									      HEBEL AUTOCLAVED AERATED CONCRETE STRUCTURAL
      FLOOR PANELS.
1.    GENERAL

1.1   DOCUMENTS
      Documents generally relating to in this section are:

      NZS 3103            Sands for mortars and plasters
      NZS 3109            Concrete construction

      There are no New Zealand Standards that relate to Autoclaved Aerated Concrete (AAC)
      specifically.

1.2   MANUFACTURER’S DOCUMENTS
      Manufacturers’ and supplier’s documents relating to work in this section are:
      CSR Hebel Technical Handbook.
      Lightweight Concrete NZ Ltd. Hebel Structural Floor Panels.
      Copies of the manufacturers literature are available by phoning Lightweight Concrete NZ
      Ltd~ (03) 455 1502

1.3   QUALIFICATIONS
      Carry out all installation of the precast concrete panels with people competent and
      experienced in this type of work, No specific AAC qualifications are required, however the
      contractors shall have had instruction and training from Trained Hebel Instructors and/ or
      other experienced Hebel installers. All personnel operating cranes shall hold the
      appropriate certification.

1.4   INSPECTION
      Call for inspection of the work at critical stages including set out of reinforcing starters,
      completion of panel and reinforcing placement at the time prior to and during grouting.
      The design engineer or his nominated representative will certify that the steelwork is
      placed in accordance with the design.

2.    PRODUCTS

2.1   FLOOR PANELS
      Brand                             ~CSR Hebel
      Width                             ~ 600mm may be site or factory cut to 300mm minimum
      Thickness                         ~200mm generally (150, 175, 225, 250mm also available)
      Edge profile                      ~Bevelled rebate and groove ring anchor

2.2   REINFORCEMENT- RING ANCHOR STEEL
      D12 steel reinforcing shall be site placed in the Ring Anchor groove and around any bond
      beam requirements, as per Engineer specification.

2.3   THICK BED MORTAR (FOR LEVELING THE PANELS ONLY)
      Use the Brighton Drymix pre-batched mortar supplied. If extra site mixed mortar is
      needed use a 6:1:1 mix (sand to NZS 3103). Chloride levels to not exceed 0.04% by dry
      weight of sand. Compressive strength shall be not less than 12.5 Mpa. Mortar is for
      levelling any slab irregularities.

2.4   GROUT FOR RING ANCHOR GROOVES
      Sand /cement mix. Spread value 450 - 530mm.
      Maximum aggregate size 6mm
      Design strength- 15 MPa at 28 days.

2.5   WATER
      Clean, fresh and free from excess alkali, salt, silt and organic materials. Water from a
      local authority water supply is acceptable.




                                          Hebel Autoclaved Aerated Concrete Structural Floor Panels…. Page 1
2.6    DAMPPROOFING
       Any Hebel Wall Panels seated upon conventional concrete must have a Bituminous damp
       proof course membrane, such as Bitumac Malthoid DPC placed between the two types of
       concrete to act as a slip joint and allow for differential movement, including drying
       shrinkage. Lay the DPC over the foundation, to the perimeter and along the lines of all
       internal walls. Neatly cut around all starters. The DPC creates a slip joint and also
       provides a moisture barrier to protect the Hebel panels from dampness. As such, the roll
       of DPC should be the same width as the wall thickness.

3.     EXECUTION

3.1    STORAGE
       Store all panels clear of the ground, under cover (plastic wrapping) and well ventilated
       until placed in the work.

3.2    MOISTURE CONTENT
       Ensure that the Hebel Panels are air dry prior to placing. Excessive moisture at the joints
       may not allow the adhesive to bond correctly.

3.3    CHECK BASE CONCRETE
       Ensure the supporting base concrete is true to line and level, requiring a base mortar bed
       of 10mm (minimum) to 20mm (maximum). The Thick Bed Mortar is laid over the DPC
       and is used to level the first run of floor panels, if required.

3.4    PROPPING
       Floor panels shall be propped at mid span on wind-up adjustable props. Place a support
       board 200x50 or similar under the panels with propping at 2 metre centres. Use the prop
       winder to ensure a level floor surface, prior to grouting the ring anchor.

3.5    COVER
       Reinforcing rods should be located centrally within the grout of the ring anchor

3.6    TOLERANCES
       Refer to Engineers notes for acceptable dimensional tolerances

3.7    PANEL LIFTING AND PLACING
       Use the CSR HEBEL floor panel cradle attached to a crane to lift and place floor panels
       horizontally. Instruction in the use of this attachment will be provided by the panel
       supplier.

3.8    PRE-GROUTING INSPECTION
       The engineer and Hebel distributor shall Inspect the ring anchor reinforcement prior to
       grouting. Ensure grooves have been cleared of all Hebel debris and that grout can flow
       freely around the rods

3.9    GROUTING OF FLOOR PANEL RING ANCHOR GROOVES
       Use a sand/cement grout. All D12 reinforcing in the ring anchor should be supported on
       lumps of concrete to ensure that they remain centrally located in the groove while
       grouting. Apply grout with a hand trowel and slightly over fill. Once initial shrinkage has
       taken place, scrape the grout flush with the panel surface. Alternatively, fill flush with the
       floor surface and allow shrinkage to dish the grout. Then skim render with Hebel High
       Build Render over the shrunk back grout.

3.10   REMOVAL OF MATERIALS
       Remove from the site materials not used. Excess stock delivered to the site belongs to
       the Hebel supplier as per the supply contract. Dispose of all cut & damaged panel and
       block.




                                          Hebel Autoclaved Aerated Concrete Structural Floor Panels…. Page 2

								