Embed
Email

10341_NTP__NTP_and_Acceleration_interplay

Document Sample

Shared by: cuiliqing
Categories
Tags
Stats
views:
0
posted:
11/7/2011
language:
English
pages:
2
July 27, 2009



Ontario Power Authority

Feed-in Tariff Program

Suite 1600

120 Adelaide Street West

Toronto, ON M5H 1T1



Dear Folks,

Thank you for your extensive work on the FIT rules and regulations. We have a few questions/comments

to submit related to the interplay of NTP and Acceleration Days and NTP in general.



1. NTP: June 8 Draft Contract:

a. Section 2.4 (f) :

If the Contract Facility is not an Automatic NTP Facility, the OPA shall be required to

either issue Notice to Proceed, deliver an NTP Deferral Notice to the Supplier, or

terminate this Agreement in accordance with Section 2.4(a), by the later of (A) the NTP

Response Date and (B) 10 Business Days following the OPA’s receipt of the Supplier’s

completed NTP Request.

i. Does this mean the OPA must either terminate the Agreement by the later of the

NTP Response Date or 10 Business Days of the NTP request or does it mean that the

OPA must provide any one of the three options within these date parameters?

ii. Should the above statement be an ‘or’ or an ‘and’ statement?

b. Exhibit A: The NTP Response Date is the date that is 15 months (455 days) following the

Contract Date.

i. Please verify that our understanding of the implications of NTP Response and

Milestone Acceleration Days is correct given the following example:



Example A: Shovel ready projects:

 Nov 1, 2009- Applicant applies for FIT and elects 455 Milestone Acceleration

days

 Jan 1, 2010 – Applicant receives Contract

 Jan 1, 2010 – Applicant applies for NTP

 Apr 1, 2011 - OPA’s NTP Response (15 months)

 Oct 1, 2011 – new Milestone COD

The project has Six months to purchase turbines and achieve Milestone

Commercial Operation date.



Example B: Non shovel ready projects

 Nov 1, 2009- Applicant applies for FIT and elects 0 Milestone Acceleration

days

 Jan 1, 2010 – Applicant receives Contract

 Jan 1, 2011 – Applicant completes CIA, REAs, permits, etc. and applies for NTP

 Apr 1, 2012 - OPA’s NTP Response (15 months)

 Jan 1, 2013 – 3 year Milestone COD

The project has 9 months to purchase turbines and achieve Milestone

Commercial Operation date.

ii. Historically, the wait for turbines has been as much as 2 years. Even though the

current wait time if far less due to the economic downturn, there is no

guarantee that turbines can be attained in a short period of time. A nine month

period to obtain turbines , as seen in Example B above, adds significant risk and

challenge to a project for which the developer has no control. Therefore, if the

OPA takes 15 months to respond to a NTP Request, it will force developers to

stretch their project timeline while they are essentially ‘on hold’ with the risk of

missing their Milestone Commercial Operation date. Note that a large

developer may be able to place a deposit on turbines earlier and move them to

other projects if NTP is not attained. Smaller companies would lose their

deposits. As this is by far the largest cost in developing wind projects, this risk is

not taken lightly.

iii. Acceleration Days: It is clear that, given the draft proposal to introduce

Acceleration Days to determine date stamp priority, that developers will simply

use these days to “play” the system without necessarily being in a greater

shovel ready position than another developer. For instance, on two competing

10 MW projects with equal shovel readiness, one developer may commit to 50

acceleration days simply to receive a better time stamp –the business

calculation will certainly be that, in an area with limited capacity, the liquidated

damages and term reduction will be a necessary “cost of doing business” to

secure grid capacity in the province of Ontario. In other words, developers will

add Liquidated Damages to their business cost model. This gamesmanship will

not produce the stable development atmosphere that the OPA, serious

developers and investors are looking for. We suggest that the time stamps from

CIA’s obtained under the RESOP program be used to allocate capacity during the

Program Launch. Developers that reach COD prior to the 3 years could receive a

bonus such as an extended contract term.





Sincerely,

Khlaire Parré and Colleagues

wpd Canada Corporation

405 Britannia Road East, Suite 214

Mississauga, Ontario

L4Z 3E6



Other docs by cuiliqing
11.1 Exploring Area and Perimeter
Views: 0  |  Downloads: 0
Volusia County
Views: 2  |  Downloads: 0
choosing_topics_and_y10
Views: 0  |  Downloads: 0
CLE Credit - rscrpubs.com
Views: 2  |  Downloads: 0
Meeting Minutes September 8 Final
Views: 0  |  Downloads: 0
nov2411
Views: 3  |  Downloads: 0
EKG Spreadsheet - Geocities.ws
Views: 0  |  Downloads: 0
Gift from Christ to the Church
Views: 0  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!