ID Risk Item Effect Cause Likelihood







What is the effect on any

or all of the project

deliverables if the cause What are the possible

Describe the risk briefly actually happens? cause(s) of this risk?

Unplanned issue,

Goal of lower cost is not unresearched, over-

1 Product over budget met designing parts 2



Product does not have

enough functional A requirement goes Run out of time, over

2 improvements unmet looking planned items 1



Under-designed parts,

Cracks and Fractures Durability is unforeseen weather

during use of well compromised, may injure conditions, unrecognized

3 maintained system user forces on system 1





Weakening of parts, Removal of paint, Strain

Significant corrosion Moving parts have higher from bending, unforeseen

4 occurs friction (sticking) weather conditions 1



Design is difficult to unintelligent part design,

manufacture and Late project, Parts need uninformed of tools

5 assemble redesign available at hand 1

Assembly does not line Errors in measuring, Bad

up, does not fit boat, design practices,

Does not improve Dimensioning parts

6 Modeling / GD&T flaws functionality incorrectly 2



Higher cost, Missing part -

need to redesign system

to work without it, parts Lack of knowledge, Using

Uncommon part is hard are harder to replace "in old design (assuming

7 to find the field" parts are still on market) 1

Durability of system is

compromised, Injure to Under-Designed parts,

user, Failure to achieve using incorrect materials,

8 Fragile part breaks requirements unforeseen forces 1

Need to redesign parts

Prototype breaks during for system, Use alternate Forcing parts to fit,

manufacturing, assembly, manufacturing method or Incorrect dimensions, non-

9 and testing phase material uniform materials 1

Fail durability

Prototype fails due to use requirement, Possible Incorrect use, wear over

10 abuse injure to user time 1

Order parts late, send

incorrect prints, Order

incorrect part, vendor

11 Parts arrive late Don't meet deadlines failure 2





Don't meet deadlines, We order parts

Wrong parts are Must alter design to fit incorrectly, Vendor

12 delivered parts failure 1



Don't deliver what we

promise, Deliver

differently from what we

Fail design requirement, promise, do not listen to

13 Dissatisfied stakeholders Must redesign system customer suggestions 1



Bad group dynamic,

Incomplete assignments, Personal disagreements,

Lack of communication Non-rational decisions Bad work ethics, Project

14 within team changing the project disagreements 2



Incorrect decisions, lack

of communication,

Inner team conflict on disagreements, bad work conflicting opinions,

15 design decision ethic different past experiences 2

conflicting opinions,

Incorrect decisions, lack different past

of communication, experiences, external

Inner team conflict due disagreements, bad work disagreements,

16 to personal reasons ethic scheduling conflicts 1

Loss of manpower, loss of

Team member/s is/are skill in an area, Loss of

17 incapacitated ideas Sick, death, drop out, etc 1

Fail to meet goals, loss of

reliability,

Team member/s does Communication Bad work ethic, Issues in

not complete distribution breakdown, Personal design arise, Out of class

18 of their work conflicts arise issues, 1

Project falls behind Fail to meet time Late parts, Slow design,

19 schedule requirment Lack of commitment 2





Late parts, Slow design,

Fail to meet time Lack of commitment,

20 Team runs out of time requirment failure to pick up slack 1

Importanc

Severity e Action to Minimize Risk Plan B Owner



What action(s) will you

take (and by when) to

prevent, reduce the What action(s) could you Who is responsible for

impact of, or transfer the take if original mitigation following through on

L*S risk of this occurring? plans fail? mitigation?

Reduce cost by seeking Reduce price by scaling

lower priced alternative back level of expensive

2 4 parts improvements Whole Team

Keep track of planned

improvements, all Plan for possible

deliverables addressed at additional improvements

3 3 each stage in project made if time is available Whole Team



Be sure to analyze all

forces and members, give

user instructions for well- Have customer sign

3 3 being of system waiver Whole Team



Use corosion resistant

materials (i.e. aluminum), Instruct customer system

appropriately coat and must be cleaned after

2 2 protect steel each use Whole Team



Check with shop on tool last effort - try other

selection, get specialist to shops on campus to see if

3 3 advise our parts they can help Whole Team



Redesign part to fit

Remeasure parts while system better than

3 6 creating prints originally planend Whole Team



Check current market for

all planned parts, Raise Include alternate designs

the question of customer for if part needs to be

purchasing spare parts replaced with different

2 2 now part in future Whole Team

Check material

brittleness, keep stress

values at required

3 3 amounts Reinforce part Whole Team

Design with factor of

safety, Do not rush

assembly, Practice

manufacturing step on

3 3 scrap material Remake part Whole Team



Design with factor of Instruct user on potential

2 2 safety bad practices Whole Team



Order parts early, Double Use alternative parts to

check prints for correct meet deadline, then swap

3 6 dimensions in better parts late Whole Team



Order parts early to build

in time to reorder, double

check with vendor on Alter design to make

3 3 parts are coming parts work Whole Team

Be sure to follow up and

make sure customer

approves our design,

Follow our designs

according to what was Fix what is not liked by

3 3 agreed upon customer Whole Team





Compromise, Know that Get it done, Out-of-

the customer is always project time (team

3 6 right building) Whole Team





Compromise, Know that Get it done, Out-of-

the customer is always project time (team

3 6 right building) Whole Team



Keep professional, Deal

with coworkers like a real Get it done, Out-of-

job, Do more work on project time (team

3 3 own time building) Whole Team



Trim project scope down,

3 3 Request a new member Put in more time/ effort Whole Team



Confront team member, Get work done for said

Bring issue to adviser, team member, assess

Lessen work load on situation after work is

3 3 member done Whole Team

Work down time into Extra work time, rush

schedule, Weekly status manufacturing, Pick up

meeting, Keep slack through another

2 4 assignments short member Whole Team

Work down time into

schedule, Weekly status

meeting, Keep

assignments short, Work

3 3 "overtime" Conference with adviser Whole Team


Shared by: xiaohuicaicai
Other docs by xiaohuicaicai
LOGFRAMES_ MONITORING AND EVALUATION
Views: 0  |  Downloads: 0
JELSApndx3SophLanguage
Views: 0  |  Downloads: 0
1997TrumpetCompetitionNYTimes
Views: 0  |  Downloads: 0
Eng_wk52_31
Views: 0  |  Downloads: 0
ENVIRONMENTAL MONITORING PROGRAMME FOR
Views: 0  |  Downloads: 0
Marketing - Ulster Business School
Views: 0  |  Downloads: 0
speech-swallowing
Views: 1  |  Downloads: 0
May_FY11_Awards_Report_Web
Views: 0  |  Downloads: 0
Related docs
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!