269.03 SMW = -104285.2







Overturning Moments SMOT = MU +MW +MICE = -2123025.41 kip-ft

Resisting Moments SMR = MV = 2,739,646.6 kip-ft





Sum of Moments SMnet = MR + MOT = 616,621 kip-ft

Sum of Vertical Forces P = Conc + Water + Uplift = 14,583 kips

Sum of Horizontal Forces H = Ice + water = -4,269 kips





Location of Resultant Xr = SM / P = 42.28 ft from Toe

e = B/2 - Xr = (0.14) ft

B/6 = 14.04809









Page 7 of 24

BARR ENGINEERING DATE 2/4/2011 SHEET NO.

PROJECT NAME Flood Control ND East (Red River) - Corps Of Engineers

COMPUTED CHECKED SUBMITTEDPROJECT NUMBER

PKN PKN SUBJECT Control Structure: ND East 35k s35k

2/4/11 Load Cases: 2.1 Water at 500 Yr HW



Case 2.1 Per COE: HW = 500yr + 5' w/ No ice

Event 500 years + 5.00 ft (ht of Levees) Provide Round Pier Nose w/Armor R= 4.0 ft



H.W. EL = 927.12 ft No. Gates 3 Number of Piers: 4 Piers between gates & Each Side

T.W. EL. = 914.41 ft Gate Width = 50 ft Pier Width = 8.0 ft EA. / assume

Gate Inv. El. 875.51 ft Total Pier Width = 32.0 ft

500 yr H.W. EL = 922.12 ft Min Gate Ht= 46.61 ft Total Gate Width = 150.0 ft

Actual Ht = 47.00 ft Gated Section Bulkhead approx.

Length = 182.0 ft 3.0' deep (also need BH slot on DS side of trunion)

The skin Plate radius will normally be set

equal to or greater than the height of the gate. For Dam Profiles see EM 1110-2-2200 Gravity Dam Design, 4-3

Rmin = 47.00 ft 39.99' 3.296' 15.0' 8.0'

Actual radius, R = 47.00 ft 500 yr Event H.W. + 5 ft freeboard

Trunion Location: 15.67 ft, 1/3 Gate ht El. 927.12 1.0'

Trial Trunion El = 891.18 7 H.W. EL. 927.12

2 yr T.W. EL = 896.82 Top of Gate El.922.5 ICE = 0 ksf

2 yr Gate ht Ratio = 0.45340426 Slope usually between 0.71 1

0.7H to 0.8 H to 1V 1 or 1.408

T.W. El. 914.41 h1 = 28.3'

L4 = 26.20 8

EL. 898.82 11



1

h = 53.61'

5 3

2

22.31' 40.90' 10

4 Hw = 57.61'

El. 875.5

12.00' 41.37' HHW = 103.550 k/ft

TW = 44.90'

HTW = 62.900 k/ft 12 2.0' 19.20'

6 El. 873.5

14.97

4.0'

gh = 2.802 ksf 8.23' 38.06' El. 869.5 gh = 3.595 ksf

"B"

34.29' 24.0'

3.0' 46.29' 32.00' 3.0'



See Piling Plan for Vert Loads and Horiz Resistance B = 84.29'









Case 1 or 2: 1

Normal Water Level, El.888.74 ft REVISED PER 7/1/10 MEETING WITH CORPS

Dh normal = 19.2 ft UPLIFT Case 1, Full Hydrostatic Head (Dashed Line)

See Geotechnical seepage Model UB = 2.802 ksf Case 2, Full HW in Front of Upstream sheets

Full TW on down stream of sheets

UA = 3.595 ksf

1.0' 82.29 1.0' enter "0" if no cut-off



Non-Overflow Dam

L W H g shape V arm Mv

Vertical Loads Section ft ft ft kcf K ft ft-k Gate Information wt = 100 psf

Pier Concrete 1 32 8.00 53.61 0.15 rec 2058.6 77.29 159,108.1 w h Gate Wt

Pier Concrete 2 32 24.00 53.61 0.15 rec 6175.9 61.29 378,510.2 mono Gate ft ft lbs # of Gates

Back of Pier 3 32 38.06 53.61 0.15 tri 4897.4 36.60 179,247.2 mono 1 50 2.0 3 Low Flow

Back of Pier 4 32 17.97 25.31 0.15 tri 1091.6 17.22 18,792.0 2 50 47.0 235000 3

Pier Concrete 5 32 8.23 25.31 0.15 rec 999.3 7.11 7,107.7

Ftg concrete 6 182 84.29 4.00 0.15 rec 9204.3 42.14 387,908.9

Bridge Slab 7 182 15.00 0.83 0.15 rec 341.1 65.79 22,441.4

Bridge Beams 7 364 2.17 1.50 0.15 rec 177.5 65.79 11,676.0 Bms 2@ 18" x 26"

Tainter Gates 8 3.00 50.00 47.00 0.100 rec 705.0 59.18 41,724.5 approx arm, 3 gates @ 100 psf

D.L. Concrete SVc = 25650.6 SMV = 1,206,516.0 CONSTANT FOR ALL LOAD CASES



Water I.S. Low Flow 12 150 78.29 2.00 0.0624 rec 1465.6 42.14 61,765.0





Page 8 of 24

BARR ENGINEERING DATE 2/4/2011 SHEET NO.

PROJECT NAME Flood Control ND East (Red River) - Corps Of Engineers

COMPUTED CHECKED SUBMITTEDPROJECT NUMBER

PKN PKN SUBJECT Control Structure: ND East 35k s35k

2/4/11 Load Cases: 2.1 Water at 500 Yr HW



T.W on ftg 10 182 3.00 40.90 0.0624 rec 1393.5 1.50 2,090.2

TW behind Tainter Gates 1, 2, 3 150 56.18 38.90 0.0624 rec 20456.7 31.09 636,037.2 above low flow, behind gate…assume rectangular

T.W above Pier 5 32 26.20 15.59 0.0624 rec 815.5 16.10 13,127.3 above L4

T.W. on Pier Slope 4 32 11.07 15.59 0.0624 tri 172.3 32.89 5,665.7 on back slope of pier

H.W. in front of Gates 11 150 22.10 51.61 0.0624 rec 10678.2 70.24 749,993.6 above low flow

H.W. on Proj. ftg 11 182 3.00 53.61 0.0624 rec 1826.5 82.79 151,214.5

D.L. Water SVw = 36808.2 SMV = 1,619,893.5



L W Pressure U arm Mu

Uplift Loads ft ft ksf K ft ft-k

UB 182 84.29 2.802 rec -42980.4 42.14 -1,811,380

UA 182 84.29 0.793 tri -6083.3 56.19 -341,836

SU = -49063.8 SMU = -2,153,215







Horizontal Loads L H Pressure ICE arm Mu

ft ft ksf Ca K ft ft-k Ice Loading is for Ice Floe on single Pier Only

ICE 8.0 ft 1.00 0.00 1.0000 rec 0.0 57.11 0.0 REVISED PER 2/1/11 MEETING WITH CORPS



L Force H arm Mw

Water Loads ft k/ft K ft ft-k

HTW 182 62.900 tri 11447.71 14.97 171334.08

HHW 182 103.550 tri -18846.11 19.20 -361908.14

SW = -7398.40 SMW = -190574.1







Overturning Moments SMOT = MU +MW +MICE = -2343789.35 kip-ft

Resisting Moments SMR = MV = 2,826,409.5 kip-ft





Sum of Moments SMnet = MR + MOT = 482,620 kip-ft

Sum of Vertical Forces P = Conc + Water + Uplift = 13,395 kips

Sum of Horizontal Forces H = Ice + water = -7,398 kips





Location of Resultant Xr = SM / P = 36.03 ft from Toe

e = B/2 - Xr = 6.11 ft

B/6 = 14.04809









Page 9 of 24

BARR ENGINEERING DATE 2/4/2011 SHEET NO.

PROJECT NAME Flood Control ND East (Red River) - Corps Of Engineers

COMPUTED CHECKED SUBMITTEDPROJECT NUMBER

PKN PKN SUBJECT Control Structure: ND East 35k s35k

2/4/11 Load Cases: 3 Construction, No Water



Case 3

Event 0 years Provide Round Pier Nose w/Armor R= 4.0 ft



H.W. EL = 0.00 ft No. Gates 3 Number of Piers: 4 Piers between gates & Each Side

T.W. EL. = 0.00 ft Gate Width = 50 ft Pier Width = 8.0 ft EA. / assume

Gate Inv. El. 875.51 ft Total Pier Width = 32.0 ft

500 yr H.W. EL = 922.12 ft Min Gate Ht= 46.61 ft Total Gate Width = 150.0 ft

Actual Ht = 47.00 ft Gated Section Length = Bulkhead approx.

182.0 ft 3.0' deep (also need BH slot on DS side of trunion)

The skin Plate radius will normally be set

equal to or greater than the height of the gate. For Dam Profiles see EM 1110-2-2200 Gravity Dam Design, 4-3

Rmin = 47.00 ft 39.99' 3.296' 15.0' 8.0'

Actual radius, R = 47.00 ft 500 yr Event H.W. + 5 ft freeboard

Trunion Location: 15.67 ft, 1/3 Gate ht El. 927.12

Trial Trunion El = 891.18 7

2 yr T.W. EL = 896.82 Top of Gate El.922.5

2 yr Gate ht Ratio = 0.45340426 Slope usually between 0.71 1

0.7H to 0.8 H to 1V 1 or 1.408

h1 = 28.3'

L4 = 26.20 8

EL. 898.82 11



1

h = 53.61'

5 3

2

22.31' 10

4

El. 875.5

12.00' 41.37'



12 2.0'

6 El. 873.5



4.0'

8.23' 38.06' El. 869.5

"B"

34.29' 24.0' 33.0 psf Wind

3.0' 46.29' 32.00' 3.0'



See Piling Plan for Vert Loads and Horiz Resistance B = 84.29'









Non-Overflow Dam

L W H g shape V arm Mv

Vertical Loads Section ft ft ft kcf K ft ft-k Gate Information wt = 100 psf

Pier Concrete 1 32 8.00 53.61 0.15 rec 2058.6 77.29 159,108.1 w h Gate Wt

Pier Concrete 2 32 24.00 53.61 0.15 rec 6175.9 61.29 378,510.2 mono Gate ft ft lbs # of Gates

Back of Pier 3 32 38.06 53.61 0.15 tri 4897.4 36.60 179,247.2 mono 1 50 2.0 3 Low Flow

Back of Pier 4 32 17.97 25.31 0.15 tri 1091.6 17.22 18,792.0 2 50 47.0 235000 3

Pier Concrete 5 32 8.23 25.31 0.15 rec 999.3 7.11 7,107.7

Ftg concrete 6 182 84.29 4.00 0.15 rec 9204.3 42.14 387,908.9

Bridge Slab 7 182 15.00 0.83 0.15 rec 341.1 65.79 22,441.4

Bridge Beams 7 364 2.17 1.50 0.15 rec 177.5 65.79 11,676.0 Bms 2@ 18" x 26"

Tainter Gates 8 3.00 50.00 47.00 0.100 rec 705.0 59.18 41,724.5 approx arm, 3 gates @ 100 psf

D.L. Concrete SVc = 25650.6 SMV = 1,206,516.0 CONSTANT FOR ALL LOAD CASES









Horizontal Loads L H Pressure arm Mu

ft ft ksf K ft ft-k

Wind 182 57.61 -0.033 rec -346.0 28.805 -9,966.7 assume gates down

150 2.0' 0.033 rec 9.9 5.0 49.5 deduct low flow





Page 10 of 24

BARR ENGINEERING DATE 2/4/2011 SHEET NO.

PROJECT NAME Flood Control ND East (Red River) - Corps Of Engineers

COMPUTED CHECKED SUBMITTEDPROJECT NUMBER

PKN PKN SUBJECT Control Structure: ND East 35k s35k

2/4/11 Load Cases: 3 Construction, No Water



SW = -336.11 SMWind = -9917.2





Overturning Moments SMOT = MWind = -9917.19 kip-ft/ft

Resisting Moments SMR = MV = 1,206,516.0 kip-ft/ft





Sum of Moments SMnet = MR + MOT = 1,196,599 kip-ft/ft

Sum of Vertical Forces P = Conc = 25,651 kips/ft

Sum of Horizontal Forces H = Wind = -336 kips/ft





Location of Resultant Xr = SM / P = 46.65 ft from Toe

e = B/2 - Xr = (4.51) ft

B/6 = 14.04809









Page 11 of 24

BARR ENGINEERING DATE 2/4/2011 SHEET NO.

PROJECT NAME Flood Control ND East (Red River) - Corps Of Engineers

COMPUTED CHECKED SUBMITTEDPROJECT NUMBER

PKN PKN SUBJECT Control Structure: ND East 35k s35k

2/4/11 Load Cases: 4 Normal Water Levels



Case 4

Event years Provide Round Pier Nose w/Armor R= 4.0 ft



H.W. EL = 888.74 ft No. Gates 3 Number of Piers: 4 Piers between gates & Each Side

T.W. EL. = 888.74 ft Gate Width = 50 ft Pier Width = 8.0 ft EA. / assume

Gate Inv. El. 875.51 ft Total Pier Width = 32.0 ft

500 yr H.W. EL = 922.12 ft Min Gate Ht= 46.61 ft Total Gate Width = 150.0 ft

Actual Ht = 47.00 ft Gated Section Bulkhead approx.

Length = 182.0 ft 3.0' deep (also need BH slot on DS side of trunion)

The skin Plate radius will normally be set

equal to or greater than the height of the gate. For Dam Profiles see EM 1110-2-2200 Gravity Dam Design, 4-3

Rmin = 47.00 ft 39.99' 3.296' 15.0' 8.0'

Actual radius, R = 47.00 ft 500 yr Event H.W. + 5 ft freeboard

Trunion Location: 15.67 ft, 1/3 Gate ht El. 927.12

Trial Trunion El = 891.18 7

2 yr T.W. EL = 896.82 Top of Gate El.922.5

2 yr Gate ht Ratio = 0.45340426 Slope usually between 0.71 1

0.7H to 0.8 H to 1V 1 or 1.408

h1 = 28.3'

L4 = 26.20 8

EL. 898.82 11



1

h = 53.61'

5 3 1.0'

T.W. El. 2

888.74 22.31' 15.23' 10 H.W. EL. 888.74

4 ICE = 0 ksf

El. 875.5

12.00' 41.37'

TW = 19.23' Hw = 19.23'

HTW = 11.538 k/ft 12 2.0' HHW = 11.538 k/ft

6 El. 873.5

6.41 6.41'

4.0'

gh = 1.200 ksf 8.23' 38.06' El. 869.5 gh = 1.200 ksf

"B"

34.29' 24.0'

3.0' 46.29' 32.00' 3.0'



See Piling Plan for Vert Loads and Horiz Resistance B = 84.29'









Use Min. Uplift? yes assumed "steady state"

Normal Water Level, El. 888.74 ft

Dh normal = 19.2 ft UPLIFT

See Geotechnical seepage Model

UB = 1.200 ksf Normal Uplift, UN = 1.200 ksf UA = 1.200 ksf



1.0' 82.29 1.0' enter "0" if no cut-off



Non-Overflow Dam

L W H g shape V arm Mv

Vertical Loads Section ft ft ft kcf K ft ft-k Gate Information wt = 100 psf

Pier Concrete 1 32 8.00 53.61 0.15 rec 2058.6 77.29 159,108.1 w h Gate Wt

Pier Concrete 2 32 24.00 53.61 0.15 rec 6175.9 61.29 378,510.2 mono Gate ft ft lbs # of Gates

Back of Pier 3 32 38.06 53.61 0.15 tri 4897.4 36.60 179,247.2 mono 1 50 2.0 3 Low Flow

Back of Pier 4 32 17.97 25.31 0.15 tri 1091.6 17.22 18,792.0 2 50 47.0 235000 3

Pier Concrete 5 32 8.23 25.31 0.15 rec 999.3 7.11 7,107.7

Ftg concrete 6 182 84.29 4.00 0.15 rec 9204.3 42.14 387,908.9

Bridge Slab 7 182 15.00 0.83 0.15 rec 341.1 65.79 22,441.4

Bridge Beams 7 364 2.17 1.50 0.15 rec 177.5 65.79 11,676.0 Bms 2@ 18" x 26"

Tainter Gates 8 3.00 50.00 47.00 0.100 rec 705.0 59.18 41,724.5 approx arm, 3 gates @ 100 psf

D.L. Concrete SVc = 25650.6 SMV = 1,206,516.0 CONSTANT FOR ALL LOAD CASES



Water I.S. Low Flow 12 150 78.29 2.00 0.0624 rec 1465.6 42.14 61,765.0





Page 12 of 24

BARR ENGINEERING DATE 2/4/2011 SHEET NO.

PROJECT NAME Flood Control ND East (Red River) - Corps Of Engineers

COMPUTED CHECKED SUBMITTEDPROJECT NUMBER

PKN PKN SUBJECT Control Structure: ND East 35k s35k

2/4/11 Load Cases: 4 Normal Water Levels



T.W on ftg 10 182 3.00 15.23 0.0624 rec 518.9 1.50 778.3

TW behind Tainter Gates 1, 2, 3 150 56.18 13.23 0.0624 rec 6957.4 31.09 216,318.1 above low flow, behind gate…assume rectangular

T.W above Pier 5 32 26.20 0.00 0.0624 rec 0.0 16.10 0.0 above L4

T.W. on Pier Slope 4 32 0.00 0.00 0.0624 tri 0.0 29.20 0.0 on back slope of pier

H.W. in front of Gates 11 150 22.10 13.23 0.0624 rec 2737.3 70.24 192,257.6 above low flow

H.W. on Proj. ftg 11 182 3.00 15.23 0.0624 rec 518.9 82.79 42,958.3

D.L. Water SVw = 12198.0 SMV = 514,077.4



L W Pressure U arm Mu

Uplift Loads ft ft ksf K ft ft-k

UB 182 1.00 1.200 rec -218.4 0.50 -109.2

UN 182 82.29 1.200 rec -17971.1 42.14 -757,379.0

UA 182 1.0' 1.200 rec -218.4 83.79 -18,298.7

SU = -18407.9 SMU = -775,787







Horizontal Loads L H Pressure ICE arm Mu

ft ft ksf Ca K ft ft-k Ice Loading is for Ice Floe on single Pier Only

ICE 8.0 ft 1.00 0.00 1.0000 rec 0.0 18.73 0.0 REVISED PER 2/1/11 MEETING WITH CORPS



L Force H arm Mw

Water Loads ft k/ft K ft ft-k

HTW 182 11.538 tri 2099.83 6.41 13459.92

HHW 182 11.538 tri -2099.83 6.41 -13459.92

SW = 0.00 SMW = 0.0







Overturning Moments SMOT = MU +MW +MICE = -775786.85 kip-ft

Resisting Moments SMR = MV = 1,720,593.3 kip-ft





Sum of Moments SMnet = MR + MOT = 944,806 kip-ft

Sum of Vertical Forces P = Conc + Water + Uplift = 19,441 kips

Sum of Horizontal Forces H = Ice + water = 0 kips





Location of Resultant Xr = SM / P = 48.60 ft from Toe

e = B/2 - Xr = (6.45) ft

B/6 = 14.04809









Page 13 of 24

BARR ENGINEERING DATE 6/24/2008

PROJECT NAME Flood Control ND Diversion Inlet - Corps Of En

COMPUTED CHECKED SUBMITTED PROJECT NUMBER

PKN PKN SUBJECT Stability

6/24/08









MATERIAL AND DESIGN PARAMETERS

SOIL:

1) FILL:

g= 0.120 kcf Unit Wt. of fill

E.F.P., K * g = 0.033 kcf

2) Foundation:

Foundation Soil Type: sand (Enter: Sand, Clay, Rock) control: 1

g= Unit Wt. of foundation soils

0.120 kcf

ff = 35.00 deg Internal friction angle of foundation soil

qn = 17.70 ksf Ultimate Soil Capacity, The qn values are provided to designers in the foundation

recommendation report. The report is based on standard penetration test (SPT) data.

Su = 0.00 ksf For Clay ONLY: undrained shear strength (ksf)

fb= 0.45 Soil Resistance Factor for Bearing, Table 10.5.5.2.2-1

qr = fb qn = #NAME?

Allowable Bearing = 5.90 ksf From Geotech FOR SERVICE LOAD DESIGN



CONCRETE:

Fc'= 4.0 ksi Strength at 28 Days (3Y43) ag = 1.5 in

Fc'= 4.0 ksi Strength at 28 Days (1A43) ag = 1.5 in

Unit Wt. = 0.150 kcf



REINFORCEMENT:

Fy = 60 ksi Yield Strength

Es = 29000 ksi Modulus of Elasticity



Design/Analysis (See "Load Combos" TAB)

For design of piling or footing bearing pressures, as a minimum consider the following load cases:





Load Cases (LRFD) (Load Modifer is for superstructure only, ALWAYS USE 1.0)

S ni gi Qi 0.95

For loads for which a minimum value of Yi is appropriate: ηi = 1 / ( ηD ηR ηI ) < 1.00

Strength Ia ηi*(0.90DC+1.00EV+1.50EH+1.75LS)

Used to check sliding and overturning, Use minimum load factors for vertical loads and

maximum load factors for horizontal loads.



Strength Ib ηi*(1.25DC+1.35EV+1.50EH+1.75LS)

Used to check bearing. Use maximum load factors for both vertical and horizontal loads.

( Includes LS acting both vertically and horizontally)



Extreme IIa ηi*(0.90DC+1.00EV+1.00CT)

Used to check sliding and overturning, Use minimum load factors for vertical loads and

maximum load factors for horizontal loads.





Extreme IIb ηi*(1.25DC+1.35EV+1.00CT)

Used to check bearing. Use maximum load factors for both vertical and horizontal loads.





SERVICE LOAD CASES (same loading ), as LRFD, only LF = 1.0)

Service Ia ηi*(1.00DC+1.00EV+1.00EH+1.00LS)



Service Ib ηi*(1.00DC+1.00EV+1.00EH+1.00LS)

( Includes LS acting both vertically and horizontally)

l ND Diversion Inlet - Corps Of Engineers









esigners in the foundation

rd penetration test (SPT) data.









maximum aggregate size

maximum aggregate size (in)









Service

Fatigue

Extreme

Final Construction

1 1

1 1

1 1

1 1

1 1

(Mn/DOT LRFD Bridge Design Manual Jan 2004)

Design abutments for active pressure using an equivalent fluid

weight of 0.033 kcf. A higher pressure may be required based

on soil conditions.



Neglect passive earth pressure in front of Walls



Use LRFD Table 3.11.6.4-1 for determination of live load surcharge

equivalent soil heights.



For resistance to lateral loads, assume piles can resist 18 kips

per pile (factored horizontal load) in addition to load taken by

battering, unless shown otherwise by analysis.



Design footing thickness such that no shear reinforcement is

required. Performance of the Service I crack control check per

LRFD 5.7.3.4 is not required for abutment footings.



Design Wall for horizontal earth pressure

and live load surcharge loads. For stem and backwall crack

control check, use z =170 kips/in.





MnDOT needs to change criteria

for AASHTO 2006 Criteria

SHEET NO.

BARR ENGINEERING DATE 2/4/2011 SHEET NO.

PROJECT NAME Flood Control ND East (Red River) - Corps Of Engineers

COMPUTED CHECKED SUBMITTED PROJECT NUMBER

PKN PKN SUBJECT Pile Capacity

2/4/11 ND East 35k



PILE FOUNDATION DESIGN



FLOW

L = 182.00 ft

Ftg. Length = 182.00 ft PILE PATTERN GEOMETRY

Distance to Longitudinal Edge Dist Trial

spacing Heel Transverse Spacing Toe, dtoe Spacing Batter Piles per Row (N) (ft) N

Row 1 to Toe 3.00 ft 3.0 ft 7.92 ft 0 "/12" 23 3.88 1 23

3.29 Row "n" Row 1 to Row 2 9.00 ft 12.0 ft 7.92 ft 0 "/12" 23 3.88 2 23

Row 2 to Row 3 9.00 ft 21.0 ft 7.92 ft 0 "/12" 23 3.88 3 23

Row 3 to Row 4 9.00 ft 30.0 ft 7.92 ft 0 "/12" 23 3.88 4 23

Row 5 Row 4 to Row 5 9.00 ft 39.0 ft 7.92 ft 0 "/12" 23 3.88 5 23

9 Row 5 to Row 6 6.00 ft 45.0 ft 7.92 ft 0 "/12" 23 3.88 6 23

Row 4 Row 6 to Row 7 6.00 ft 51.0 ft 5.88 ft 0 "/12" 30 5.8125 7 31

Row 7 to Row 8 6.00 ft 57.0 ft 5.88 ft 0 "/12" 30 5.8125 8 31

9 Row 8 to Row 9 6.00 ft 63.0 ft 5.88 ft 0 "/12" 30 5.8125 9 31

b = 84.289 Row 3 Row 9 to Row 10 6.00 ft 69.0 ft 5.88 ft 0 "/12" 30 5.8125 10 31

Row 10 to Row 11 6.00 ft 75.0 ft 5.88 ft 0 "/12" 30 5.8125 11 31

9 Row 11 to Row 12 6.00 ft 81.0 ft 5.88 ft 0 "/12" 30 5.8125 12 31

Row 2 Row 12 to Row 13 0.00 ft 0.0 ft 0.00 ft 0 "/12" 0 91 0 0

Row 13 to Row 14 0.00 ft 0.0 ft 0.00 ft 0 "/12" 0 91 0 0

9 Row 14 to Row 15 0.00 ft 0.0 ft 0.00 ft 0 "/12" 0 91 0 0

Row 1 Last Row to Heel 3.29 ft

84.29 ft Note: Enter 0 for Longitudinal Spacing SN = 318 324

3 for Rows Not Used)

Toe

`

Ftg EL. 869.51

Row 1 Longitudinal Spacing Pile Properties: Pile Type: HP (C.I.P or HP) Pile Length = 34.7 ft Pile Tip El. 835.8

HP Nominal Depth, h = 14.0 in Pile Cap Embed = 1.00 ft

Wt. per ft, plf 73 Total pile Length = 11,038 LF

Pile Group Properties

N.A. of Pile Group to Toe

XNA = (SN * dtoe) / SN = 48.21 ft Test Pile = 45.0 ft (add 10 ft)

ALLOWABLE LOADS (from Geotechnical)

2

Dist. From N.A. to Pile Row d N I=N*d Service Allowable Pile Loads

1 Dist. To Row 1 45.21 ft 23 47005.6 Case 1 1.1 2 2.1 3 4

2 Dist. To Row 2 36.21 ft 23 30152.7 Usual Unusual Unusual Exteme Unusual Usual

3 Dist. Row 3 27.21 ft 23 17025.8 Axial Comp. 59.8 tons 79.7 tons 79.7 tons 104.0 tons 79.7 tons 31.8 tons

4 Dist. Row 4 18.21 ft 23 7624.8 Tension 37.0 tons 49.3 tons 49.3 tons 64.3 tons 49.3 tons 4.6 tons

5 Dist. Row 5 9.21 ft 23 1949.9 Lateral 30.0 kips/pile 35.0 kips/pile 35.0 kips/pile 35.0 kips/pile 30.0 kips/pile 22.0 kips/pile w/o Group effects

6 Dist. Row 6 3.21 ft 23 236.6

7 Dist. Row 7 -2.79 ft 30 233.9

8 Dist. Row 8 -8.79 ft 30 2319.2

9 Dist. Row 9 -14.79 ft 30 6564.5

10 Dist. Row 10 -20.79 ft 30 12969.8

11 Dist. Row 11 -26.79 ft 30 21535.1

12 Dist. Row 12 -32.79 ft 30 32260.3

0 Row 13 (not used) 0.00 ft 0 0.0

0 Row 14 (not used) 0.00 ft 0 0.0

0 Row 15 (not used) 0.00 ft 0 0.0

318 S I = 179878.3

Summary Pile Reactions

Pile Loads (tons/pile) Max. Horiz Pile

Load Combinations Vertical Group

Load Capacity

Allowable Pile Loads 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 (Tons) (k)

1 59.8 tons 39.6 35.8 31.9 28.0 24.1 21.6 19.0 16.4 13.8 11.3 8.7 6.1 0.0 0.0 0.0 39.6 9,540 OK

1.1 79.7 tons 40.2 36.2 32.2 28.2 24.3 21.6 19.0 16.3 13.7 11.0 8.4 5.7 0.0 0.0 0.0 40.2 11,130 OK

2 79.7 tons 33.8 31.6 29.5 27.3 25.1 23.7 22.3 20.8 19.4 17.9 16.5 15.1 0.0 0.0 0.0 33.8 11,130 OK

2.1 104.0 tons 41.6 37.5 33.4 29.3 25.2 22.5 19.8 17.1 14.4 11.6 8.9 6.2 0.0 0.0 0.0 41.6 11,130 OK

3 79.7 tons 45.4 44.4 43.4 42.4 41.4 40.7 40.0 39.4 38.7 38.0 37.4 36.7 0.0 0.0 0.0 45.4 9,540 OK

4 31.8 tons 29.6 29.8 30.0 30.2 30.4 30.5 30.6 30.8 30.9 31.0 31.1 31.3 0.0 0.0 0.0 31.3 6,996 OK

Max Service : P = 45.4



Using solid mechanics equations adapted for discrete elements, the forces in the pile rows for different load combinations are determined.

The force in each pile row is found using:

Pile Load = P / N + MNA / I

First, the moment about the toe must be translated to get the moment about the neutral axis of the pile group.

e toe = M toe / P Pvert

Then the eccentricity about the neutral axis of the pile group is

e NA= XNA - e toe









Page 19 of 24

BARR ENGINEERING DATE 2/4/2011 SHEET NO.

PROJECT NAME Flood Control ND East (Red River) - Corps Of Engineers

COMPUTED CHECKED SUBMITTED PROJECT NUMBER

PKN PKN SUBJECT Pile Capacity

2/4/11 ND East 35k



The moment about the neutral axis of the pile group becomes 0.0 in

MNA = P * e NA 12 12

For battered pile, the Vertical pile load needs to be transformed to the axial load along the pile axis

Paxial = 1.000 Pvert Paxial



FORCE RESULTANT (see Stability Analysis) XNA = 48.21 ft to Toe

Vertical Horizontal

SM toe e toe = M toe / P e NA= XNA - e toe MNA = P * e NA

Load P Load H

(kip-ft) (ft) (ft) (kip-ft)

CASE Flood Event (kips) (kips)

1 100 12,843 9,505 464,521 36.17 12.04 154594 Usual

1.1 100 12,843 9,587 460,245 35.84 12.37 158871 Unusual

2 500 14,583 4,269 616,621 42.28 5.92 86405 Unusual

2.1 500 13,395 7,398 482,620 36.03 12.18 163123 Extreme

3 0 25,651 336 1,196,599 46.65 1.56 39955 Unusual

4 Normal 19,441 0 944,806 48.60 -0.39 -7615 Usual



SERVICE

Case 1 Allowable Axial 59.8 tons

100

Usual



Vertical Load, P = 12843 kips

Horizontal Load, H = 9505 kips

MNA = 154594 kip-ft 318



Vertical Pile Loading P/N + MNA* d / S I = Pile Loads Axial Pile Load

1 Row 1 40.4 38.9 79.2 kips/pile 39.6 tons/pile 39.6 tons/pile Row 1

2 Row 2 40.4 31.1 71.5 kips/pile 35.8 tons/pile 35.8 tons/pile Row 2

3 Row 3 40.4 23.4 63.8 kips/pile 31.9 tons/pile 31.9 tons/pile Row 3

4 Row 4 40.4 15.6 56.0 kips/pile 28.0 tons/pile 28.0 tons/pile Row 4

5 Row 5 40.4 7.9 48.3 kips/pile 24.1 tons/pile 24.1 tons/pile Row 5

6 Row 6 40.4 2.8 43.1 kips/pile 21.6 tons/pile 21.6 tons/pile Row 6

7 Row 7 40.4 -2.4 38.0 kips/pile 19.0 tons/pile 19.0 tons/pile Row 7

8 Row 8 40.4 -7.6 32.8 kips/pile 16.4 tons/pile 16.4 tons/pile Row 8

9 Row 9 40.4 -12.7 27.7 kips/pile 13.8 tons/pile 13.8 tons/pile Row 9

10 Row 10 40.4 -17.9 22.5 kips/pile 11.3 tons/pile 11.3 tons/pile Row 10

11 Row 11 40.4 -23.0 17.4 kips/pile 8.7 tons/pile 8.7 tons/pile Row 11

12 Row 12 40.4 -28.2 12.2 kips/pile 6.1 tons/pile 6.1 tons/pile Row 12

13 Row 13 0.0 0.0 0.0 kips/pile 0.0 tons/pile 0.0 tons/pile Row 13

14 Row 14 0.0 0.0 0.0 kips/pile 0.0 tons/pile 0.0 tons/pile Row 14

15 Row 15 0.0 0.0 0.0 kips/pile 0.0 tons/pile 0.0 tons/pile Row 15

max: 39.6 tons/pile max: 39.6 tons/pile

Assumed lateral Capacity: 30.0 kips/pile

Resistance due Resitance due Group

Horizontal Pile Capacity Batter "/ft N to Batter, kips to Bending, kips Efficiency Lateral Resitance

1 Row 1 0 23 0.0 690 1.000 690 kips

2 Row 2 0 23 0.0 690 1.000 690 kips

3 Row 3 0 23 0.0 690 1.000 690 kips

4 Row 4 0 23 0.0 690 1.000 690 kips

5 Row 5 0 23 0.0 690 1.000 690 kips

6 Row 6 0 23 0.0 690 1.000 690 kips

7 Row 7 0 30 0.0 900 1.000 900 kips

8 Row 8 0 30 0.0 900 1.000 900 kips

9 Row 9 0 30 0.0 900 1.000 900 kips

10 Row 10 0 30 0.0 900 1.000 900 kips

11 Row 11 0 30 0.0 900 1.000 900 kips

12 Row 12 0 30 0.0 900 1.000 900 kips

13 Row 13 0 0 0.0 0 1.000 0 kips

14 Row 14 0 0 0.0 0 1.000 0 kips

15 Row 15 0 0 0.0 0 1.000 0 kips

318 9540 9540 kips OK



Case 1.1 Allowable Axial 79.7 tons Allow. Tension 104.0 tons

100

Unusual



Vertical Load, P = 12843 kips

Horizontal Load, H = 9587 kips

MNA = 158871 kip-ft



Vertical Pile Loading P/N + MNA* d / S I = Pile Loads Axial Pile Load

1 Row 1 40.4 39.9 80.3 kips/pile 40.2 tons/pile 40.2 tons/pile Row 1









Page 20 of 24

BARR ENGINEERING DATE 2/4/2011 SHEET NO.

PROJECT NAME Flood Control ND East (Red River) - Corps Of Engineers

COMPUTED CHECKED SUBMITTED PROJECT NUMBER

PKN PKN SUBJECT Pile Capacity

2/4/11 ND East 35k



2 Row 2 40.4 32.0 72.4 kips/pile 36.2 tons/pile 36.2 tons/pile Row 2

3 Row 3 40.4 24.0 64.4 kips/pile 32.2 tons/pile 32.2 tons/pile Row 3

4 Row 4 40.4 16.1 56.5 kips/pile 28.2 tons/pile 28.2 tons/pile Row 4

5 Row 5 40.4 8.1 48.5 kips/pile 24.3 tons/pile 24.3 tons/pile Row 5

6 Row 6 40.4 2.8 43.2 kips/pile 21.6 tons/pile 21.6 tons/pile Row 6

7 Row 7 40.4 -2.5 37.9 kips/pile 19.0 tons/pile 19.0 tons/pile Row 7

8 Row 8 40.4 -7.8 32.6 kips/pile 16.3 tons/pile 16.3 tons/pile Row 8

9 Row 9 40.4 -13.1 27.3 kips/pile 13.7 tons/pile 13.7 tons/pile Row 9

10 Row 10 40.4 -18.4 22.0 kips/pile 11.0 tons/pile 11.0 tons/pile Row 10

11 Row 11 40.4 -23.7 16.7 kips/pile 8.4 tons/pile 8.4 tons/pile Row 11

12 Row 12 40.4 -29.0 11.4 kips/pile 5.7 tons/pile 5.7 tons/pile Row 12

13 Row 13 0.0 0.0 0.0 kips/pile 0.0 tons/pile 0.0 tons/pile Row 13

14 Row 14 0.0 0.0 0.0 kips/pile 0.0 tons/pile 0.0 tons/pile Row 14

15 Row 15 0.0 0.0 0.0 kips/pile 0.0 tons/pile 0.0 tons/pile Row 15

max: 40.2 tons/pile max: 40.2 tons/pile

Assumed lateral Capacity: 35.0 kips/pile

Resistance due Resitance due Group

Horizontal Pile Capacity Batter "/ft N to Batter, kips to Bending, kips Efficiency Lateral Resitance

1 Row 1 0 23 0.0 805 1.000 805 kips

2 Row 2 0 23 0.0 805 1.000 805 kips

3 Row 3 0 23 0.0 805 1.000 805 kips

4 Row 4 0 23 0.0 805 1.000 805 kips

5 Row 5 0 23 0.0 805 1.000 805 kips

6 Row 6 0 23 0.0 805 1.000 805 kips

7 Row 7 0 30 0.0 1050 1.000 1050 kips

8 Row 8 0 30 0.0 1050 1.000 1050 kips

9 Row 9 0 30 0.0 1050 1.000 1050 kips

10 Row 10 0 30 0.0 1050 1.000 1050 kips

11 Row 11 0 30 0.0 1050 1.000 1050 kips

12 Row 12 0 30 0.0 1050 1.000 1050 kips

13 Row 13 0 0 0.0 0 1.000 0 kips

14 Row 14 0 0 0.0 0 1.000 0 kips

15 Row 15 0 0 0.0 0 1.000 0 kips

318 11130 11130 kips OK



Case 2

500

Unusual



Vertical Load, P = 14583 kips

Horizontal Load, H = 4269 kips

MNA = 86405 kip-ft



Vertical Pile Loading P/N + MNA* d / S I = Pile Loads Axial Pile Load

1 Row 1 45.9 21.7 67.6 kips/pile 33.8 tons/pile 33.8 tons/pile

2 Row 2 45.9 17.4 63.3 kips/pile 31.6 tons/pile 31.6 tons/pile

3 Row 3 45.9 13.1 58.9 kips/pile 29.5 tons/pile 29.5 tons/pile

4 Row 4 45.9 8.7 54.6 kips/pile 27.3 tons/pile 27.3 tons/pile

5 Row 5 45.9 4.4 50.3 kips/pile 25.1 tons/pile 25.1 tons/pile

6 Row 6 45.9 1.5 47.4 kips/pile 23.7 tons/pile 23.7 tons/pile

7 Row 7 45.9 -1.3 44.5 kips/pile 22.3 tons/pile 22.3 tons/pile

8 Row 8 45.9 -4.2 41.6 kips/pile 20.8 tons/pile 20.8 tons/pile

9 Row 9 45.9 -7.1 38.8 kips/pile 19.4 tons/pile 19.4 tons/pile

10 Row 10 45.9 -10.0 35.9 kips/pile 17.9 tons/pile 17.9 tons/pile

11 Row 11 45.9 -12.9 33.0 kips/pile 16.5 tons/pile 16.5 tons/pile

12 Row 12 45.9 -15.8 30.1 kips/pile 15.1 tons/pile 15.1 tons/pile

13 Row 13 0.0 0.0 0.0 kips/pile 0.0 tons/pile 0.0 tons/pile

14 Row 14 0.0 0.0 0.0 kips/pile 0.0 tons/pile 0.0 tons/pile

15 Row 15 0.0 0.0 0.0 kips/pile 0.0 tons/pile 0.0 tons/pile

max: 33.8 tons/pile max: 33.8 tons/pile

Assumed lateral Capacity: 35.0 kips/pile

Resistance due Resitance due Group

Horizontal Pile Capacity Batter "/ft N to Batter, kips to Bending, kips Efficiency Lateral Resitance

1 Row 1 0 23 0.0 805 1.000 805 kips

2 Row 2 0 23 0.0 805 1.000 805 kips

3 Row 3 0 23 0.0 805 1.000 805 kips

4 Row 4 0 23 0.0 805 1.000 805 kips

5 Row 5 0 23 0.0 805 1.000 805 kips

6 Row 6 0 23 0.0 805 1.000 805 kips

7 Row 7 0 30 0.0 1050 1.000 1050 kips

8 Row 8 0 30 0.0 1050 1.000 1050 kips

9 Row 9 0 30 0.0 1050 1.000 1050 kips

10 Row 10 0 30 0.0 1050 1.000 1050 kips

11 Row 11 0 30 0.0 1050 1.000 1050 kips









Page 21 of 24

BARR ENGINEERING DATE 2/4/2011 SHEET NO.

PROJECT NAME Flood Control ND East (Red River) - Corps Of Engineers

COMPUTED CHECKED SUBMITTED PROJECT NUMBER

PKN PKN SUBJECT Pile Capacity

2/4/11 ND East 35k



12 Row 12 0 30 0.0 1050 1.000 1050 kips

13 Row 13 0 0 0.0 0 1.000 0 kips

14 Row 14 0 0 0.0 0 1.000 0 kips

15 Row 15 0 0 0.0 0 1.000 0 kips

318 11130 11130 kips OK



Case 2.1

500

Extreme



Vertical Load, P = 13395 kips

Horizontal Load, H = 7398 kips

MNA = 163123 kip-ft



Vertical Pile Loading P/N + MNA* d / S I = Pile Loads Axial Pile Load

1 Row 1 42.1 41.0 83.1 kips/pile 41.6 tons/pile 41.6 tons/pile

2 Row 2 42.1 32.8 75.0 kips/pile 37.5 tons/pile 37.5 tons/pile

3 Row 3 42.1 24.7 66.8 kips/pile 33.4 tons/pile 33.4 tons/pile

4 Row 4 42.1 16.5 58.6 kips/pile 29.3 tons/pile 29.3 tons/pile

5 Row 5 42.1 8.3 50.5 kips/pile 25.2 tons/pile 25.2 tons/pile

6 Row 6 42.1 2.9 45.0 kips/pile 22.5 tons/pile 22.5 tons/pile

7 Row 7 42.1 -2.5 39.6 kips/pile 19.8 tons/pile 19.8 tons/pile

8 Row 8 42.1 -8.0 34.1 kips/pile 17.1 tons/pile 17.1 tons/pile

9 Row 9 42.1 -13.4 28.7 kips/pile 14.4 tons/pile 14.4 tons/pile

10 Row 10 42.1 -18.9 23.3 kips/pile 11.6 tons/pile 11.6 tons/pile

11 Row 11 42.1 -24.3 17.8 kips/pile 8.9 tons/pile 8.9 tons/pile

12 Row 12 42.1 -29.7 12.4 kips/pile 6.2 tons/pile 6.2 tons/pile

13 Row 13 0.0 0.0 0.0 kips/pile 0.0 tons/pile 0.0 tons/pile

14 Row 14 0.0 0.0 0.0 kips/pile 0.0 tons/pile 0.0 tons/pile

15 Row 15 0.0 0.0 0.0 kips/pile 0.0 tons/pile 0.0 tons/pile

max: 41.6 tons/pile max: 41.6 tons/pile

Assumed lateral Capacity: 35.0 kips/pile

Resistance due Resitance due Group

Horizontal Pile Capacity Batter "/ft N to Batter, kips to Bending, kips Efficiency Lateral Resitance

1 Row 1 0 23 0.0 805 1.000 805 kips

2 Row 2 0 23 0.0 805 1.000 805 kips

3 Row 3 0 23 0.0 805 1.000 805 kips

4 Row 4 0 23 0.0 805 1.000 805 kips

5 Row 5 0 23 0.0 805 1.000 805 kips

6 Row 6 0 23 0.0 805 1.000 805 kips

7 Row 7 0 30 0.0 1050 1.000 1050 kips

8 Row 8 0 30 0.0 1050 1.000 1050 kips

9 Row 9 0 30 0.0 1050 1.000 1050 kips

10 Row 10 0 30 0.0 1050 1.000 1050 kips

11 Row 11 0 30 0.0 1050 1.000 1050 kips

12 Row 12 0 30 0.0 1050 1.000 1050 kips

13 Row 13 0 0 0.0 0 1.000 0 kips

14 Row 14 0 0 0.0 0 1.000 0 kips

15 Row 15 0 0 0.0 0 1.000 0 kips

318 11130 11130 kips OK



Case 3

0

Unusual



Vertical Load, P = 25651 kips

Horizontal Load, H = 336 kips

MNA = 39955 kip-ft



Vertical Pile Loading P/N + MNA* d / S I = Pile Loads Axial Pile Load

1 Row 1 80.7 10.0 90.7 kips/pile 45.4 tons/pile 45.4 tons/pile

2 Row 2 80.7 8.0 88.7 kips/pile 44.4 tons/pile 44.4 tons/pile

3 Row 3 80.7 6.0 86.7 kips/pile 43.4 tons/pile 43.4 tons/pile

4 Row 4 80.7 4.0 84.7 kips/pile 42.4 tons/pile 42.4 tons/pile

5 Row 5 80.7 2.0 82.7 kips/pile 41.4 tons/pile 41.4 tons/pile

6 Row 6 80.7 0.7 81.4 kips/pile 40.7 tons/pile 40.7 tons/pile

7 Row 7 80.7 -0.6 80.0 kips/pile 40.0 tons/pile 40.0 tons/pile

8 Row 8 80.7 -2.0 78.7 kips/pile 39.4 tons/pile 39.4 tons/pile

9 Row 9 80.7 -3.3 77.4 kips/pile 38.7 tons/pile 38.7 tons/pile

10 Row 10 80.7 -4.6 76.0 kips/pile 38.0 tons/pile 38.0 tons/pile

11 Row 11 80.7 -6.0 74.7 kips/pile 37.4 tons/pile 37.4 tons/pile

12 Row 12 80.7 -7.3 73.4 kips/pile 36.7 tons/pile 36.7 tons/pile

13 Row 13 0.0 0.0 0.0 kips/pile 0.0 tons/pile 0.0 tons/pile

14 Row 14 0.0 0.0 0.0 kips/pile 0.0 tons/pile 0.0 tons/pile









Page 22 of 24

BARR ENGINEERING DATE 2/4/2011 SHEET NO.

PROJECT NAME Flood Control ND East (Red River) - Corps Of Engineers

COMPUTED CHECKED SUBMITTED PROJECT NUMBER

PKN PKN SUBJECT Pile Capacity

2/4/11 ND East 35k



15 Row 15 0.0 0.0 0.0 kips/pile 0.0 tons/pile 0.0 tons/pile

max: 45.4 tons/pile max: 45.4 tons/pile

Assumed lateral Capacity: 30.0 kips/pile

Resistance due Resitance due Group

Horizontal Pile Capacity Batter "/ft N to Batter, kips to Bending, kips Efficiency Lateral Resitance

1 Row 1 0 23 0.0 690 1.000 690 kips

2 Row 2 0 23 0.0 690 1.000 690 kips

3 Row 3 0 23 0.0 690 1.000 690 kips

4 Row 4 0 23 0.0 690 1.000 690 kips

5 Row 5 0 23 0.0 690 1.000 690 kips

6 Row 6 0 23 0.0 690 1.000 690 kips

7 Row 7 0 30 0.0 900 1.000 900 kips

8 Row 8 0 30 0.0 900 1.000 900 kips

9 Row 9 0 30 0.0 900 1.000 900 kips

10 Row 10 0 30 0.0 900 1.000 900 kips

11 Row 11 0 30 0.0 900 1.000 900 kips

12 Row 12 0 30 0.0 900 1.000 900 kips

13 Row 13 0 0 0.0 0 1.000 0 kips

14 Row 14 0 0 0.0 0 1.000 0 kips

15 Row 15 0 0 0.0 0 1.000 0 kips

318 9540 9540 kips OK



Case 4

Normal

Usual



Vertical Load, P = 19441 kips

Horizontal Load, H = 0 kips

MNA = -7615 kip-ft



Vertical Pile Loading P/N + MNA* d / S I = Pile Loads Axial Pile Load

1 Row 1 61.1 -1.9 59.2 kips/pile 29.6 tons/pile 29.6 tons/pile

2 Row 2 61.1 -1.5 59.6 kips/pile 29.8 tons/pile 29.8 tons/pile

3 Row 3 61.1 -1.2 60.0 kips/pile 30.0 tons/pile 30.0 tons/pile

4 Row 4 61.1 -0.8 60.4 kips/pile 30.2 tons/pile 30.2 tons/pile

5 Row 5 61.1 -0.4 60.7 kips/pile 30.4 tons/pile 30.4 tons/pile

6 Row 6 61.1 -0.1 61.0 kips/pile 30.5 tons/pile 30.5 tons/pile

7 Row 7 61.1 0.1 61.3 kips/pile 30.6 tons/pile 30.6 tons/pile

8 Row 8 61.1 0.4 61.5 kips/pile 30.8 tons/pile 30.8 tons/pile

9 Row 9 61.1 0.6 61.8 kips/pile 30.9 tons/pile 30.9 tons/pile

10 Row 10 61.1 0.9 62.0 kips/pile 31.0 tons/pile 31.0 tons/pile

11 Row 11 61.1 1.1 62.3 kips/pile 31.1 tons/pile 31.1 tons/pile

12 Row 12 61.1 1.4 62.5 kips/pile 31.3 tons/pile 31.3 tons/pile

13 Row 13 0.0 0.0 0.0 kips/pile 0.0 tons/pile 0.0 tons/pile

14 Row 14 0.0 0.0 0.0 kips/pile 0.0 tons/pile 0.0 tons/pile

15 Row 15 0.0 0.0 0.0 kips/pile 0.0 tons/pile 0.0 tons/pile

max: 31.3 tons/pile max: 31.3 tons/pile

Assumed lateral Capacity: 22.0 kips/pile

Resistance due Resitance due Group

Horizontal Pile Capacity Batter "/ft N to Batter, kips to Bending, kips Efficiency Lateral Resitance

1 Row 1 0 23 0.0 506 1.000 506 kips

2 Row 2 0 23 0.0 506 1.000 506 kips

3 Row 3 0 23 0.0 506 1.000 506 kips

4 Row 4 0 23 0.0 506 1.000 506 kips

5 Row 5 0 23 0.0 506 1.000 506 kips

6 Row 6 0 23 0.0 506 1.000 506 kips

7 Row 7 0 30 0.0 660 1.000 660 kips

8 Row 8 0 30 0.0 660 1.000 660 kips

9 Row 9 0 30 0.0 660 1.000 660 kips

10 Row 10 0 30 0.0 660 1.000 660 kips

11 Row 11 0 30 0.0 660 1.000 660 kips

12 Row 12 0 30 0.0 660 1.000 660 kips

13 Row 13 0 0 0.0 0 1.000 0 kips

14 Row 14 0 0 0.0 0 1.000 0 kips

15 Row 15 0 0 0.0 0 1.000 0 kips

318 6996 6996 kips OK









Page 23 of 24

BARR ENGINEERING DATE 2/4/2011 SHEET NO.

PROJECT NAME RRN Control Structure

COMPUTED CHECKED SUBMITTED PROJECT NUMBER

PKN PKN SUBJECT ACOE Stability Requirements

2/4/11



EM 1110-2-2100 Stability Analysis of Concrete Structures 12/1/2005 * Pile-founded structures are not included

EM 1110-2-2200 Gravity Dam Design 6/30/1995

EM 1110-2-2104 Strength Design for Reinforced-Concrete Hydraulic Structures 6/30/1992 8/20/2003

EM 1110-2-2906 Design of Pile Foundations 1/15/1991



Load Condition Pobabilities See 6/21/10, response from COE to critical path check list item:

Case: 1 2 3 Follow-up on structural design criteria

Usual Unusual Unusual

Return Period, yrs: 100 500 + free Bd

allowable stress increase: 1 33% 33%

Lateral pile deflection, in.: 0.67 0.875 0.67

Ice thickness, ft: 2 2 0 Ice



Piles Minimum Factor of Saftey, Ultimate axial capacity EM 1110-2-2906 Ratios

Usual Unusual Extreme Usual/ Unusual Usual/ Extreme

compression 2.00 1.50 1.15 verified by load tests 1.333 1.739

tension 2.00 1.50 1.15 1.333 1.739

compression 2.50 1.90 1.40 verified by pile driver analyzer 1.316 1.786

tension 3.00 2.25 1.70 1.333 1.765

compression 3.00 2.25 1.70 not verified by load test 1.333 1.765

tension 3.00 2.25 1.70 1.333 1.765



Usual Unusual Extreme

EM 1110-2-2906, P. 4-9 1.33 1.75 Increase per allowable stress increase

Vertical displacemet 0.25 in 0.33 in 0.44 in

Horizonatl Displacement 0.50 in 0.67 in 0.875 in



Pile Capacity: HP14x73

Usual Unusual Unusual Extreme Unusual Usual



Case 1 1.1 2 2.1 3 4 Note

Pile Tip El. 835.8 835.8 835.8 835.8 835.8 835.8 Case 1, 2, 3: Flood & Construction loading using Undrained Analysis

Ultimate Axial capacity: 239.1 k 239.1 k 239.1 k 239.1 k 239.1 k 127.2 k Case 4: Long-term loading using Drained Analysis

Ultimate Uplift capacity: 148.0 k 148.0 k 148.0 k 148.0 k 148.0 k 18.3 k Cases 1.1 & 2.1 include ice, use next higher load classification

Horizonatl Displacement: 0.67 in 0.875 in 0.875 in 1.000 in 0.67 in 0.50 in Per Corp meeting 2/1/11

Allow. Lateral Capacity: 30 k 35 k 35 k 35 k 30 k 22 k FOR PHASE 4 : Use GROUP FOR Lateral capacity

FS: 2.00 1.50 1.50 1.15 1.50 2.00 Per Corp meeting 2/1/11

Allow. Axial Compression: 119.6 k 159.4 k 159.4 k 207.9 k 159.4 k 63.6 k

Allow. Axial Tension: 74.0 k 98.7 k 98.7 k 128.7 k 98.7 k 9.2 k



Pile P-Multipliers, Pm for multiple Row Shading (ave from Hannigan….2005) See Table 10.7.2.4-1 AASHTO P. 10-88

1 2 3 4

Pile Spacing Row 1 Row 2 Row 3 Row n B= 1.1667 Load

3 B 0.7 0.5 0.35 0.35 Row 1 Row 2 Row 3 Row n

5 B 1 0.85 0.7 0.7 Pile Spacing 9.00 ft 9.00 ft 9.00 ft 6.00 ft parallel to Load

h Long 1.000 1.000 1.000 1.000 parallel Ratio s/B 7.714 7.714 7.714 5.143

h Trans 1.000 1.000 1.000 1.000 perp 7.92 ft 7.92 ft 7.92 ft 8.88 ft perp to Load

h Total 1.000 1.000 1.000 1.000 Total Lateral reduction Ratio L/B 6.789 6.789 6.789 7.607

FOR PHASE 4 : NO Pm applied for Lateral capacity



Hydraulic Data - RRN Mainstream - Optimized w/Control Structures

6/9/2010

Structure: ND East Red River 35k

Event HeadwaterTailwater

Year ft ft Case

1/24/2011 2 896.85 896.82

5 906.37 902.2

1/18/2011 10 914.77 903.05

20 910.87 903.23

50 920.02 902.11

1/18/2011 100 922.01 902.41 1

200 916.79 908.37

** 300 918.567 910.383

1/18/2011 500 922.12 914.41 2









** **





**300 yr event is linearly interploated between 200 & 500 yr event









Page 24 of 24



Related docs
Other docs by xiaopangnv
Synchronicity Performance Group
Views: 4  |  Downloads: 0
Tabelle1 - VfL Bensheim Basketball
Views: 2  |  Downloads: 0
seguridad en un sistema informatico
Views: 0  |  Downloads: 0
2010-216 LUZ amd-Corrected-Not Used
Views: 0  |  Downloads: 0
9768118_9768160
Views: 0  |  Downloads: 0
Applied and Net Force
Views: 0  |  Downloads: 0
MONTAG
Views: 0  |  Downloads: 0
National Taiwan University_Macbeth
Views: 0  |  Downloads: 0
docjeotbAONe1
Views: 0  |  Downloads: 0
TEMPLATE--EAUpdate--Sept2007
Views: 0  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!