Embed
Email

GOP_Mapping_2009-02

Document Sample

Shared by: cuiliqing
Categories
Tags
Stats
views:
0
posted:
10/31/2011
language:
English
pages:
24
1

2



3

4



5

6



7

8





KEY

GENERATOR OPERATOR MAPPING MATRIX

NOTES

Requirements of standards could change depending on the NERC approval processes and

modified versions of the same standards

Requirements of standards could be added or deleted depending on version changes

Current viewpoints could change depending on factors like NERC and NPCC requirements

and inputs from other regulatory bodies

This is not a final list and is subject to change

The IESO may modify certification requirements as deemed appropriate, for reliability,

reporting, certification, or auditing concerns

The IESO will work with all market participants to guide them through the process.

CIP standards (CIP-002 through CIP-009) are not covered in these requirements. The IESO

will be working with each affected market participant in this regard.

The implementation dates for these standards are subject to change









Requirement applies and is appropriate to actively monitor market participants





Requirement applies but the IESO is reviewing the need to actively monitor market participants. Address





Requirement applies but managed through other processes and no need to actively monitor market partic

participants. Addressed by the IESO or IESO processes currently.





monitor market participants

Generator Operator









Requirement





IRCP Form

Number





Number

Standard

Text of Requirement Comments

Number





CIP-001-1 R1. 1610 Each Reliability Coordinator, Balancing Authority, Transmission Operator, Generator Dependent on the critical assets owned by

Operator, and Load Serving Entity shall have procedures for the recognition of and for the market participant and pursuant to the

making their operating personnel aware of sabotage events on its facilities and multi site market rules and Market Manual 7.1 . This

sabotage affecting larger portions of the Interconnection. will be determined by the IESO in

consultation with the MP.

CIP-001-1 R2. 1610 Each Reliability Coordinator, Balancing Authority, Transmission Operator, Generator Dependent on the critical assets owned by

Operator, and Load Serving Entity shall have procedures for the communication of the market participant and pursuant to the

information concerning sabotage events to appropriate parties in the Interconnection. market rules and Market Manual 7.1 . This

will be determined by the IESO in

consultation with the MP.

CIP-001-1 R3. 1610 Each Reliability Coordinator, Balancing Authority, Transmission Operator, Generator Dependent on the critical assets owned by

Operator, and Load Serving Entity shall provide its operating personnel with sabotage the market participant and pursuant to the

response guidelines, including personnel to contact, for reporting disturbances due to market rules and Market Manual 7.1 . This

sabotage events. will be determined by the IESO in

consultation with the MP.

CIP-001-1 R4. 1610 Each Reliability Coordinator, Balancing Authority, Transmission Operator, Generator Dependent on the critical assets owned by

Operator, and Load Serving Entity shall establish communications contacts, as the market participant and pursuant to the

applicable, with local Federal Bureau of Investigation (FBI) or Royal Canadian Mounted market rules and Market Manual 7.1 . This

Police (RCMP) officials and develop reporting procedures as appropriate to their will be determined by the IESO in

circumstances. consultation with the MP.

EOP-001-0 R1 1608 Each market participant shall ensure that its emergency preparedness plan is on file with Obligations are explicitly in accordance

the IESO (Ch. 5, S. 11.2.4 of the market rules ) and that it: with Ch., S.11. of the market rules as

establish in consultation with the EPTF and

fulfill the requirements of EOP-001

EOP-001-0 R1.1. 1608 Describes such planning, testing, information, communication and other elements "

designated by the IESO ;

EOP-001-0 R1.2. 1608 Complies with the OEEP emergency planning criteria "



Jan, 2007 4of-24

Generator Operator









Requirement





IRCP Form

Number





Number

Standard

Text of Requirement Comments

Number





EOP-001-0 R2 1608 Each market participant shall review its emergency preparedness plan at least annually, or "

as required, and shall, following such review, submit to the IESO :

EOP-001-0 R2.1. 1608 Certification confirming that the review has not required any change to be made to its "

emergency preparedness plan ; or

EOP-001-0 R2.2. 1608 A revised version of its emergency preparedness plan , amended as may be required by "

the results of the review, together with a statement identifying such amendments, as

the case may be.

EOP-001-0 R3. 1608 Each market participant shall ensure that any revised emergency preparedness plan "

prepared and submitted pursuant to Requirement R2 complies with requirement R1.

EOP-005-1 R1. 1609 Each restoration participant shall ensure that its restoration participant attachment is on Obligations are explicitly in accordance

file with the IESO (Ch. 5, S. 11.3.6 of the market rules and Market Manual 7.8 - OPSRP). with Ch., S.11. of the market rules as

establish in consultation with the OPSRP-

WG and fulfill the requirements of EOP-005



EOP-005-1 R1.1. 1609 Each restoration participant shall review its restoration participant attachment at least "

annually, or more often if required, and shall submit a revised version of its restoration

participant attachment , amended as may be required by the results of the review.





EOP-005-1 R2. 1609 Each restoration participant shall ensure that records are maintained and available, "

and its restoration participant attachment (Ch. 5, S. 11.3.7 of the market rules and Market

Manual 7.8 - OPSRP):

EOP-005-1 R2.1. 1609 Identifies any constraints preventing or limiting its capability to execute its obligations "

assigned in the Ontario power system restoration plan .

EOP-005-1 R2.2. 1609 Identifies permanently installed emergency power generators including the facilities at "

which they are installed, and what they are intended to supply.

EOP-005-1 R3. 1609 Each restoration participant shall ensure its restoration participant attachment includes "

(Ch. 5, S. 11.3.7 of the market rules and Market Manual 7.8 – OPSRP):

Jan, 2007 5of-24

Generator Operator









Requirement





IRCP Form

Number





Number

Standard

Text of Requirement Comments

Number





EOP-005-1 R3.1. 1609 A declaration that on-shift operators have been trained on system restoration activities "

has an operator training program in place and operator training records are maintained

and available.

EOP-005-1 R3.2. 1609 For those restoration participants identified as owners of key facilities, a program for For Key Facility Owners only

testing the restoration participant’s critical components as designated in the Ontario power

system restoration plan ( Market Manual 7.8, - Ontario Power System Restoration Plan

Section 4.12), shall be maintained and available along with a record of the test results.





EOP-009-0 R2. 1532 The Generator Owner or Generator Operator shall provide documentation of the test For Black-start generator only

results of the start-up and operation of each blackstart generating unit to the Regional

Reliability Organizations and upon request to NERC.

PRC-001-1 R1. 1637 Each Transmission Operator, Balancing Authority, and Generator Operator shall be Each facility owner is required to be

familiar with the purpose and limitations of protection system schemes applied in its familiar with its facility protection systems

area. and the implications when such protection

systems fails for notifying the IESO.

PRC-001-1 R2. 1637 Each Generator Operator and Transmission Operator shall notify reliability entities of M.R and market manual 7.1 Section 3 and

relay or equipment failures as follows: market manual 7.3 - Outage Management

re: reporting of equipment failures or

degradation.

PRC-001-1 R2.1. 1637 If a protective relay or equipment failure reduces system reliability, the Generator ditto

Operator shall notify its Transmission Operator and Host Balancing Authority. The

Generator Operator shall take corrective action as soon as possible.

TOP-006-1 R1.1. 1645 Each Generator Operator shall inform its Host Balancing Authority and the Market rules obligates generators to notify

Transmission Operator of all generation resources available for use. the IESO when units are de-rated. Need to

monitor to ensure generators notify the

IESO of resource availability.







Jan, 2007 6of-24

Generator Operator









Requirement





IRCP Form

Number





Number

Standard

Text of Requirement Comments

Number





VAR-002-1.1a R1. 1571 The Generator Operator shall operate each generator connected to the interconnected

transmission system in the automatic voltage control mode (automatic voltage regulator

in service and controlling voltage) unless the Generator Operator has notified the

Transmission Operator.

VAR-002-1.1a R2. 1571 Unless exempted by the Transmission Operator, each Generator Operator shall maintain

the generator voltage or Reactive Power output (within applicable Facility Ratings 1.



VAR-002-1.1a R2.1. 1571 When a generator’s automatic voltage regulator is out of service, the Generator Operator

shall use an alternative method to control the generator voltage and reactive output to

meet the voltage or Reactive Power schedule directed by the Transmission Operator.



VAR-002-1.1a R2.2. 1571 When directed to modify voltage, the Generator Operator shall comply or provide an

explanation of why the schedule cannot be met.

VAR-002-1.1a R3. 1571 Each Generator Operator shall notify its associated Transmission Operator as soon as Appendix 5.1-3, Chp.5 of Market Rules,

practical, but within 30 minutes of any of the following: states that :"Each ancillary service provider

shall: 1.3.6.1 notify the IMO immediately upon

the forced outage of the AVR at its registered

facility that is a generation facility being forced

out of service; or 1.3.6.2 for planned outages,

prior to the AVR being removed from its

registered facility that is a generation facility

for maintenance, follow the procedures outlined

in section 6" .





VAR-002-1.1a R3.1. 1571 A status or capability change on any generator Reactive Power resource, including the

status of each automatic voltage regulator and power system stabilizer and the expected

duration of the change in status or capability.

Jan, 2007 7of-24

Generator Operator









Requirement





IRCP Form

Number





Number

Standard

Text of Requirement Comments

Number





VAR-002-1.1a R3.2. 1571 A status or capability change on any other Reactive Power resources under the

Generator Operator’s control and the expected duration of the change in status or

capability.

VAR-002-1.1a R5.1. 1571 If the Generator Operator can’t comply with the Transmission Operator’s specifications,

the Generator Operator shall notify the Transmission Operator and shall provide the

technical justification.





1

When a Generator is operating in manual control, reactive power capability may change

based on stability considerations and this will lead to a change in the associated Facility

Ratings.









Jan, 2007 8of-24

Implementation

Requirement

Number

Standard









Date

Number







BAL-005-0b R1.1. 4/1/2005









COM-002-2 R1. 1/1/2007









EOP-004-1 R2. 1/1/2007









EOP-004-1 R3. 1/1/2007









EOP-004-1 R3.1. 1/1/2007

EOP-004-1 R3.2. 1/1/2007









EOP-004-1 R3.3. 1/1/2007









EOP-005-1 R3.2.1 Form 1532









EOP-004-1 R3.4. 1/1/2007









IRO-001-1 R8. 1/1/2007

IRO-004-1 R4. 11/1/2006









PRC-001-1 R3. 1/1/2007







PRC-001-1 R3.1. 1/1/2007







PRC-001-1 R5. 1/1/2007







PRC-001-1 R5.1. 1/1/2007







TOP-001-1 R3. 1/1/2007









TOP-001-1 R6. 1/1/2007









TOP-001-1 R7. 1/1/2007

TOP-001-1 R7.1. 1/1/2007









TOP-001-1 R7.3. 1/1/2007









TOP-002-2 R3. 1/1/2007









TOP-002-2 R13. 1/1/2007









TOP-002-2 R14. 1/1/2007







TOP-002-2 R14.1. 1/1/2007



TOP-002-2 R15. 1/1/2007









TOP-002-2 R18. 1/1/2007







TOP-003-0 R1. 1/4/2005



TOP-003-0 R1.1. 1/4/2005

TOP-003-0 R2. 1/4/2005









TOP-003-0 R3. 1/4/2005

Text of Requirement









Each Generator Operator with generation facilities operating in an Interconnection shall

ensure that those generation facilities are included within the metered boundaries of a

Balancing Authority Area.









Each Transmission Operator, Balancing Authority, and Generator Operator shall have

communications (voice and data links) with appropriate Reliability Coordinators,

Balancing Authorities, and Transmission Operators. Such communications shall be

staffed and available for addressing a real-time emergency condition.







A Reliability Coordinator, Balancing Authority, Transmission Operator, Generator

Operator or Load Serving Entity shall promptly analyze Bulk Electric System

disturbances on its system or facilities.







A Reliability Coordinator, Balancing Authority, Transmission Operator, Generator

Operator or Load Serving Entity experiencing a reportable incident shall provide a

preliminary written report to its Regional Reliability Organization and NERC.







The affected Reliability Coordinator, Balancing Authority, Transmission Operator,

Generator Operator or Load Serving Entity shall submit within 24 hours of the

disturbance or unusual occurrence either a copy of the report submitted to DOE, or, if no

DOE report is required, a copy of the NERC Interconnection Reliability Operating Limit

and Preliminary Disturbance Report form. Events that are not identified until some time

after they occur shall be reported within 24 hours of being recognized.

Applicable reporting forms are provided in Attachments 022-1 and 022-2.









Under certain adverse conditions, e.g., severe weather, it may not be possible to assess

the damage caused by a disturbance and issue a written Interconnection Reliability

Operating Limit and Preliminary Disturbance Report within 24 hours. In such cases, the

affected Reliability Coordinator, Balancing Authority, Transmission Operator, Generator

Operator, or Load Serving Entity shall promptly notify its Regional Reliability

Organization(s) and NERC, and verbally provide as much information as is available at

that time. The affected Reliability Coordinator, Balancing Authority, Transmission

Operator, Generator Operator, or Load Serving Entity shall then provide timely, periodic

verbal updates until adequate information is available to issue a written Preliminary

Disturbance Report.

Testing of critical components associated with key facilities shall be performed at a frequency and for a

duration that is sufficient to reasonably ensure that the critical components will function properly when

isolated from all power sources not available during a partial or complete IESO-controlled grid blackout.

Currently, this frequency and duration of testing must meet the requirements of NPCC Document A-3

Section 4.10 or its successor A-12.





If, in the judgment of the Regional Reliability Organization, after consultation with the

Reliability Coordinator, Balancing Authority, Transmission Operator, Generator

Operator, or Load Serving Entity in which a disturbance occurred, a final report is

required, the affected Reliability Coordinator, Balancing Authority, Transmission

Operator, Generator Operator, or Load Serving Entity shall prepare this report within 60

days. As a minimum, the final report shall have a discussion of the events and its cause,

the conclusions reached, and recommendations to prevent recurrence of this type of

event. The report shall be subject to Regional Reliability Organization approval.



Transmission Operators, Balancing Authorities, Generator Operators, Transmission

Service Providers, Load-Serving Entities, and Purchasing-Selling Entities shall comply

with Reliability Coordinator directives unless such actions would violate safety,

equipment, or regulatory or statutory requirements. Under these circumstances, the

Transmission Operator, Balancing Authority, Generator Operator, Transmission Service

Provider, Load-Serving Entity, or Purchasing-Selling Entity shall immediately inform the

Reliability Coordinator of the inability to perform the directive so that the Reliability

Coordinator may implement alternate remedial actions.

Each Transmission Operator, Balancing Authority, Transmission Owner, Generator

Owner, Generator Operator, and Load-Serving Entity in the Reliability Coordinator Area

shall provide information required for system studies, such as critical facility status, Load,

generation, operating reserve projections, and known Interchange Transactions. This

information shall be available by 1200 Central Standard Time for the Eastern

Interconnection and 1200 Pacific Standard Time for the Western Interconnection.



A Generator Operator or Transmission Operator shall coordinate new protective systems

and changes as follows.



Each Generator Operator shall coordinate all new protective systems and all protective

system changes with its Transmission Operator and Host Balancing Authority.



A Generator Operator or Transmission Operator shall coordinate changes in generation,

transmission, load or operating conditions that could require changes in the protection

systems of others:

Each Generator Operator shall notify its Transmission Operator in advance of changes in

generation or operating conditions that could require changes in the Transmission

Operator’s protection systems.

Each Transmission Operator, Balancing Authority, and Generator Operator shall comply

with reliability directives issued by the Reliability Coordinator, and each Balancing

Authority and Generator Operator shall comply with reliability directives issued by the

Transmission Operator, unless such actions would violate safety, equipment, regulatory

or statutory requirements. Under these circumstances the Transmission Operator,

Balancing Authority or Generator Operator shall immediately inform the Reliability

Coordinator or Transmission Operator of the inability to perform the directive so that the

Reliability Coordinator or Transmission Operator can implement alternate remedial

actions.

Each Transmission Operator, Balancing Authority, and Generator Operator shall render

all available emergency assistance to others as requested, provided that the requesting

entity has implemented its comparable emergency procedures, unless such actions would

violate safety, equipment, or regulatory or statutory requirements.

Each Transmission Operator and Generator Operator shall not remove Bulk Electric

System facilities from service if removing those facilities would burden neighboring

systems unless:

For a generator outage, the Generator Operator shall notify and coordinate with the

Transmission Operator. The Transmission Operator shall notify the Reliability

Coordinator and other affected Transmission Operators, and coordinate the impact of

removing the Bulk Electric System facility.

When time does not permit such notifications and coordination, or when immediate

action is required to prevent a hazard to the public, lengthy customer service

interruption, or damage to facilities, the Generator Operator shall notify the Transmission

Operator, and the Transmission Operator shall notify its Reliability Coordinator and

adjacent Transmission Operators, at the earliest possible time.

Each Load Serving Entity and Generator Operator shall coordinate (where confidentiality

agreements allow) its current-day, next-day, and seasonal operations with its Host

Balancing Authority and Transmission Service Provider. Each Balancing Authority and

Transmission Service Provider shall coordinate its current-day, next-day, and seasonal

operations with its Transmission Operator.

At the request of the Balancing Authority or Transmission Operator, a Generator

Operator shall perform generating real and reactive capability verification that shall

include, among other variables, weather, ambient air and water conditions, and fuel

quality and quantity, and provide the results to the Balancing Authority or Transmission

Operator operating personnel as requested.

Generator Operators shall, without any intentional time delay, notify their Balancing

Authority and Transmission Operator of changes in capabilities and characteristics

including but not limited to:

Changes in real output capabilities. (Effective August 1, 2007)



Generation Operators shall, at the request of the Balancing Authority or Transmission

Operator, provide a forecast of expected real power output to assist in operations

planning (e.g., a seven-day forecast of real output).



Neighboring Balancing Authorities, Transmission Operators, Generator Operators,

Transmission Service Providers and Load Serving Entities shall use uniform line

identifiers when referring to transmission facilities of an interconnected network.

Generator Operators and Transmission Operators shall provide planned outage

information.

Each Generator Operator shall provide outage information daily to its Transmission

Operator for scheduled generator outages planned for the next day (any foreseen outage

of a generator greater than 50 MW). The Transmission Operator shall establish the

outage reporting requirements.

Each Transmission Operator, Balancing Authority, and Generator Operator shall plan

and coordinate scheduled outages of system voltage regulating equipment, such as

automatic voltage regulators on generators, supplementary excitation control,

synchronous condensers, shunt and series capacitors, reactors, etc., among affected

Balancing Authorities and Transmission Operators as required.

Each Transmission Operator, Balancing Authority, and Generator Operator shall plan

and coordinate scheduled outages of telemetering and control equipment and associated

communication channels between the affected areas.

Comments









Although the responsibility to have and

maintain metering equipment

operationally lies with the facility owner

under the market rules, the IESO assures

adherence to the requirement through ME

registration and enforcement through

MACD for the Ontario Area.

Communication (voice and data) and

staffing requirements are explicitly defined

by the market rules and must are required

to be in place as a prerequisite to being

registering and permitted to participate in

the IAM.

Per the M.R. all incidents are to be analysed

& reported to the IESO in real time. Follow-

up reporting needs will be determined by

the IESO on a case by case bases in

consultation with the MP.

Reported to the IESO CRO in real-time.

Follow-up is performed by Market

Analysis Incident review and F/U

processes, as required for all reportable

incidents.

Reported to the IESO CRO in real-time.

Follow-up is performed by Market

Analysis Incident review and F/U

processes, as required for all reportable

incidents.

Reported to the IESO CRO in real-time.

Follow-up is performed by Market

Analysis Incident review and F/U

processes, as required for all reportable

incidents.

Reported to the IESO CRO in real-time.

Follow-up is performed by Market

Analysis Incident review and F/U

processes, as required for all reportable

incidents.









Obligations for critical component testing

explicit for key facility owners and is in

accordance with NPCC A3, S4.10 and is

monitored via A3-1 template IESO form

1532

Incident Report prepared by the IESO with

input from all affected market participants

as required.









Obligations under Ch. 5 of the MRs & MM

7.4 S. 4.0 requires MPs to take action as

directed by the IESO.

Real-time day to day operations and

logging of compliance issues by the CRO

with MACD F/U.

Existing obligations under the MRs for the

provision of information as required for

Day-ahead MFI analysis. Reviewing need

to monitor through IRCP?









CAA Process and requirements of the OEB

codes for connecting to transmitter or

distribution system.

CAA Process and requirements of the OEB

codes for connecting to transmitter or

distribution system

CAA Process and requirements of the OEB

codes for connecting to transmitter or

distribution system

CAA Process and requirements of the OEB

codes for connecting to transmitter or

distribution system

See IRO-001 R8; Obligations covered by

Ch. 5 of the M.R and compliance issues

logged by the CRO in Real-time operations

(also see IRO-001-R8)









IESO real-time operations provides

emergency assistance to other Areas

pursuant to agreements and will direct

MPs as appropriate.

Managed by the IESO Outage Management

and Approval process. IESO MFI Outage

analysis determines implications and

approves accordingly

Part of the IESO outage approval process

and in accordance with obligations under

the market rules. Reviewing need for active

monitoring

Notification and F/U in real-time









GOP must notify the IESO when

generating unit is unavailable and is

factored into SAA







IESO initiates these tests pursuant to Ch 5

of the MRs and is considering to monitor

through IRCP?

Also addressed by the MOD-024 MOD-025

standards (NPCC A13 and A14)

May monitor to ensure obligations are

understood and followed by all.



May monitor to ensure obligations are

understood and followed by all.

GOP must notify when generating unit is

unavailable and is factored into SAA

May monitor to ensure obligations are

understood and followed by all.

N/A since managed by the IESO through

Use of SDX standards for uploading to

NERC. IESO for R/T and day-ahead

IESO outage Process under the market rules



Obligations to notify the IESO for planned

outages under the M.R and part of the

outage process. Will consider need for

active monitoring via IRCP.

Obligations to coordinate planned outages

with the IESO as part of the outage process

and reviewed by MFI and market limits to

assess impact.



Not necessary since the market rules and

Market Manual obligates all generators to

notify the IESO when units are unavailable

or de-rated. Notification failures are logged

and F/U by MACD.

Corresponding NERC

Criteria Sections GOP Forms Standard

Directory #2 - Emergency Section 5.4 - Generator Underfrequency

Operations Tripping Requirement √ IESO Form 1519 PRC-007



Directory #3 - Maintenance Section 5.0 - NPCC Full Member, More

Criteria for Bulk Power Stringent Criteria (Transmission facilities

System Protection protection system maintenance & test

program) √ IESO Form 1521 PRC-005



Directory #9 - Verification of

Generator Gross and Net

Real Power Capability √ IESO Form 1635 MOD-024



Directory #10 - Verification

of Generator Gross and Net

Reactive Power Capability

√ IESO Form 1636 MOD-025



Other docs by cuiliqing
7 Recipes from Joe A.
Views: 2  |  Downloads: 0
Re-installingXPMode
Views: 3  |  Downloads: 0
telefonica_en
Views: 4  |  Downloads: 0
3220 Chap 6 demos
Views: 2  |  Downloads: 0
chap history.docx
Views: 3  |  Downloads: 0
Subcontractor Bid Form - The Fountains
Views: 1  |  Downloads: 0
English
Views: 1  |  Downloads: 0
DESIGNER'S SCHEDULE USE
Views: 1  |  Downloads: 0
Security Service Providers
Views: 45  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!