Embed
Email

EL PASO - LAS CRUCES REGIONAL SUSTAINABLE WATER PROJECT

Document Sample

Shared by: cuiliqing
Categories
Tags
Stats
views:
0
posted:
10/29/2011
language:
English
pages:
39
EL PASO - LAS CRUCES REGIONAL

SUSTAINABLE WATER PROJECT

CONSTRUCTION DETAILS FOR NEPA PROCESS

FINAL TECHNICAL MEMORANDUM









PREPARED FOR:



New Mexico – Texas Water Commission

December 1999







Boyle Engineering Corp. Parsons Engineering Science, Inc.

6400 Uptown Blvd. NE, Suite 600-E 406 W. So. Jordan Parkway, Suite 300

Albuquerque, NM 87110 South Jordan, UT 84095

(505) 883-7700 (801) 572-5999

Table of Contents

Executive Summary ......................................................................................................................... I



Introduction..........................................................................................................................1

Objectives ................................................................................................................ 1

Related Reports........................................................................................................ 1



Construction Schedule for Identified Improvements for New Mexico Entities ..................3

General Description of the System ..........................................................................3

Hatch Area Water Treatment Plant..........................................................................3

Las Cruces Area Water Treatment Plant..................................................................4

Anthony Area Water Treatment Plant......................................................................4

Factors that Impact the Construction Schedule........................................................5

Design/Construction Packages.................................................................................5

Construction Workforce Estimates, Duration Estimates, and Overall Project

Schedule...................................................................................................................6

Environmental Surface Exposure ............................................................................9

Fuel Depots ..............................................................................................................9

Groundwater and NPDES Permitting ....................................................................11

Staging Areas .........................................................................................................12



References..........................................................................................................................14



Construction Details for Identified Improvements for El Paso Water Utilities .................15

General Description of the System ........................................................................15

Factors that Impact the Construction Schedule......................................................15

Design/Construction Packages...............................................................................16





i

Construction Workforce Estimates, Duration Estimates, and Overall Project

Schedule.................................................................................................................19

Environmental Surface Exposure ..........................................................................22

Fuel Depots ............................................................................................................22

Groundwater and NPDES Permitting ....................................................................26

Staging Areas .........................................................................................................27



References..........................................................................................................................30









ii

TABLES



Table 1 New Mexico Entities Design and Construction Packages ..............................7

Table 2 New Mexico Entities Construction Projects Estimated Construction

Workforce by Month (Construction Personnel)..............................................8

Table 3 New Mexico Entities Phase 1 Environmental Surface Exposure ...................9

Table 4 Phase 1 Fuel Depot Requirements for New Mexico Construction

Projects..........................................................................................................10

Table 5 Phase 1 Permitting Requirements for New Mexico Entities Construction

Projects..........................................................................................................12

Table 6 El Paso Construction Projects Design and Construction Packages ..............17

Table 7 El Paso Construction Projects Estimated Construction Workforce

by Month .......................................................................................................23

Table 8 Environmental Surface Exposure .................................................................24

Table 9 Fuel Depot Requirements for El Paso Construction Projects .......................25

Table 10 Permitting Requirements for El Paso Construction Projects ........................28





PLATE



Plate 1 – El Paso Water Utilities Project Design and Construction Schedule ..................21





APPENDIX



Appendix A

El Paso Water Utilities Project Design and Construction Schedule

New Mexico Entities Project Design and Construction Schedule









iii

Executive Summary





The City of El Paso realized in the late 1980s that its existing

water supply was declining at an alarming rate and that supply

would not be sufficient to meet its current population water

needs, much less satisfy its rapidly increasing population. To

address the current ground water decline problem and assure

that a sustainable water supply for the future could be found, El

Paso and its surrounding neighbors concerned about water

supply in southern New Mexico and west Texas created the New

Mexico – Texas Water Commission (Commission). The

Commission embarked on a series of evaluations, under the

primary heading of the El Paso - Las Cruces Regional

Sustainable Water Project, to determine the most feasible way of

providing a sustainable water supply not only to El Paso but also

to its neighbors to the north, in northern and southern Dona Ana

County.



The overall sustainable water supply project was divided into a

number of water supply alternatives that are composed of major

improvement components, including water treatment plants for

Hatch, Las Cruces, and Anthony, New Mexico, and El Paso,

Texas; the El Paso Upper Valley Water Treatment Plant; the El

Paso Aqueduct; and the Northeast El Paso Aquifer Storage and

Recovery System. Conceptual design packages were prepared

for each project component, describing the scope of actual

construction product for that component, the magnitude of

product required, land requirements, and estimated construction

costs.





I

The primary focus of this technical memorandum is to evaluate

the overall construction project’s physical and time constraints,

determine reasonable construction packaging and scheduling as

consistent as possible with local workforce constituents, estimate

actual construction labor requirements on a monthly basis, and

characterize the physical requirements of construction as they

relate to rights of way, environmental surface exposure, fuel

storage, staging, and other construction related activities.









II

Introduction









Objectives

The goal of this technical memorandum is to document all construction phase activities for the Phase 1

Alternative Components of the El Paso – Las Cruces Regional Sustainable Water Project under the

authority of the El Paso Water Utilities (EPWU). This work is in support of the National Environment

and Policy Act (NEPA) process, which is currently underway in connection with the El Paso – Las

Cruces Regional Sustainable Water Project.





Related Reports

Information, primarily, from the following reports was used in developing this report. Other references

used to a lesser extent are presented in the reference section of this Technical Memorandum.



Siting Study for Phase 1 Facilities for Dona Ana County, Draft Final Report, July 1999



This study, prepared by Parsons Engineering Science, Inc., provides information as to the location,

capital cost, and operations and maintenance cost of a 4.5 million-gallon-per-day (mgd) water treatment

plant for the Village of Hatch, New Mexico, a 50 mgd water treatment plant for the City of Las Cruces,

New Mexico, as well as other central Dona Ana County users, and a 16 mgd water treatment plant for

Anthony, New Mexico. The aqueduct routes evaluated and capital costs of treated water transmission

waterlines are also included.



Addendum to the Siting Study for Phase 1 Facilities for Dona Ana County, Draft Final

Report, November 1999



The objectives of this study, prepared by Parsons Engineering Science, Inc. was to:



• Determine the capacity of the water treatment plant required for the Central Planning Area

(CPA) in 2010, 2020, and 2030, considering conjunctive use of ground water by CPA water

suppliers.



• Identify a land parcel north of Las Cruces for a water treatment plant to serve the CPA.



• Estimate treatment plant construction, operation, and maintenance costs for the water treatment

plant.



• Identify any impacts of construction activities on the current operations of the canals if canals are

used for raw water delivery.









1

• Compare costs of construction of a water treatment plant on the Rio Grande at the I-10 site and a

site north of Las Cruces.



Study of Conveyance Facilities for Year-Round Delivery of Surface Water to Water

Treatment Plants (New Mexico- Texas Aqueduct), Draft, July 1999



This study, prepared by Parsons Engineering Science, Inc., evaluated the feasibility of a number of open

channel and closed conduit conveyance systems and alignments to transport 96 mgd from the Mesilla

Dam and deliver 16 mgd to Anthony, New Mexico, and 80 mgd to the Upper Valley Treatment Plant

site. Construction requirements, including anticipated construction zones and construction schedules

associated with viable options and lined and unlined channels and closed conduit pipe, were provided in

the study.



El Paso Upper Valley Water Treatment Plant Conceptual Site Layout, June 8, 1999



This report, prepared by Boyle Engineering Corporation, provided information on capital and annual

operation and maintenance costs for conventional and membrane technology water treatment plant for a

capacity of 80 mgd.



El Paso Aqueduct Conceptual Design, Draft Final Report, June 18, 1999



This technical memorandum, prepared by Boyle Engineering, provided preliminary cost estimates of

construction improvements required to convey treated water from the Upper Valley Water Treatment

Plant to northwest El Paso and, through the Anthony Gap, to northeast El Paso for either direct use in

the EPWU water distribution system or to the contemplated Aquifer Storage and Recovery System.



Concept Design of ASR Wellfield and Collection Facilities, Final Report, July 1999



This report, prepared by Boyle Engineering Corporation, provided proposed system components and

engineer’s estimate of construction cost for 71 Aquifer Storage and Recovery (ASR) wells in northeast

El Paso.



Project Economic Details Technical Memorandum, Draft Report, August 1999



This report, prepared by Boyle Engineering Corporation and Parsons Engineering Science, Inc.,

documented the overall Engineer’s Opinion of Probable Capital Costs as well as Operations and

Maintenance Costs for the major system components of the El Paso – Las Cruces Regional Sustainable

Water Project.







2

Construction Schedule for Identified

Improvements for New Mexico Entities





General Description of the System

The identified Phase 1 needs for New Mexico entity water supply improvements include providing 3.5

million gallons per day (mgd) of treated water to municipal water entities in Rincon Valley, 20 mgd of

treated water to municipal water entities in north and central Mesilla Valley, and 4.0 mgd of treated

water to municipal water entities in southern Mesilla Valley. To provide this water will require the

construction of three new water treatment plants and associated distribution pipelines. This section

describes the Phase 1 water treatment and delivery facilities needed and provides construction details for

their construction.





Hatch Area Water Treatment Plant

The Hatch Area (North Planning Area) Water Treatment Plant will be located near the community of

Hatch in the Rincon Valley. Phase 1 construction for this plant will provide a total treatment capacity of

3.5 mgd with the capability for later expansion to 4.5 mgd capacity. The treatment plant will initially

service the communities of Hatch, Rincon, and Spaceport in Phase 1, but will eventually service the

communities of Salem and Garfield as well.



Raw water will be either diverted to the plant directly from a new diversion facility at the Rio Grande or

through the existing Rio Grande Project canal system with initial diversion from the river at Percha Dam

and delivery to the Hatch Area Water Treatment Plant from the Hatch Canal. No enlargement of the

canal system would be necessary, but substantial non-irrigation season conveyance losses may occur due

to evaporation and seepage. Due to these potential losses, this study assumes raw water will be diverted

directly from the Rio Grande to the treatment plant rather than delivered through the existing canal

system. The Hatch Area Water Treatment plant will receive the delivered raw water into a series of

storage/sedimentation ponds for settling of suspended solids. The water will then be pumped through a

membrane treatment process and passed through a granular activated carbon (GAC) filter. Chlorination

will complete the treatment process to achieve Safe Drinking Water Act (SDWA) standards for finished

drinking water.



Two conveyance pipelines will distribute treated water from the Hatch Area Water Treatment Plant to

the communities of Hatch, Rincon, Spaceport, and eventually to Salem and Garfield. A 14-inch

diameter pipeline will convey treated water 4.0 miles to the communities of Rincon and Spaceport. A

10-inch diameter pipeline will convey treated water 1.9 miles to Hatch. In a later phase, an 8-inch

pipeline will extend from the 10-inch Hatch pipeline terminus another 4.8 miles to Salem and Garfield.



As a part of Phase 1, two treated water pump stations will be located at the Hatch Area Water Treatment

Plant site. The North Pump Station will provide pressure for the transmission line to Hatch and

eventually to Salem and Garfield. The South Pump Station will provide pressure for transmission to

Rincon and Spaceport.







3

Las Cruces Area Water Treatment Plant

The Las Cruces Area (Central Planning Area) Water Treatment Plant will be located near Las Cruces

alongside the Rio Grande at Interstate 10 and will serve the communities of north and central Mesilla

Valley. Phase 1 construction for this plant will provide a total treatment capacity of 20 mgd with the

capability for later expansion to 26 mgd and finally to 34 mgd capacity. Phase 1 will include the

construction of all transmission pipelines required for water delivery to Las Cruces and to the smaller

communities of north and central Mesilla Valley. This will make the Phase 1 20 mgd treatment plant

capacity available to service all areas of growth in the Las Cruces Area.



Raw water will be diverted to the Las Cruces Area Water Treatment Plant directly from a new diversion

on the Rio Grande and through a short 48-inch pipeline to the treatment plant. The plant will employ the

treatment process described above for the Hatch Area Water Treatment Plant.



Phase 1 distribution facilities include:



• 0.9 mile 48-inch transmission line to Las Cruces



• 15.4 mile north transmission line beginning at Las Cruces as a 24-inch line and reducing to a 14-

inch line at Dona Ana that extends to Radium Springs



• 1.6 mile 18-inch lateral transmission line to Dona Ana



• 11.7 mile 14-inch south transmission line extending from Las Cruces to Mesquite



• 2.6 mile 12-inch lateral transmission line to San Miguel



For Phase 1, a 20 mgd treated water pump station will be located at the Las Cruces Area Water

Treatment Plant site to pressurize the transmission lines. Later phases will expand the pumping plant as

additional pumping capacity becomes needed. Ultimate pumping capacity is expected to be 34 mgd.





Anthony Area Water Treatment Plant

The Anthony Area (South Planning Area) Water Treatment Plant, located in southern Mesilla Valley

near the community of Chamberino, will have a Phase 1 treatment capacity of 4.0 mgd with capability

for later expansion to 8.0 mgd and ultimately to 16 mgd. In Phase 1, the Anthony Area Water Treatment

Plant will provide treated water to the community of Anthony. Later expansions will extend treated

water service to the communities of Chaparral, Berino, La Mesa, Vado, and Chamberino.



A diversion facility at the Rio Grande will divert raw water will to the Anthony Area Water Treatment

Plant. The treatment plant will employ the treatment process described above for the Hatch Area Water





4

Treatment Plant. Following treatment, a Phase 1 pumping plant located at the treatment plant will pump

treated water to use through a transmission pipeline system. The system will begin as a 30-inch

diameter pipeline, reduce to a 24-inch pipeline, and further reduce to an 18-inch pipeline which will

extend to Anthony.





Factors that Impact the Construction Schedule

The New Mexico entities improvements component of the overall El Paso-Las Cruces Regional

Sustainable Water Project includes the three treatment plant and distribution systems described above.

These facilities have a total capital cost of approximately $75 million and a construction time line of

about 7 years. For such a large project, there are many factors that can have an impact on the

construction schedule. Such factors as the time length of the project, the desired completion dates for

each of the water treatment plants and service pipelines, required permits and contracts, construction

bonding requirements, and the desire to have local business participate in the project construction all

effect the schedule.



The ideal construction scenario is to complete the water treatment plants at the same time that the

distribution pipelines are completed. Concurrent construction will allow the entire system to begin

operation sooner. This will help prevent wasting of financial capital and construction warranty periods

for system components that might otherwise sit idle waiting for other system components to be

constructed. Also, flushing and cleaning of the system will be more efficient since the entire system can

be flushed and cleaned once rather than having to clean each component separately and then having to

do it again for disinfection once the system is completed.





Design/Construction Packages

The New Mexico entities water treatment and distribution systems improvements involve many different

communities scattered for many miles along the Rio Grande. Different funding mechanisms and

numerous approvals and permits will be required from many different city, state, and federal agencies.

Separate design and construction packages for each of the three planning area water treatment and

distribution systems are therefore prudent.



Management of the design, land acquisition, permitting, and construction can be accomplished either

under an umbrella program management approach or under a separate project approach. The program

management approach would involve a lead agency, such as the county, that would hire a program

management consultant to coordinate all activities required to construct all three systems. The separate

project approach would either require each set of communities in each planning area to obtain funding,

obtain permits, and oversee design and construction of their system separately; or the county could act

as the lead agency for performing these functions.







5

Due to the fragmented nature of the planning area systems and the communities served, the program

management approach is probably not warranted for New Mexico entities improvements. The better

approach appears to be for separate project management for each of the three planning area systems with

the county acting as the lead agency to be the prime mover for coordination between the communities

and keeping each planning area project on-track. This latter approach was assumed for the estimates

presented herein.



Design activities for each of the planning areas are quite similar. Each involves the design of a

diversion structure on the Rio Grande, the design of a membrane water treatment plant with identical

processes, and the design of pump stations and transmission lines. Each project should thus be divided

into separate design packages for the diversion structures, the treatment plants and pump stations, and

the transmission pipelines. The greatest efficiency in design and shared maintenance may result if

similar the designs are developed for the diversions and treatment plants.



For each distribution system, transmission pipeline design packages may be awarded for each Phase 1

system as a whole or may be divided into separate design packages for each major pipeline segment.

The latter would better achieve the goal of providing maximum opportunity for local design and

construction firms and has therefore been assumed for the estimates presented herein. Table 1 describes

the design and construction packages.





Construction Workforce Estimates, Duration Estimates, and Overall Project

Schedule

Construction workforce estimates were determined based on the level of effort required to perform a

specific activity. Workforce estimates for distribution facilities were prepared by Parsons Engineering

Science in consultation with Burns Construction Company who has constructed numerous pipelines in

the Las Cruces area and Greg Fischer of Ames Construction who has constructed numerous pipelines in

Utah. Since there are no local New Mexico contractors familiar with water treatment plant construction,

Parsons compared its experience on other projects with the information developed for El Paso Upper

Valley Water Treatment Plant. Construction activities for the diversion facilities, treatment plants,

pumping stations, and distribution pipelines can proceed independently and concurrently. Minor

coordination activities are necessary between the components of each system to ensure matching of

locations, lines, and grades.



The major activities of the project design and construction schedule are shown on Table 2. Project

construction manpower requirements on a monthly basis were prepared overlaying the estimate of

individual construction project workforce requirements on the overall construction project schedule.

Table 2 is a summary of construction manpower requirements by month for the entire period that

construction is expected to occur.









6

Table 1

New Mexico Entities Design and Construction Packages

Project Design and Rationale for Design and

Construction Packaging Work Effort Construction Packaging

Hatch Area Water Treatment Plant Design/Construction One site, sophisticated interdisciplinary work

and Pump Station Package

Hatch Area Design/Construction One site, sophisticated interdisciplinary work

Diversion Structure and Pipeline Package

Hatch Area Distribution Pipelines

Design/Construction Similar construction, bid package dollar amount

14-inch transmission line Package designed to encourage local contractor involvement

Design/Construction Similar construction, bid package dollar amount

10-inch transmission line Package designed to encourage local contractor involvement

Las Cruces Area Water Treatment Design/Construction One site, sophisticated interdisciplinary work

Plant and Pump Station Package

Las Cruces Area Design/Construction One site, sophisticated interdisciplinary work

Diversion Structure and Pipeline Package

Las Cruces Area

Distribution Pipelines

48-inch transmission line to Las Design/Construction Similar construction, bid package dollar amount

Cruces Package designed to encourage local contractor involvement

24-inch transmission line and 18-inch Design/Construction Similar construction, bid package dollar amount

lateral to Dona Ana Package designed to encourage local contractor involvement

14-inch transmission line to Radium Design/Construction Similar construction, bid package dollar amount

Springs Package designed to encourage local contractor involvement

14-inch and 12-inch transmission lines Design/Construction Similar construction, bid package dollar amount

to Mesquite and San Miguel Package designed to encourage local contractor involvement

Anthony Area Design/Construction One site, sophisticated interdisciplinary work

Water Treatment Plant and Pump Package

Station

Anthony Area Design/Construction One site, sophisticated interdisciplinary work

Diversion Structure and Pipeline Package

Anthony Area

Distribution Pipeline

Design/Construction Similar construction, bid package dollar amount

Anthony transmission line Package designed to encourage local contractor involvement









7

Table 2

New Mexico Entities Construction Projects Estimated Construction Workforce by Month (Construction Personnel)

Resource Name 2001 2002 2003

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Hatch Area

Water Treatment Plant (3.5 MGD)

Construction Administration Support 3 3 3 3 3 3 3 3 3 3 3 3 3 3

Construction Labor Force 20 20 20 35 35 50 50 50 35 35 20 20

Transmission Lines (3.5 MGD)

Construction Administration Support 1 1 1 1

Construction Labor Force 10 10 10 10

Rio Grande Diversion (3.5 MGD) 1 1 1

Construction Administration Support 9 9 9

Construction Labor Force

Total Construction Personnel 0 0 0 0 0 0 0 0 0 0 0 3 23 23 23 38 38 53 53 53 49 59 44 44 3 0 0 0 0 0 0 0 0 0 0 0



Year 2003 2004 2005

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Anthony Area

Water Treatment Plant (4 MGD)

Construction Administration Support 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3

Construction Labor Force 20 20 20 35 35 60 60 60 60 35 35 20 20 20

Transmission Lines (4 MGD)

Construction Administration Support 1 1 1 1 1

Construction Labor Force 5 5 5 5 5

Rio Grande Diversion (4 MGD)

Construction Administration Support 1 1 1

Construction Labor Force 10 10 10



Total Construction Personnel 0 0 0 0 0 0 0 0 0 0 0 3 23 23 23 38 38 63 63 63 63 44 44 40 40 40 3 0 0 0 0 0 0 0 0 0



Year 2006 2007 2008

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Las Cruces Area

Water Treatment Plant (20 MGD)

Construction Administration Support 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4

Construction Labor Force 55 55 55 55 55 55 80 80 115 115 115 115 115 115 80 80 80 55 55 55 55 55 55

Transmission Lines (20 MGD)

Construction Administration Support 1 1 1 1 1 1 1

Construction Labor Force 20 20 20 20 20 20 20

Rio Grande Diversion (20 MGD)

Construction Administration Support 1 1 1 1

Construction Labor Force 14 14 14 14

Total Construction Personnel 0 0 0 0 0 0 0 0 0 4 59 59 59 59 59 59 84 84 119 119 119 119 119 119 84 84 105 80 80 95 95 95 95 0 0 0

Environmental Surface Exposure

During construction, work will be performed within permanent easements and sites and also in

temporary construction easements obtained specifically for construction of the improvements. A

summary of soil disturbance areas for New Mexico’s portion of the El Paso - Las Cruces Regional

Sustainable Water Project is listed in Table 3.





Table 3

New Mexico Entities Phase 1 Environmental Surface Exposure

Disturbance Description for

New Mexico Construction Area

Construction Component Area Description Projects (acres)

Hatch Area Phase 1

Hatch Area Water Treatment Plant and pump station Treatment and pump plant site 17

Diversion structure and pipeline Diversion structure site 1

Pipeline (300’ x 50’) <1

Distribution system 31,600’ X 50’ 36

Las Cruces Area Phase 1

Las Cruces Area Water Treatment Plant and pump Treatment and pump plant site 38

station

Diversion structure and pipeline Diversion structure site 1

Pipeline (200’ X 55’) <1

Distribution system 169,900’ X 50’ 195

Anthony Area Phase 1

Anthony Area Water Treatment Plant and pump station Treatment and pump plant site 21

Diversion structure and pipeline Diversion structure site 1

Pipeline (2400’ X 55’) 3

Distribution system 36,363’ X 50’ 42





Fuel Depots

Construction vehicle and equipment fueling requirements are based on the size of construction site

available, location and proximity of construction activity to existing fuel sources and type of equipment

required to perform the actual construction work. Options identified are:



• On-Site Storage. – For construction activities on a fixed site where there is 24-hour security and

a need for vast quantities of fuel, fuel may be stored on site.



9

• Existing Facilities – For mobile construction equipment where fuel is required on an irregular

basis, such as other than daily or several times a day, it may be cost effective to purchase fuel at

existing sites. In the particular case of gasoline powered equipment this is the preferred method

of fuel storage since non-construction vehicles also use the same fueling facilities.



• Jobber Service – Where equipment is relatively immobile, but requires fuel on a regular and

generally daily basis, it is common to enlist the services of an independent fuel service to provide

on-site fueling of equipment.



• Combination – Many combinations of fuel service are available and applicable for some

construction activities. For example, pipeline construction is a construction activity where

gasoline driven machinery is often driven to the closest existing facilities on an as-needed basis

while excavation and backfill equipment may be serviced by the general contractor’s service

vehicles, using above ground fuel storage erected on the specific project.



Table 4 summarizes the location and type of fuel depots anticipated for each construction project.



Table 4

Phase 1 Fuel Depot Requirements for New Mexico Construction Projects

Construction Component Area

Description Fuel Depot Description

Hatch Area Phase 1

Hatch Area Water Treatment Plant and On-site fuel storage

pump station

Diversion structure and pipeline Use existing facilities

Distribution system Use existing facilities plus set up two above ground fuel

storage sites (one for each construction contract)

Las Cruces Area Phase 1

Las Cruces Area Water Treatment On-site fuel storage

Plant and pump station

Diversion structure and pipeline Use existing facilities

Distribution system Use existing facilities plus set up four above ground fuel

storage sites (one for each construction contract)

Anthony Area Phase 1

Anthony Area Water Treatment Plant On-site fuel storage

and pump station

Diversion structure and pipeline Use existing facilities

Distribution system Use existing facilities plus set up one above ground fuel

storage site







10

Groundwater and NPDES Permitting

Permits are required for three main activities during the construction process for the New Mexico

entities improvements. A significant portion of construction activities involves groundwater dewater

activities in the Rio Grande Valley. Phase 1 pipeline construction involves flushing and testing of

nearly 14 miles of water transmission lines. In most cases, if construction related water is discharged

into an arroyo or can reach waters or the United States when discharged, a permit is required.



Dewatering Activities



Excavation in the flood plain region of the Rio Grande Valley area will require dewatering. A discharge

permit must be obtained from the State of New Mexico before beginning any dewatering operations.

The permit will require the permittee to estimate the concentrations Total Petroleum Hydrocarbons

(TPH), Total Dissolved Solids (TDS), Total Suspended Solids (TSS), pH, and sulfate in the dewatering

discharge. If any of these constituents are determined to exceed the allowable levels, the permit request

may be denied. If the permit is denied, another method for disposal of the water would be required, such

as treating the water prior to disposal, or the method of construction would have to be modified to

eliminate the undesirable discharge constituents.



Discharge to canals or agricultural drains will require approval of Elephant Butte Irrigation District

(EBID). Discharge to storm sewers will require approval of the municipality or entity responsible for

the storm sewer. In any case, discharge reaching the river will require a State of New Mexico National

Pollution Discharge Elimination System (NPDES) permit.



Use of Chlorinated Water or Discharge to Arroyos or Waters of the United States



Where possible, water used for testing should be reused to minimize the amount of water wasted.

Discharge of chlorinated water from flushing operations and disinfection into storm or sanitary sewers

will require approval of the municipality or entity responsible for the facility. Discharge onto the

ground will require State of New Mexico Environment Department approval. Discharge into an arroyo,

the Rio Grande, or other waters of the United States will require a state NPDES permit. Dechlorination

treatment will be required for discharges to the natural environment.



Storm Water Discharges from Construction Activities



An NPDES permit will be required for any construction activity disturbing at least 5 acres, or

construction activity disturbing less than 5 acres which is part of a larger common plan of development.

All three of the planning area water treatment and distribution systems will fall within these criteria.

Therefore, NPDES permits for the construction of each of these systems will be required. Table 5

summarizes potential permit requirements for the New Mexico entities improvements.





11

Table 5

Phase 1 Permitting Requirements for New Mexico Entities Construction Projects

Groundwater Chlorinated Water Storm Water

Discharge or Discharge to Pollution

Project Construction Package Permit Waters of the US Prevention Plan

Hatch Area Phase 1

Water Treatment Plant and pump

station √ √ √

Diversion structure and pipeline √ √

Distribution system √ √ √

Las Cruces Area Phase 1

Water Treatment Plant and pump

station √ √ √

Diversion structure and pipeline √ √

Distribution system √ √ √

Anthony Area Phase 1

Water Treatment Plant and pump

station √ √ √

Diversion structure and pipeline √ √

Distribution system √ √ √





Staging Areas

Staging areas, for use by the contractor and the New Mexico entities representatives vary in accordance

with site specific work activities. Staging area requirements for major construction components such as

water treatment plant, diversion, and pipeline construction were evaluated. Staging areas for the major

work activities for each treatment and transmission system for New Mexico’s portion of the El Paso –

Las Cruces Regional Sustainable Water Project are described below:



• Project Management – Project management will be conducted either from existing municipal

entity offices or at on-site trailers at the staging area sites for the construction.



• Treatment Plants/Pump Stations – The treatment plant/pump station sites should be of

sufficient size to provide equipment and supplies storage for not only the contractor, but also for

owner representative construction offices as well.









12

• Diversion Structures – A staging area of approximately 1-acre will be required at or near the

Rio Grande diversion structure for the contractor’s construction trailer and for storage of

construction materials.



• Pipeline Distribution Systems – Transmission line construction activities should be contained

within the anticipated construction easements. Pipe will be transported to the general project

vicinity by truck and laid (strung) along the transmission line alignment in front of the

installation crew on an as-needed basis. Equipment such as backhoes, front-end loaders, and

compactors will be staged along the pipeline route. An additional one-half acre of land

somewhere along the pipeline route will be required for the contractor’s trailer and

miscellaneous equipment and materials storage.









13

References









Fischer, Greg, 1999. Ames Construction, Inc., Salt Lake City. Personal communication.



Burns Construction Co., Las Cruces. Personal communication.



Dona Ana County Comprehensive Plan, 1995-2015. Dona Ana County, 1994.



Dona Ana County Final Regional Wastewater Facilities Master Plan. Molzen-Corbin & Associates,

August, 1998.









14

Construction Details for Identified

Improvements for El Paso Water Utilities





General Description of the System

EPWU’s identified needs include processing of 80 mgd of water from the Upper Valley Water

Treatment Plant (UVWTP). Raw water will be conveyed from Mesilla Dam to the UVWTP by one of

two methods. The first method utilizes the New Mexico-Texas Aqueduct to transfer water between the

two sites. This method’s recommended option involves pumping water from immediately downstream

of the Mesilla Dam into the Westside Regulating Reservoir for presedimentation and storage purposes.

A gravity system comprising some 22.4 miles of 72-inch diameter pipe would convey water from the

Westside Regulating Reservoir to the UVWTP. The second method of transport involves transporting

raw water down the Rio Grande River to the UVWTP site, where a diversion structure either across or

along the side of the Rio Grande River at the UVWTP site would be constructed to capture the water for

treatment at the site.



Once the raw water has been conveyed to the UVWTP, water would be pumped under either scenario

into an on-site settling basin. Water will then be treated to Safe Drinking Water Act (SDWA) standards

using either conventional or membrane treatment technology, disinfected, and then placed into on-site

finished water storage, to await distribution as required in EPWU’s distribution system or into the ASR

System as contemplated by the project.



Initially, 20 mgd will be pumped from the UVWTP into northwest El Paso to the Canutillo production

transmission system, through a 60-inch transmission line. The remainder, 60 mgd, will be supplied via

the El Paso Aqueduct System, from the UVWTP, over the Anthony Gap and into northeast El Paso. All

water delivered to northeast El Paso through the El Paso Aqueduct System will be used first to meet area

demands, in lieu of pumping from existing wells in the Hueco Bolson. During early years of operation,

20 mgd of the 60 mgd may be used to meet the northeast area demands. Water in excess of that required

to meet demands will be diverted to one or more of the five selected ASR service areas for recharge

through the network of ASR wells. In later years, less water will be available for injection as more

water is used to meet the northeast area’s demands.



As EPWU’s northwest side system demands increase, it is expected that up to 40 mgd of the total 80

mgd UVWTP capacity will be utilized in northwest El Paso, with the remaining 40 mgd being

transferred to northeast El Paso.





Factors that Impact the Construction Schedule

EPWU’s Alternative improvements component of the overall El Paso – Las Cruces Regional

Sustainable Water Project includes the New Mexico - Texas Aqueduct, Upper Valley Water Treatment

Plant, El Paso Aqueduct, and the Northeast El Paso Aquifer Storage and Recovery System. The cost of

these project improvements is estimated to be in the range of $246,000,000 to $316,000,000. The

targeted completion date for the entire project is the spring of 2005, prior to the summer peak system

demand. Many elements impact the construction schedule. The sheer size of the project, overall desired



15

completion date, similar work effort requirements, construction bonding requirements (EPWU currently

requires a minimum bonding capacity for any of its construction contracts of $15,000,000), and desire

that local business be afforded an opportunity to participate in its construction are all factors that impact

the construction schedule. The construction of several improvement components cannot be completed

until other improvement component construction has been completed and placed on line, such as water

for flushing and testing the El Paso Aqueduct must be supplied from the UVWTP through the El Paso

Aqueduct stations and reservoirs. It is also not prudent to have equipment in place and not in service

through its warranty period, capital investments not used for years, or facilities such as wells disinfected

at the construction completion phase and then idle for years, requiring disinfection before being placed

in service.





Design/Construction Packages

The project, providing a sustainable water supply to El Paso and its neighbors in New Mexico, is a very

large and complex project. The project comprises construction activities over a substantial physical

territory. It will require coordination of the significant simultaneous design and construction activities

of numerous engineering and construction firms, and will also require approvals and permitting from

numerous local, state, and federal agencies. To keep the projects focused, coordinated, and moving and

to act as a clearinghouse for the various activities, a program manager concept is proposed. The job of

the program manager, along with his assistant program managers, will be to first insure the work effort

progresses in accordance with the interests of EPWU and insure the activities are coordinated.



The overall project can be easily divided into the four major topics listed above – namely, the New

Mexico – Texas Aqueduct, Upper Valley Water Treatment Plant, El Paso Aqueduct, and Northeast

Aquifer Storage and Recovery System. Table 6 describes the design and construction packages. Each

major improvement component is described below.



New Mexico – Texas Aqueduct



EPWU’s portion of the recommended New Mexico – Texas Aqueduct alternative, Option D, comprises

constructing some 22.4 miles of 72-inch diameter pipe between the Mesilla Dam and UVWTP site. This

design and construction effort, which will cost nearly $50,000,000, is considered to be one design phase

and under only one construction contract for several important reasons. It is one contiguous project that

must deal with similar permitting and right of way issues with the same authorities throughout its entire

length, requires similar equipment to install identical material, and there is sufficient time available for

the design and construction activities.









16

Table 6

El Paso Construction Projects Design and Construction Packages

Project Design and Rationale for Design and

Construction Packaging Work Effort Construction Packaging

Upper Valley Water Design/Construction One site, sophisticated interdisciplinary work

Treatment Plant Package

New Mexico – Texas Design/Construction One contiguous project

Aqueduct Package

El Paso Aqueduct

Transmission line, UVWTP to Design/Construction Similar construction, bid package dollar amount

Canutillo Package designed to encourage local contractor involvement

Aqueduct UVWTP to Anthony Design Package Similar design

Summit

UVWTP to Anthony 1A Construction Package Similar construction, bid package dollar amount

designed to encourage local contractor involvement

Anthony 1A to Anthony 2A Construction Package Similar construction, bid package dollar amount

designed to encourage local contractor involvement

Anthony 2A to Anthony Construction Package Similar construction, bid package dollar amount

Summit designed to encourage local contractor involvement

Aqueduct, Anthony Summit to Design Package

Loop 375

Anthony Summit to New War Construction Package Similar construction, bid package dollar amount

designed to encourage local contractor involvement

New War to Loop 375 Construction Package Similar construction, bid package dollar amount

designed to encourage local contractor involvement

UVWTP, Anthony 1A and 2A Design/Construction Similar type construction, economy of scale,

Pump Package identical equipment source for critical equipment

Stations

UVWTP Finished Water and Design Package

El Paso Aqueduct Reservoirs

UVWTP Finished Water Construction Package Similar type construction, economy of scale, bid

Reservoirs package dollar amount designed to encourage local

contractor interest

Anthony 1A, 2A, Summit Construction Package Similar type construction, economy of scale, bid

Reservoirs package dollar amount designed to encourage local

contractor interest

Aquifer Storage and

Recovery System

ASR Well Drilling and Design Package

Equipment

ASR Well Drilling Construction Package Specialized construction, consistent construction

product required, based on geology information

obtained throughout project

ASR Well Equipment Construction Package Similar type construction, economy of scale,

identical equipment source for critical equipment

ASR Collection System Piping Design/Construction Similar construction, bid package dollar amount

Package designed to encourage local contractor involvement





17

Upper Valley Water Treatment Plant



The UVWTP project consists of design and construction phase activities of sophisticated equipment and

supporting infrastructure for a water treatment plant within one specific designated site. The cost of the

UVWTP, which is estimated to cost from $103,510,000 to $121,260,000 to design and construct,

includes approximately $2,500,000 estimated for the Open Intake River Diversion Structure located

adjacent to the UVWTP site and required in the event the New Mexico – Texas Aqueduct is not

constructed. This essentially independent or stand alone design and construction effort is considered to

be one design phase and construction phase. Both the design and construction phase require intricate

coordination of numerous disciplines for the design phase as well as the work trades during the

construction phase to successfully build this complex water treatment plant and its auxiliary systems.



El Paso Aqueduct



The El Paso Aqueduct project comprises a series of booster stations and reservoirs, along with 9.5 miles

of 60-inch diameter, 9.4 miles of 42-inch diameter, and 8.9 miles of 48-inch diameter transmission line

to convey water from the UVWTP site to the Anthony Gap Summit and then into EPWU’s northeast

water distribution system. It also includes 4.24 miles of 60-inch diameter transmission line between the

UVWTP site and the existing Canutillo production transmission system.



As with the New Mexico – Texas Aqueduct the El Paso Aqueduct comprises similar design and

construction activities, along with similar permitting and approval processes. Therefore, it is reasonable

to break the project into no more than two design contracts—one from UVWTP to the Anthony Gap

Summit and one from the Anthony Gap Summit into northeast El Paso. However, the fact that the

aqueduct traverses numerous sites between UVWTP and northeast El Paso, coupled with the fact that

the estimated construction cost just for the transmission lines is approximately $47,000,000 and coupled

with the desire by EPWU to give local contractors the opportunity to bid on specific construction

packages, numerous construction packages for the El Paso Aqueduct transmission lines are

recommended.



Similar logic was used in evaluating the booster stations and reservoirs. Booster stations will be nearly

mirror images of each other for design simplicity and ease of maintenance, being modified only as

required to comply with the minor hydraulic changes from one station to another. For this reason, it is

suggested that the booster station component be based on one design and one construction phase

contract. Similar logic dictates the reservoir design be performed by one firm. However, the nearly

$10,000,000 estimated construction cost combined with the desire to give local contractors the

opportunity to bid on specific construction packages results in two construction packages being

recommended. The first construction package is for the booster stations and the second is for the

reservoirs.







18

Aquifer Storage and Recovery



The Northeast El Paso Aquifer Storage and Recovery System (ASR) comprises drilling and equipping

71 injection/recovery wells, and constructing well collector line systems to convey either water through

the El Paso Aqueduct into the wells, in injection mode, or from the well site into distribution system

treatment and storage reservoirs in recovery mode.



The well drilling phase of the contract will involve drilling through a media, which cannot be examined

or described exactly. Estimates of the formation underlying each well site will be prepared prior to

drilling so the contractor is aware of the approximate work effort required to drill the well. As work

proceeds at each site, the drilling will be modified as required to construct the most efficient well. Once

the well has been drilled and test pumped its specific production and water drawn down characteristics

can be described. Knowledge learned from the well drilling construction phase is essential in describing

the permanent pumping equipment that will be then constructed at each site. Based on the time

available for drilling and equipping 71 ASR wells, it is assumed that the well drilling will precede the

well equipment by several months.



Since coordination and sharing of site specific data obtained during the is critical for the equipping

phase of the project well drilling and well equipment design activities are envisioned as a single activity.

And, since the critical data will be shared within the design phase and since well drilling and different

construction firms often perform well equipment activities, well drilling and well equipment

construction activities are separate construction packages.



Well collection system design and construction are single-phase activities and will be one construction

package.





Construction Workforce Estimates, Duration Estimates, and Overall Project

Schedule

Construction workforce estimates were determined based on level of effort required to perform a

specific intended activity. These workforce estimates were prepared by Boyle Engineering Corporation

in conjunction the expertise of a Vice President of Bradbury Stamm Construction, Inc., an Engineering

News-Record top 400 (224 in 1997) contractor. Bradbury Stamm Construction, Inc., is a well-respected

construction firm in the region that is familiar with the terrain, work force, and general construction

climate in and near El Paso. Level of effort included skill level and construction supervision by the

contractor of their workforce. Pipeline construction, for example, was divided into three categories of

workforce effort—installation of 12-inch diameter through 20-inch diameter pipe, 24-inch diameter

through 42-inch diameter pipe, and 48-inch diameter and up pipe, based on the different levels of effort

required to trench, place spoil, install, and finally backfill and compact the trench. Office support was

estimated for each workforce category.







19

Coincident with workforce estimates, duration estimates were created for both the design phase services

identified in Table 1 and for each individual construction package. Dependencies between construction

packages were also evaluated. Specific issues concerning construction packages are provided below:



• New Mexico – Texas Aqueduct – Design and construction activities are primarily independent

of all other design/construction activities. Minor coordination activities will be required between

it and the UVWTP design effort.



• UVWTP – The treatment plant design and construction activities are primarily independent of

other design/construction activities. Minor coordination activities will be required between it

and the New Mexico – Texas Aqueduct and the El Paso Aqueduct.



• El Paso Aqueduct – Design phases of the El Paso Aqueduct components, which include pipe

line design, reservoir design, and pump station design, will require minor coordination

requirements between those components. Construction activities are dependent not only on

individual component construction activities, but are also dependent on the UVWTP construction

completion. Two specific issues must be considered. The first is that water in sufficient

quantities will not be available for flushing/disinfecting/testing the transmission lines until the

plant is on line. It will take over 7.0 million gallons just to fill the transmission line between the

UVWTP and the El Paso Aqueduct Anthony Gap Summit Reservoir. The second issue is that

the facilities cannot be used until the UVWTP is complete since the plant is the source of water

for Northeast El Paso. The capital cost should not be incurred until the facilities are capable of

being used. The normal warranty period for equipment is one year, which should commence

only when the facilities are on line, rather than commence when the equipment cannot be used.



• ASR Well Drilling and Equipment – The design activities for well drilling and equipment are

very dependent, as described earlier in this Technical Memorandum. Since one firm performs

design services, and in doing so the data obtained during the construction phase is transmitted to

the equipment design phase, the construction activities will be performed under two separate

construction contracts. As with other construction components, particularly with substantial

equipment, this entire activity is scheduled to begin as late as possible so the well sites are

complete just after the UVWTP construction is complete.



• ASR Collector Line – The ASR well collector line system design and construction is relatively

independent of other activities except that the well sites must be selected and there is no need to

complete construction until the wells have been equipped and the UVWTP is in operation.



The major activity components of the project design and construction schedule are shown on Plate 1. A

detailed schedule showing breakdown of both the design and construction of all El Paso improvement

components is included as an insert to this report in Appendix A.









20

PLATE 1

El Paso - Las Cruces Regional Sustainable Water Project

El Paso Water Utilities Project Design and Construction Schedule

99 2000 2001 2002 2003 2004 2005

ID Task Name Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3

1 Program Management

2 New Mexico - Texas Aqueduct

3 Upper Valley Water Treatment Plant

4 El Paso Aqueduct

5 Pump Stations

6 UVWTP Finished Water and El Paso Aqueduct Reservoirs

7 Pipeline between UVWTP and Anthony Gap Summit

8 Pipeline Between Anthony Gap Summit and Loop 375 Facilities

9 Aquifer Storage and Recovery System

10 Recovery and Injection Well Drilling/Equipment

11 Collection Pipeline System









Task Summary Rolled Up Progress



Progress Rolled Up Task



Milestone Rolled Up Milestone

Project construction manpower requirements on a monthly basis were prepared by overlaying the

estimate of individual construction project workforce requirements on the overall construction project

schedule. Table 7 is a summary of construction manpower requirements by month for the entire period

that construction is expected to occur.





Environmental Surface Exposure

During construction, work will be performed within permanent easements and sites and also in

temporary construction easements obtained specifically for this project. Construction activities, which

involve soil disturbance, were identified for specific project components in several technical

memorandums. These include land requirements for both the regulating reservoir and pipe line

construction described in the Study of Conveyance Facilities for Year-Round Delivery of Surface Water

to Water Treatment Plants (New Mexico – Texas Aqueduct), Draft, July 1999, water treatment plant

land requirements described in the El Paso Upper Valley Water Treatment Plant Conceptual Site

Layout, June 1999, facility sites and pipe line proposed easements (temporary and permanent) in the El

Paso Aqueduct Conceptual Design, Draft Final Report, June 18, 1999, and facility sites as contained in

Concept Design of ASR Wellfield and Collection Facilities, Final Report, July 1999. A summary of soil

disturbance areas for El Paso’s portion of the El Paso – Las Cruces Regional Sustainable Water Project

is listed in Table 8.





Fuel Depots

Construction vehicle and equipment fueling requirements are based on the size of construction project,

size of construction site available, location and proximity of construction activity to existing fuel sources

and type of equipment required to perform the actual construction work. As with the construction

workforce estimates and project duration estimates, the experience of a Vice President of Bradbury

Stamm Construction, Inc., was utilized to evaluate fuel depot requirements. Numerous options were

identified, based on the specific supply requirements, for example diesel fuel versus gasoline, quantities

of supplies needed, availability of 24-hour site security, and proximity to existing independent suppliers.

The options identified are described below. Table 9 summarizes the location and type of fuel depots

anticipated for each construction project.



• On-site fuel storage – On sites where there is 24-hour security and a need for vast quantities of

fuel, fuel may be stored on site.



• Existing Facilities – Construction activities in which fuel is required on an irregular basis, such

as other than daily or several times a day, and that the equipment is mobile it may be cost

effective to purchase fuel at existing sites. In the particular case of gasoline powered equipment







22

Table 7

El Paso Construction Projects Estimated Construction Workforce by Month (construction personnel)

Resource Name 2001 2002 2003 2004 2005

SepOctNovDecJanFeb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug

UVWTP

Construction Administration Support and Labor Force UVWTP 150 150 150 150 150 150 150 150 150 150 150 150 170 170 170 300 300 300 300 300 300 300 170 170 170 150 150 150 150 150 150 150 150 150 150 150 150 0 0 0 0

New Mexico - Texas Aqueduct

Construction Administration Support New Mexico-Texas Aqueduct 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5

Construction Labor Force New Mexico-Texas Aqueduct 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25

Aquifer Storage and Recovery System

Construction Administration Support ASR Well Drilling 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

Construction Labor Force ASR Well Drilling 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24 24

Construction Administration Support ASR Well Equipment 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

Construction Labor Force ASR Well Equipment 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1 12.1

Construction Administration Support ASR Well Collector 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5

Construction Labor Force ASR Well Collector - 12"-20" 11.5 11.5 11.5 11.5 11.5

Construction Labor Force ASR Well Collector - 24"-42" 19 19 19 19 19 19 19 19 19 19 19 19

El Paso Aqueduct

Construction Administration Support Pump Stations 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4

Construction Labor Force Pump Stations 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9

Construction Administration Support UVWTP and Finished Water Reservoirs 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

Construction Labor Force UVWTP and Finished Water Reservoirs 11 11 11 11 11 11 11 11 11 11 11 11 11 11 11 11 11 11 11

Construction Administration Support Anthony Gap Summit Reservoirs 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

Construction Labor Force Anthony Gap Summit Reservoirs 11.8 11.8 11.8 11.8 11.8 11.8 11.8 11.8 11.8 11.8 11.8 11.8 11.8 11.8 11.8 11.8 11.8 11.8 11.8

Construction Administration Support UVWTP to Anthony 1A Aqueduct 5 5 5 5 5 5 5

Construction Labor Force UVTWP to Anthony 1A Aqueduct 25 25 25 25 25

Construction Administration Support UVWTP to Canutillo queduct 5 5 5 5 5 5 5 5 5

Construction Labor Force UVWTP to Canutillo Aqueduct 25 25 25 25 25 25

Construction Administration Support Anthony 1A to Anthony 2A Aqueduct 5 5 5 5 5 5 5 5 5 5

Construction Labor Force Anthony 1A to Anthony 2A Aqueduct 25 25 25 25 25 25

Construction Administration Support Anthony 2A to Anthony Gap Summit Aqueduct 5 5 5 5 5

Construction Labor Force Anthony 2A to Anthony Gap Summit Aqueduct 25 25 25 25

Construction Administration Support Anthony Gap Summit to New War Road Aqueduct 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5

Construction Labor Force Anthony Gap Summit to New War Road Aqueduct 25 25 25 25 25 25 25 25 25 25 25 25

Construction Administration Support New War Road to Loop 375 Aqueduct 5 5 5 5 5 5 5 5 5 5 5 5 5 5

Construction Labor Force New War Road to Loop 375 Aqueduct 19 19 19 19 19 19 19 19 19 19





Total Construction Personnel 2 2 2 2 4 28 28 190 190 190 190 195 195 195 195 220 220 220 220 240 240 240 370 383 383 383 415 426 426 296 301 301 289 319 319 338 343 348 353 403 379 379 409 407 226 63 38 23

Table 8

El Paso Construction Projects Environmental Surface Exposure

Disturbance Description for

El Paso Construction Area

Construction Component Area Description Projects (acres)

Upper Valley Water Treatment Plant

Conventional or Membrane Parcel IV, New Land 233

New Mexico – Texas Aqueduct

Westside Regulating Reservoir Regulating reservoir site 29

72” Transmission Line * 118,237’ x 50’ 136

Aquifer Storage and Recovery

Well Drilling and Equipment ** 71 sites @ 1-½ acres per site 106.5

Well Collector Pipe System

8” - 18” Waterline 87,188’ x 52’ 104

20” - 36” Waterline 39,521’ x 64’ 58

42” Waterline 21,483’ x 72’ 36

El Paso Aqueduct

Pump Stations and Reservoirs

Anthony 1A Site 271’ x 290’ 2

Anthony 2A Site 261’ x 270’ 2

Anthony Gap Summit Reservoirs 390’ x 225’ 2

Transmission Line, UVWTP to Canutillo *** 22,400’ x 80’ 41

Aqueduct, UVWTP to Anthony Summit ***

UVWTP to Anthony 1A 14,400’ x 80’ 26

Anthony 1A to Anthony 2A 25,000’ x 80’ 46

Anthony 2A to Anthony Gap Summit 10,800’x 80’ 20

Aqueduct, Anthony Summit to Loop 375 ***

Anthony Summit to New War Road with Connection to New War Road 47,200’ x 72’ + 600’ x 72’ 79

New War Road to Loop 375 w/Connections to Northeast and Loop 375 29,200’ x 72’ + 3,600’ x 72’ +

15,900’ x 72’ + 700’ x 72’ 82

* Total estimated construction area. Includes disturbance area of 36” pipe as joint trench installation

** 1-½ acres estimated for well drilling activities. Once complete, the permanent land required per site is

more nearly 1.0 acre, which includes 40’x50’ fenced area for well and 110’ x 100’ for blow-off pond

*** Anticipated construction zone per page 46, El Paso Aqueduct Conceptual Design, Draft Final Report









24

Table 9

Fuel Depot Requirements for El Paso Construction Projects

Construction Component Area Description Fuel Depot Description

Upper Valley Water Treatment Plant On-site fuel storage

New Mexico - Texas Aqueduct Use existing facilities plus set up one above-ground fuel storage site

Aquifer Storage and Recovery

Well Drilling and Equipment

Well Drilling Jobber service daily

Well Equipment Use existing facilities

Well Collector Pipe System Use existing facilities plus set up one above-ground fuel storage site

El Paso Aqueduct

UVWTP, Anthony 1A and 2A Pump Stations Use existing facilities

UVWTP Finished Water and El Paso Use existing facilities

Aqueduct Reservoirs

Transmission Line, UVWTP to Canutillo Use existing facilities plus set up one above-ground fuel storage site

Aqueduct UVWTP to Anthony Summit

UVWTP to Anthony 1A Use existing facilities plus set up one above-ground fuel storage site

Anthony 1A to Anthony 2A Use existing facilities plus set up one above-ground fuel storage site

Anthony 2A to Anthony Gap Summit Use existing facilities plus set up one above-ground fuel storage site

Aqueduct, Anthony Summit to Loop 375

Anthony Summit to New War Road with Use existing facilities plus set up one above-ground fuel storage site

connection to New War

New War Road to Loop 375 with Use existing facilities plus set up one above-ground fuel storage site

connections to Northeast and Loop 375



this is the preferred method of fuel storage, since non-construction vehicles also use the same

fuel.



• Jobber Service – In cases in which equipment is relatively immobile, but requires fuel on a

regular, generally daily basis, it is common to enlist the services of an independent fuel service to

provide on-site fueling of equipment.



• Combination – Many combinations of fuel service are available and applicable for certain

construction activities. Pipe line construction, for example, is a construction activity in which

gasoline driven machinery is often driven to the closest existing facilities on an as needed basis

while the excavation and backfill equipment would be serviced by the general contractor’s

service vehicles, using above ground fuel storage erected for the specific project.









25

Groundwater and NPDES Permitting

Permits are required for three main activities during the construction process for the El Paso

construction projects. A significant portion of construction activities involves groundwater dewatering

activities in the Rio Grande Valley and well development activities for the 71 ASR wells in Northeast El

Paso. Pipeline construction involves flushing and testing of nearly 83 miles of water transmission and

well collector lines. In most cases if construction related water is discharged into an arroyo or can reach

waters of the United States when discharged, a permit is required.



Dewatering Activities



Excavation in the flood plain region of the Rio Grande Valley area will require dewatering. According

to Terry McMillan, Texas Natural Resource Conservation Commission (TNRCC) Division Manager,

Region 6, Water and Wastewater Section, a discharge permit must be obtained before beginning any

dewatering operations. The permit will require the permittee to estimate the concentrations of Total

Petroleum Hydrocarbons (TPH), Total Dissolved Solids (TDS), Total Suspended Solids (TSS), pH, and

sulfate in the dewatering discharge. If any of the above constituents are determined to exceed the

allowable levels, the permit request may be denied. If the permit is denied, another method for disposal

of the water would be required, such as treating the water prior to disposal, or the method of

construction would have to be modified to eliminate the undesirable discharge constituents.



EPWU has an existing agreement with El Paso County Water Improvement District No. 1 (EPCWID

#1), dated April 11, 1997, for dewatering fees. EPCWID #1 will perform the monitoring of the

dewatering discharge. Based on communication with Ed Fifer, General Manager of EPCWID #1, TDS

will be the only constituent monitored during the construction. If the TDS concentration exceeds 1,000

ppm, EPCWID #1 will fine the contractor $0.05 per acre-foot discharged. EPCWID #1 discourages

discharges to the river, canals, or irrigation ditches. They prefer approving discharges to the agricultural

drains because that water is usually of lower quality when it comes off the irrigated fields. At this time,

EPCWID #1 is unaware of any water quality issues or discharge limits that would severely impact the

dewatering operations.



Use of Chlorinated Water or Discharge to Arroyos or Waters of the United States



Where possible, water used for testing should be reused to minimize the amount of water wasted.

Discharge of chlorinated water from flushing operations and disinfection will have to be coordinated

with the City of El Paso, if the water is discharged into its drainage and/or wastewater facilities, or with

TNRCC or New Mexico Environment Department if the water is discharged onto the ground. Discharge

into an arroyo or waters of the United States may require a National Pollution Discharge Elimination

System (NPDES) permit issued by the TNRCC/EPA for construction in Texas or by the Environment

Protection Agency (EPA) for construction in New Mexico.





26

Storm Water Discharges from Construction Activities in Region 6



A National Pollution Discharge Elimination System (NPDES) permit will be required for any

construction activity disturbing at least 5 acres, or construction activity disturbing less than 5 acres

which is part of a larger common plan of development. At least one storm water pollution prevention

plan (SWPPP) must be developed for each construction project.



Table 10 summarizes potential permit requirements for EPWU’s Construction Projects under the

El Paso – Las Cruces Regional Sustainable Water Project.





Staging Areas

Staging areas, for use by the contractor and also for use by El Paso Water Utilities and their

representatives, vary in accordance with site specific work activities. Staging area requirements for

major construction components including water treatment plant construction, well drilling and

equipment, pipeline construction and booster station construction were discussed with the Vice

President of Bradbury Stamm Construction, Inc., at the same time other phases of construction were

discussed. The reservoir construction phase activities represent a significant but separate work effort

than the aforementioned construction activities. To determine how construction for five steel on-grade

reservoirs could be accomplished under two construction contracts, PDM Water, a Division of Pitt-Des

Moines, Inc. was contacted to solicit their input concerning industry standards for this type reservoir

construction. Pitt-Des Moines, Inc., is also a member of the Engineering News-Record top 400 (93 in

1997) contractors and ranked number 5 in water supply.



The major work activities with resulting staging areas for each construction project of El Paso’s portion

of the El Paso – Las Cruces Regional Sustainable Water Project are described below:



• Program Management Activities – A multitude of concurrent construction activities will occur

over a very large area. To effectively assure construction activities are coordinated and that

problems can be addressed in a timely manner it is envisioned that Program Management trailers

will be located at two locations. One will be located on the UVWTP site, while the second

should be located at some location on the eastside of El Paso in conjunction with the construction

activities in northeast of El Paso.



• Upper Valley Water Treatment Plant – The overall site contains 233 acres. It is anticipated

that the site will be sufficient to provide equipment and supplies storage for not only the

contractor but also EPWU and their construction and program management representatives.



• Transmission Line Construction Activities - Transmission line construction activities are

expected to be contained within the anticipated construction zones areas identified earlier in this

Technical Memorandum for each project. Pipe will be transported to the general project vicinity





27

Table 10

Permitting Requirements for El Paso Construction Projects

Chlorinated Water or

Groundwater Discharge to Waters of Storm Water Pollution

Project Construction Package Discharge Permit the US Prevention Plan

Upper Valley Water Treatment Plant Site dewater √ √

New Mexico – Texas Aqueduct Partial transmission

construction zone

dewater √ √

El Paso Aqueduct

Transmission line, UVWTP to Canutillo Partial transmission

construction zone

dewater √ √

Aqueduct UVWTP to Anthony Gap

Summit

UVWTP to Anthony 1A Partial transmission

construction zone

dewater √ √

Anthony 1A to Anthony 2A √ √

Anthony 2A to Anthony Summit √ √

Aqueduct, Anthony Summit to Loop 375

Anthony Summit to New War √ √

New War to Loop 375 √ √

ASR Well Drilling and Equipment

ASR Well Drilling Discharge from well

during well

development √ √

ASR Well Equipment √ √

ASR Well Collection System Piping √ √

UVWTP Pump Station Partial dewater at

UVWTP Site √ √

Anthony 1A and 2A Pump Stations √ √

UVWTP Finished Water and El Paso

Aqueduct Reservoirs

UVWTP Finished Water Reservoirs Partial dewater √ √

Anthony 1A, 2A, Summit Reservoirs √ √









28

by truck and laid (strung) along the transmission line alignment in front of the installation crew

on an as-needed basis. Equipment such as backhoes, front-end-loaders, and compactors will be

staged along the pipeline route.



• Pump Station Construction – It is anticipated that the pump station sites will be sufficient in

size to allow storage of equipment and supplies on site. Also, EPWU and their representatives’

construction facilities will be located on each designated booster station site.



• Well Drilling and Equipment – An area comprising 1-½ acres has been set aside during the drilling

phase to accommodate the extensive equipment and drilling pits required for that construction phase

period. Well drilling activities, which include drilling equipment, fluid-recirculating pits, casing and

gravel supplies will be contained on site. Well holding pits will not be constructed until the well

casing has been set. Equipment construction activities, which include a large rig required for setting

the pump assembly and column piping, will also be contained on-site. Any construction facilities

required by EPWU or their representatives will also be contained on site. Once construction

activities have been completed, 1 acre has been set aside for each permanent well site.



• Reservoir Construction – All materials and equipment for field erection can be contained on-site.

Also, reservoir foundation work will all be contained on-site. Because of the magnitude of the two

reservoir projects reservoir steel preparation, which includes cutting and forming the steel shell and

shop priming the shells prior to erection activities will be performed at the contractor’s fabrication

plant. The fabrication site will depend on the contractor selected, but in any case the fabrication site

will not be located in the vicinity of the El Paso – Las Cruces Regional Sustainable Water Project.

Once the steel has been fabricated and shop primed, it will be transported by truck to its erection site.

This form of transportation will require loading the supplies once at the fabrication site and

unloading it once only at the erection site. If the steel were transported by rail, which is an viable

alternative in El Paso, at least one more unloading and reloading activity would be required at the

railhead. Any construction facilities required by EPWU or their representatives will be contained on

site at each individual reservoir site.









29

References









Boyle Engineering Corporation, 1995. Aquifer Storage and Recovery Investigations.



Boyle Engineering Corporation, 1997. Aquifer Storage and Recovery – Supplemental Investigations of

Recharge Basins.



Peterson, Art, 1999. Bradbury Stamm Construction, Inc., personal communications.



Marlatt, Jack, 1999. PDM Water. A Division of Pitt-Des Moines, personal communications.



EPWU, 1999. DRAFT 2025 Projected General Land Uses, Northeast Planning Area, El Paso, Texas.

Department of Planning, Research, and Development.



Hantush, M. S. and C. E. Jacob, 1955. Non-steady radial flow in an infinite leaky aquifer. Trans. Am.

Geophysical Union V 36.



Juarez, Bert, 1999. El Paso Water Utilities letter from Bert Juarez to Alan O’Brien dated March 15,

1999, with attachments.



Meyer, W.R., 1976. Digital Model for Simulated Effects of Ground-Water Pumping in the Hueco

Bolson, El Paso Area, Texas, New Mexico, and Mexico. U.S. Geological Survey WRI Report 58-75.



Orr, Brennon R. and Dennis W. Risser, 1992. Geohydrology and Potential Effects of Development of

Freshwater Resources in the Northern Part of the Hueco Bolson, Dona Ana and Otero Counties, New

Mexico. U.S. Geological Survey WRI Report 91-4082.



Sperka, Roger, 1999. El Paso Water Utilities’ personal communications.









30

APPENDIX

El Paso-Las Cruces Regional Sustainable Water Project

El Paso Water Utilities Project Design and Construction Schedule

Qtr 3, 1999 Qtr 4, 1999 Qtr 1, 2000 Qtr 2, 2000 Qtr 3, 2000 Qtr 4, 2000 Qtr 1, 2001 Qtr 2, 2001 Qtr 3, 2001 Qtr 4, 2001 Qtr 1, 2002 Qtr 2, 2002 Qtr 3, 2002 Qtr 4, 2002 Qtr 1, 2003 Qtr 2, 2003 Qtr 3, 2003 Qtr 4, 2003 Qtr 1, 2004 Qtr 2, 2004 Qtr 3, 2004 Qtr 4, 2004 Qtr 1, 2005 Qtr 2, 2005 Qtr 3, 200

ID Task Name Duration Start Finish Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug

1 NEPA Process 450d Wed 7/7/99 Mon 3/26/01



2 Preliminary EIS 30w Wed 7/7/99 Mon 1/31/00 1/31

3 Final EIS 52w Tue 2/29/00 Mon 2/26/01 2/29 2/26

4 Record of Decision 52w Tue 3/28/00 Mon 3/26/01 3/28 3/26

5 Program Management 1439d Tue 2/1/00 Fri 8/5/05



6 Program Managers 1439d Tue 2/1/00 Fri 8/5/05 2/1 8/5

7 Property Aquisition/Easements/Permitting 130w Tue 2/29/00 Mon 8/26/02 2/29 8/26

8 Upper Valley Water Treatment Plant 1360d Tue 2/1/00 Mon 4/18/05



9 Preliminary Design/ Equipment Prequalification 52w Tue 2/1/00 Mon 1/29/01 2/1 1/29

10 Preliminary Design Review 12w Tue 1/30/01 Mon 4/23/01 1/30 4/23

11 Final Design 26w Tue 4/24/01 Mon 10/22/01 4/24 10/22

12 Bid/Award 26w Tue 10/23/01 Mon 4/22/02 10/23 4/22

13 Construction 780d Tue 4/23/02 Mon 4/18/05



14 Construction Management Services 156w Tue 4/23/02 Mon 4/18/05 4/23 4/18

15 Initial Construction 52w Tue 4/23/02 Mon 4/21/03 4/23 4/21

16 Transition Construction Effort 13w Tue 4/22/03 Mon 7/21/03 4/22 7/21

17 Peak Work Effort 26w Tue 7/22/03 Mon 1/19/04 7/22 1/19

18 Transition Construction Effort 13w Tue 1/20/04 Mon 4/19/04 1/20 4/19

19 Complete Construction 52w Tue 4/20/04 Mon 4/18/05 4/20 4/18

20 New Mexico - Texas Aqueduct 1440d Mon 1/31/00 Fri 8/5/05



21 Preliminary Design 78w Mon 1/31/00 Fri 7/27/01 1/31 7/27

22 Preliminary design review 12w Mon 7/30/01 Fri 10/19/01 7/30 10/19

23 Final Design 16w Mon 10/22/01 Fri 2/8/02 10/22 2/8

24 Bid/Award Process 26w Mon 2/11/02 Fri 8/9/02 2/11 8/9

25 Construction 780d Mon 8/12/02 Fri 8/5/05



26 Construction Management Services 156w Mon 8/12/02 Fri 8/5/05 8/12 8/5

27 Construction Office Support 156w Mon 8/12/02 Fri 8/5/05 8/12 8/5

28 Actual Construction 106w Sun 12/1/02 Fri 12/10/04 12/1 12/10

29 Aquifer Storage and Recovery System 1305d Mon 8/7/00 Fri 8/5/05



30 Recovery and Injection Well Drilling/Equipmet 1250d Mon 8/7/00 Fri 5/20/05



31 Preliminary & Final Design 39w Mon 8/7/00 Fri 5/4/01 8/7 5/4

32 Well Drilling Construction 1010d Mon 5/7/01 Fri 3/18/05



33 Bid/Award Process 20w Mon 5/7/01 Fri 9/21/01 5/7 9/21

34 Construction Management Services 182w Mon 9/24/01 Fri 3/18/05 9/24 3/18

35 Construction Office Support 182w Mon 9/24/01 Fri 3/18/05 9/24 3/18

36 Actual Construction 147.07w Mon 2/11/02 Mon 12/6/04 2/11 12/6

37 Well Equipment Construction 980d Mon 8/20/01 Fri 5/20/05



38 Bid/Award Process 20w Mon 8/20/01 Fri 1/4/02 8/20 1/4

39 Construction Management Services 176w Mon 1/7/02 Fri 5/20/05 1/7 5/20

40 Construction Office Support 176w Mon 1/7/02 Fri 5/20/05 1/7 5/20

41 Actual Construction 156w Mon 4/8/02 Fri 4/1/05 4/8 4/1

42 Collection Pipeline System 795d Mon 7/22/02 Fri 8/5/05



43 Preliminary & Final Design 39w Mon 7/22/02 Fri 4/18/03 7/22 4/18

44 Bid/Award Process 16w Mon 4/21/03 Fri 8/8/03 4/21 8/8

45 Construction 520d Mon 8/11/03 Fri 8/5/05



46 Construction Management Services 104w Mon 8/11/03 Fri 8/5/05 8/11 8/5

47 Construction Office Support 104w Mon 8/11/03 Fri 8/5/05 8/11 8/5

48 Actual Construction 12"-20" pipe 20w Mon 12/1/03 Fri 4/16/04 12/1 4/16

49 Actual Construction 24"-42" pipe 52w Mon 5/3/04 Fri 4/29/05 5/3 4/29

50 El Paso Aqueduct 990d Mon 10/22/01 Fri 8/5/05



51 Pump Stations 920d Mon 1/28/02 Fri 8/5/05



52 Preliminary Design 32w Mon 1/28/02 Fri 9/6/02 1/28 9/6

53 Preliminary Design Review 12w Mon 9/9/02 Fri 11/29/02 9/9 11/29

54 Final Design 16w Mon 12/2/02 Fri 3/21/03 12/2 3/21

55 Bid/Award Process 20w Mon 3/24/03 Fri 8/8/03 3/24 8/8

56 Construction 520d Mon 8/11/03 Fri 8/5/05



57 Construction Management Services 104w Mon 8/11/03 Fri 8/5/05 8/11 8/5

58 Construction Office Support 104w Mon 8/11/03 Fri 8/5/05 8/11 8/5

59 Actual Construction 78w Tue 11/4/03 Mon 5/2/05 11/4 5/2

60 UVWTP Finished Water and El Paso Aqueduct Reservoirs 750d Mon 9/23/02 Fri 8/5/05



61 Preliminary & Final Design 26w Mon 9/23/02 Fri 3/21/03 9/23 3/21

62 Construction, UVWTP Finished Water Reservoirs 620d Mon 3/24/03 Fri 8/5/05



63 Bid/Award Process 20w Mon 3/24/03 Fri 8/8/03 3/24 8/8

64 Construction Management Services 104w Mon 8/11/03 Fri 8/5/05 8/11 8/5

65 Construction Office Support 104w Mon 8/11/03 Fri 8/5/05 8/11 8/5

66 Actual Construction 78w Tue 11/18/03 Mon 5/16/05 11/18 5/16

67 Construction, Anthony Gap Summit Reservoirs 620d Mon 3/24/03 Fri 8/5/05



68 Bid/Award Process 20w Mon 3/24/03 Fri 8/8/03 3/24 8/8

69 Construction Management Services 104w Mon 8/11/03 Fri 8/5/05 8/11 8/5

70 Construction Office Support 104w Mon 8/11/03 Fri 8/5/05 8/11 8/5

71 Actual Construction 78w Tue 11/4/03 Mon 5/2/05 11/4 5/2

72 Pipeline between UVWTP and Anthony Gap Summit 859d Wed 4/3/02 Mon 7/18/05



73 Preliminary Design 78w Wed 4/3/02 Tue 9/30/03 4/3 9/30

74 Preliminary Review 12w Wed 10/1/03 Tue 12/23/03 10/1 12/23

75 Final Design 16w Wed 12/24/03 Tue 4/13/04 12/24 4/13

76 Construction Between UVWTP and Anthony 1A 249d Wed 5/26/04 Mon 5/9/05



77 Bid/Award Process 20w Wed 5/26/04 Tue 10/12/04 5/26 10/12

78 Construction Management Services 26w Tue 11/9/04 Mon 5/9/05 11/9 5/9

79 Construction Office Support 26w Tue 11/9/04 Mon 5/9/05 11/9 5/9

80 Actual Construction 15w Tue 1/18/05 Mon 5/2/05 1/18 5/2

81 Construction Between UVWTP and Canutillo 284d Wed 4/14/04 Mon 5/16/05



82 Bid/Award Process 20w Wed 4/14/04 Tue 8/31/04 4/14 8/31

83 Construction Management Services 34w Tue 9/21/04 Mon 5/16/05 9/21 5/16

84 Construction Office Support 34w Tue 9/21/04 Mon 5/16/05 9/21 5/16

85 Actual Construction 22w Tue 12/14/04 Mon 5/16/05 12/14 5/16

86 Construction Between Anthony 1A and Anthony 2A 324d Wed 4/14/04 Mon 7/11/05



87 Bid/Award Process 20w Wed 4/14/04 Tue 8/31/04 4/14 8/31

88 Construction Management Services 39w Wed 9/1/04 Tue 5/31/05 9/1 5/31

89 Construction Office Support 39w Tue 10/12/04 Mon 7/11/05 10/12 7/11

90 Actual Construction 25w Tue 12/7/04 Mon 5/30/05 12/7 5/30

91 Construction Between Anthony 2A and Anthony Gap Summit 229d Wed 9/1/04 Mon 7/18/05



92 Bid/Award Process 20w Wed 9/1/04 Tue 1/18/05 9/1 1/18

93 Construction Management Services 20w Tue 3/1/05 Mon 7/18/05 3/1 7/18

94 Construction Office Support 20w Tue 3/1/05 Mon 7/18/05 3/1 7/18

95 Actual Construction 11w Tue 3/29/05 Mon 6/13/05 3/29 6/13

96 Pipeline Between Anthony Gap Summit and Loop 375 Facilities 990d Mon 10/22/01 Fri 8/5/05



97 Preliminary Design 78w Mon 10/22/01 Fri 4/18/03 10/22 4/18

98 Preliminary Review 16w Mon 4/21/03 Fri 8/8/03 4/21 8/8

99 Final Design 16w Mon 8/11/03 Fri 11/28/03 8/11 11/28

100 Construction Between Anthony Gap and New War Road 440d Mon 12/1/03 Fri 8/5/05



101 Bid/Award Process 16w Mon 12/1/03 Fri 3/19/04 12/1 3/19

102 Construction Management Services 72w Mon 3/22/04 Fri 8/5/05 3/22 8/5

103 Construction Office Support 72w Mon 3/22/04 Fri 8/5/05 3/22 8/5

104 Actual Construction 48w Tue 6/15/04 Mon 5/16/05 6/15 5/16

105 Construction Between New War Road and Loop 375 Facilities 422.64d Mon 12/1/03 Wed 7/13/05



106 Bid/Award Process 16w Mon 12/1/03 Fri 3/19/04 12/1 3/19

107 Construction Management Services 56w Wed 6/16/04 Wed 7/13/05 6/16 7/13

108 Construction Office Support 56w Wed 6/16/04 Wed 7/13/05 6/16 7/13

109 Actual Construction 39.67w Wed 8/11/04 Mon 5/16/05 8/11 5/16

El Paso-Las Cruces Regional Sustainable Water Project

New Mexico Entities Project Design and Construction Schedule

Qtr 3, 1999 Qtr 4, 1999 Qtr 1, 2000 Qtr 2, 2000 Qtr 3, 2000 Qtr 4, 2000 Qtr 1, 2001 Qtr 2, 2001 Qtr 3, 2001 Qtr 4, 2001 Qtr 1, 2002 Qtr 2, 2002 Qtr 3, 2002 Qtr 4, 2002 Qtr 1, 2003 Qtr 2, 2003 Qtr 3, 2003 Qtr 4, 2003 Qtr 1, 2004 Qtr 2, 2004 Qtr 3, 2004 Qtr 4, 2004 Qtr 1, 2005 Qtr 2, 2005 Qtr 3, 2005 Qtr 4, 2005 Qtr 1, 2006 Qtr 2, 2006 Qtr 3, 2006 Qtr 4, 2006 Qtr 1, 2007 Qtr 2, 2007 Qtr 3, 2007 Qtr 4, 2007 Qtr 1, 2008 Qtr 2, 2008 Qtr 3, 2008

ID Task Name Duration Start Finish Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

1 NEPA PROCESS 450d Tue 7/6/99 Mon 3/26/01



2 Preliminary EIS 30w Tue 7/6/99 Mon 1/31/00 1/31

3 Final EIS 52w Tue 2/29/00 Mon 2/26/01 2/29 2/26

4 Record of Decision 52w Tue 3/28/00 Mon 3/26/01 3/28 3/26

5 HATCH AREA TREATMENT PLANT 522d Mon 1/1/01 Tue 12/31/02



6 Property Acquisition/Easements/Permitting 61d Mon 1/1/01 Mon 3/26/01 1/1 3/26

7 Preliminary Design/Equipment Prequalification 156d Mon 1/1/01 Mon 8/6/01 1/1 8/6

8 Preliminary Design Review 3w Tue 8/7/01 Mon 8/27/01 8/7 8/27

9 Final Design 10w Tue 8/28/01 Mon 11/5/01 8/28 11/5

10 Bid/Award 8w Tue 11/6/01 Mon 12/31/01 11/6 12/31

11 Construction 261d Tue 1/1/02 Tue 12/31/02



12 Construction Management Services 261d Tue 1/1/02 Tue 12/31/02 1/1 12/31

13 Initial Construction 54d Tue 1/1/02 Fri 3/15/02 1/1 3/15

14 Transition Construction Effort 42d Mon 3/18/02 Tue 5/14/02 3/18 5/14

15 Peak Work Effort 67d Wed 5/15/02 Thu 8/15/02 5/15 8/15

16 Transition Construction Effort 55d Fri 8/16/02 Thu 10/31/02 8/16 10/31

17 Complete Construction 43d Fri 11/1/02 Tue 12/31/02 11/1 12/31

18 HATCH AREA DIVERSION 522d Mon 1/1/01 Tue 12/31/02



19 Property Acquisition/Easements/Permitting 90d Mon 1/1/01 Fri 5/4/01 1/1 5/4

20 Preliminary Design 150d Tue 8/7/01 Mon 3/4/02 8/7 3/4

21 Preliminary Design Review 45d Tue 3/5/02 Mon 5/6/02 3/5 5/6

22 Final Design 45d Tue 5/7/02 Mon 7/8/02 5/7 7/8

23 Bid/Award 60d Tue 7/9/02 Mon 9/30/02 7/9 9/30

24 Construction 66d Tue 10/1/02 Tue 12/31/02



25 Construction Management Services 66d Tue 10/1/02 Tue 12/31/02 10/1 12/31

26 Construction Office Support 66d Tue 10/1/02 Tue 12/31/02 10/1 12/31

27 Actual Construction 66d Tue 10/1/02 Tue 12/31/02 10/1 12/31

28 HATCH AREA TRANSMISSION LINES 522d Mon 1/1/01 Tue 12/31/02



29 Property Acquisition/Easements/Permitting 90d Mon 1/1/01 Fri 5/4/01 1/1 5/4

30 Preliminary Design 180d Thu 4/12/01 Wed 12/19/01 4/12 12/19

31 Preliminary Design Review 45d Thu 12/20/01 Wed 2/20/02 12/20 2/20

32 Final Design 71d Fri 3/1/02 Fri 6/7/02 3/1 6/7

33 Bid/Award 60d Mon 6/10/02 Fri 8/30/02 6/10 8/30

34 Construction 87d Mon 9/2/02 Tue 12/31/02



35 Construction Management Services 87d Mon 9/2/02 Tue 12/31/02 9/2 12/31

36 Construction Office Support 87d Mon 9/2/02 Tue 12/31/02 9/2 12/31

37 Actual Construction 87d Mon 9/2/02 Tue 12/31/02 9/2 12/31

38 LAS CRUCES AREA TREATMENT PLANT 758d Tue 11/1/05 Thu 9/25/08



39 Property Acquisition/Easements/Permitting 61d Tue 11/1/05 Tue 1/24/06 11/1 1/24

40 Preliminary Design/Equipment Prequalification 31.2w Tue 11/1/05 Tue 6/6/06 11/1 6/6

41 Preliminary Design Review 3w Wed 6/7/06 Tue 6/27/06 6/7 6/27

42 Final Design 10w Wed 6/28/06 Tue 9/5/06 6/28 9/5

43 Bid/Award 8w Wed 9/6/06 Tue 10/31/06 9/6 10/31

44 Construction 497d Wed 11/1/06 Thu 9/25/08



45 Construction Management Services 497d Wed 11/1/06 Thu 9/25/08 11/1

46 Initial Construction 129d Wed 11/1/06 Mon 4/30/07 11/1 4/30

47 Transition Construction Effort 54d Tue 5/1/07 Sun 7/15/07 5/1 7/15

48 Peak Work Effort 132d Mon 7/16/07 Tue 1/15/08 7/16 1/15

49 Transition Construction Effort 54d Wed 1/16/08 Mon 3/31/08 1/16 3/31

50 Complete Construction 128d Tue 4/1/08 Thu 9/25/08 4/1

51 LAS CRUCES AREA DIVERSION 758d Tue 11/1/05 Thu 9/25/08



52 Property Acquisition/Easements/Permitting 60d Tue 11/1/05 Mon 1/23/06 11/1 1/23

53 Preliminary Design 150d Mon 4/9/07 Fri 11/2/07 4/9 11/2

54 Preliminary Design Review 45d Mon 11/5/07 Fri 1/4/08 11/5 1/4

55 Final Design 45d Mon 1/7/08 Fri 3/7/08 1/7 3/7

56 Bid/Award 60d Mon 3/10/08 Fri 5/30/08 3/10 5/30

57 Construction 84d Mon 6/2/08 Thu 9/25/08



58 Construction Management Services 84d Mon 6/2/08 Thu 9/25/08 6/2

59 Construction Office Support 84d Mon 6/2/08 Thu 9/25/08 6/2

60 Actual Construction 84d Mon 6/2/08 Thu 9/25/08 6/2

61 LAS CRUCES AREA TRANSMISSION LINES 758d Tue 11/1/05 Thu 9/25/08



62 Property Acquisition/Easements/Permitting 60d Tue 11/1/05 Mon 1/23/06 11/1 1/23

63 Preliminary Design 210d Fri 9/8/06 Thu 6/28/07 9/8 6/28

64 Preliminary Design Review 45d Fri 6/29/07 Thu 8/30/07 6/29 8/30

65 Final Design 71d Fri 8/31/07 Fri 12/7/07 8/31 12/7

66 Bid/Award 60d Mon 12/10/07 Fri 2/29/08 12/10 2/29

67 Construction 149d Mon 3/3/08 Thu 9/25/08



68 Construction Management Services 149d Mon 3/3/08 Thu 9/25/08 3/3

69 Construction Office Support 149d Mon 3/3/08 Thu 9/25/08 3/3

70 Actual Construction 149d Mon 3/3/08 Thu 9/25/08 3/3

71 ANTHONY AREA TREATMENT PLANT 564d Wed 1/1/03 Mon 2/28/05



72 Property Acquisition/Easements/Permitting 61d Wed 1/1/03 Wed 3/26/03 1/1 3/26

73 Preliminary Design/Equipment Prequalification 31.2w Wed 1/1/03 Wed 8/6/03 1/1 8/6

74 Preliminary Design Review 3w Thu 8/7/03 Wed 8/27/03 8/7 8/27

75 Final Design 10w Thu 8/28/03 Wed 11/5/03 8/28 11/5

76 Bid/Award 8w Thu 11/6/03 Wed 12/31/03 11/6 12/31

77 Construction 303d Thu 1/1/04 Mon 2/28/05



78 Construction Management Services 303d Thu 1/1/04 Mon 2/28/05 1/1 2/28

79 Initial Construction 65d Thu 1/1/04 Wed 3/31/04 1/1 3/31

80 Transition Construction Effort 43d Thu 4/1/04 Mon 5/31/04 4/1 5/31

81 Peak Work Effort 88d Tue 6/1/04 Thu 9/30/04 6/1 9/30

82 Transition Construction Effort 43d Fri 10/1/04 Tue 11/30/04 10/1 11/30

83 Complete Construction 64d Wed 12/1/04 Mon 2/28/05 12/1 2/28

84 ANTHONY AREA DIVERSION 564d Wed 1/1/03 Mon 2/28/05



85 Property Acquisition/Easements/Permitting 90d Wed 1/1/03 Tue 5/6/03 1/1 5/6

86 Preliminary Design 150d Mon 9/8/03 Sun 4/4/04 9/8 4/4

87 Preliminary Design Review 45d Mon 4/5/04 Sun 6/6/04 4/5 6/6

88 Final Design 45d Wed 7/7/04 Tue 9/7/04 7/7 9/7

89 Bid/Award 60d Wed 9/8/04 Tue 11/30/04 9/8 11/30

90 Construction 64d Wed 12/1/04 Mon 2/28/05



91 Construction Management Services 64d Wed 12/1/04 Mon 2/28/05 12/1 2/28

92 Construction Office Support 64d Wed 12/1/04 Mon 2/28/05 12/1 2/28

93 Actual Construction 64d Wed 12/1/04 Mon 2/28/05 12/1 2/28

94 ANTHONY AREA TRANSMISSION LINES 564d Wed 1/1/03 Mon 2/28/05



95 Property Acquisition/Easements/Permitting 72d Wed 1/1/03 Thu 4/10/03 1/1 4/10

96 Preliminary Design 211d Fri 4/11/03 Fri 1/30/04 4/11 1/30

97 Preliminary Design Review 43d Mon 2/2/04 Wed 3/31/04 2/2 3/31

98 Final Design 71d Thu 4/1/04 Thu 7/8/04 4/1 7/8

99 Bid/Award 60d Fri 7/9/04 Thu 9/30/04 7/9 9/30

100 Construction 107d Fri 10/1/04 Mon 2/28/05



101 Construction Management Services 107d Fri 10/1/04 Mon 2/28/05 10/1 2/28

102 Construction Office Support 107d Fri 10/1/04 Mon 2/28/05 10/1 2/28

103 Actual Construction 107d Fri 10/1/04 Mon 2/28/05 10/1 2/28



Related docs
Other docs by cuiliqing
7 Recipes from Joe A.
Views: 0  |  Downloads: 0
Re-installingXPMode
Views: 0  |  Downloads: 0
telefonica_en
Views: 0  |  Downloads: 0
3220 Chap 6 demos
Views: 0  |  Downloads: 0
chap history.docx
Views: 1  |  Downloads: 0
Subcontractor Bid Form - The Fountains
Views: 0  |  Downloads: 0
English
Views: 0  |  Downloads: 0
DESIGNER'S SCHEDULE USE
Views: 0  |  Downloads: 0
Security Service Providers
Views: 44  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!