					1. Project Title:                  Belle - II
2. WBS element No.:                1.3
3. WBS Owner:                      G. Varner - University of Hawaii
4. WBS Element Title:              Readout Systems
5. Task/Element Description:       Provide general scope statement of the WBS.
                               --> Design, prototype, fabrication, test, integration and assembly into final detector readout modules of high-
                                   performance, waveform-sampling (WFS) ASIC-based readout.




10/27/2011                                                   WBS Description                                                           1 of 20
A. Technical Objective
                            A statement of project objectives and goals is needed to clearly and concisely translate project mission and
                            expectations into corresponding project commitments and deliverables. Objectives are statements that describe
                            what this WBS will achieve and deliver. Objectives should be “SMART”: S pecific, M easurable, A chievable,
                            R ealistic, and T ime-Based. To be specific and tangible, objectives should be deliverable-based. The completion
                            of an objective should be evident through the creation of one or more deliverables. If the statement is at a high
                            level and does not imply the creation of a deliverable, it may be a goal instead. If the statement is too low-level and
                            describes features and functions, then it may be a requirement statement instead.


                         --> First generation R&D prototypes of iTOP, KLM, and beam monitoring readout have been produced. The remaining
                             R&D/prototyping work consists of 2 more phases. In Rev. B, the final form-factors of the readout PCBs and ASICs
                             will be fabricated and evaluated. In Rev. C, pre-production prototypes will be assembled, using candidate final
                             versions of all commercial and custom components, and evaluated versus all final engineering specifications.
                             Successful completion of Phase C prototyping is necessary prior to commitment for production fabrication. Due to
                             the use of Ball Grid Array and other difficult to assemble parts (for space reasons), all production boards will be
                             assembled in industry and checked/debugged at Belle II member institute laboratories. Subcomponents will be
                             individually tested and characterized prior to integration into Sub-detector Readout Modules (SRMs). SRMs are the
                             units that are directly integrated with opto-detector front-ends to form the (iTOP or eKLM) detector instrumentation.
                             Integration of the SRMs and backend readout (FINESSE/COPPER) into fully-assembled detector sub-modules,
                             wherein cosmic ray calibration data can be taken completes this WBS element.
                             First generation R&D prototypes of iTOP, KLM, and beam monitoring readout have been produced. The remaining
                             R&D/prototyping work consists of 2 more phases. In Rev. B, more refined readout PCBs and ASICs will be
                             fabricated and evaluated. In Rev. C, pre-production prototypes will be assembled, using candidate final versions of
                             all commercial and custom components, and evaluated versus all final engineering specifications.
                             Successful completion of Phase C prototyping is necessary prior to commitment for production fabrication. Due to
                             the use of Ball Grid Array and other difficult to assemble parts (for space reasons), all production boards will be




10/27/2011                                                       A. Tech Objective                                                           2 of 20
B. Assumptions        Project assumptions are circumstances and events that need to occur for the project to be successful but are
                      outside the total control of the project team. They are listed as assumptions if there is a HIGH probability that they
                      will in fact happen. The assumptions provide a historical perspective when evaluating project performance and
                      determining justification for project-related decisions and direction.

                      In order to identify and estimate the required tasks and timing for the project, certain assumptions and premises
                      need to be made. Based on the current knowledge today, the project assumptions are listed below. If an
                      assumption is invalidated at a later date, then the activities and estimates in the project plan should be adjusted
                      accordingly

                  1   Funding for needed manpower will not limit provided schedule.
                  2   ASIC foundries will maintain a consistent production schedule.
                  3   Beam monitoring schedule depends on test beam availability.
                  4   Estimates for electromechanical development depend upon maintaining current detector envelope.
                  5
                  6
                  7
                  8
                  9
                 10




10/27/2011                                                 B. Assumption(s)                                                            3 of 20
C. Scope of Work Statement
                              In this section, you should clearly define the logical boundaries of the WBS element. Scope statements are used to
                              define what is within the boundaries of the project and what is outside those boundaries. Examples of areas that could
                              be examined include: facility design, construction, readiness assessment/startup, staff & equipment transition, etc. The
                              following types of information can be helpful:

                              • The types of deliverables that are in scope and out of scope (program requirements, current state assessment)
                              • The major life-cycle processes that are in scope and out of scope (analysis, design, testing)
                              • The types of data that are in scope and out of scope (quantity of work, performance criteria, safety and security
                              requirements)
                              • The data sources that are in scope and out of scope (labor, subcontract, travel, materials)
                              • The organizations that are in scope and out of scope ( support organizations, R&D organizations, DOE, state &
                              federal regulators)
                              • The major functionality that is in scope and out of scope (decision support, data entry, management reporting)

                              The scope section may be broken into parts dependent on the size and complexity of the scope.




                         WBS
                        1.3.01 Development (iTOP)
                           --> Finalize specifications for production boards being fabricated in iTOP WBS elements, 1.3.04. Does not include
                               development of KLM or beam monitoring systems, WBS 1.3.05-1.3.07. First generation R&D prototypes of iTOP
                               readout have been produced. The remaining R&D/prototyping work consists of 2 more phases. In Rev. B, fully
                               functional readout PCBs and ASICs will be fabricated and evaluated in cosmic and beam tests. In Rev. C, pre-
                               production prototypes will be assembled, using candidate final versions of all commercial and custom components, and
                               evaluated versus all final engineering specifications.
                               Successful completion of Phase C prototyping is necessary prior to commitment for production fabrication. Due to the
                               use of Ball Grid Array and other difficult to assemble parts (for space reasons), all production boards will be assembled
                               in industry and checked/debugged at Belle II member institute laboratories. Subcomponents will be individually tested
                               and characterized prior to integration into Sub-detector Readout Modules (SRMs). SRMs are the units that are directly
                               integrated with opto-detector front-ends to form the iTOP detector instrumentation.
                               Integration of the SRMs and backend readout (FINESSE/COPPER) into fully-assembled detector sub-modules, wherein
                               Cosmic ray and beam test can be taken completes this and element.
                      1.3.01.1 cosmic ray calibration data (1/16th system): ConstructionWBS integration of a full bar readout
                    1.3.01.1.1 Electromechanical design and engineering
                    1.3.01.1.2 HV board : PMT high voltage distribution
                    1.3.01.1.3 Front board: PMT-to-ASIC electromechanical interface
                    1.3.01.1.4 ASIC carrier: daughter card signal distribution interface for 4x ASIC daughter cards
                    1.3.01.1.5 BLAB3A (first revision ASIC) daughter card: single ASIC and services


10/27/2011                                                        C. Scope of Work                                                                  4 of 20
              1.3.01.1.6   Interface board: power regulation and clock jitter cleaning
              1.3.01.1.7   SCROD control and data collection module
              1.3.01.1.8   cPCI_DSP: Back-end data receiver and fast feature extraction module
              1.3.01.1.9   Prototype clock and JTAG programming distribution
             1.3.01.1.10   Prototype back-end trigger receiver and logic module
                1.3.01.2   ASIC Development (BLAB3B) : Integration of DACs and tri-state bus output
                1.3.01.3   Pre-production prototyping
              1.3.01.3.1   Electromechanical design and engineering
              1.3.01.3.2   HV board : PMT high voltage distribution
              1.3.01.3.3   Front board: PMT-to-ASIC electromechanical interface
              1.3.01.3.4   ASIC carrier: daughter card signal distribution interface for 4x ASIC daughter cards
              1.3.01.3.5   BLAB3B daughter card: single ASIC and services
              1.3.01.3.6   Interface board: power regulation and clock jitter cleaning
              1.3.01.3.7   SCROD control and data collection module
              1.3.01.3.8   DSP_FIN: Back-end FINESSE data receiver and fast feature extraction module for COPPER system
              1.3.01.3.9   TRIG_FIN: Back-end trigger receiver and logic module
             1.3.01.3.10   Test Fixtures
                  1.3.02   Development (barrel KLM: B-KLM, endcap KLM: E-KLM)
                     -->   Finalize specifications for production boards being fabricated in KLM scintillator-based systems (endcap KLM and layer
                           0,1 barrel KLM) WBS elements, 1.3.05 and 1.3.06.1-1.3.06.3. Does not include development of barrel KLM RPC
                           readout or beam monitoring systems, WBS 1.3.06.4 and 1.3.07. First generation R&D prototypes of KLM scintillator
                           readout have been produced. The remaining R&D/prototyping work consists of 2 more phases. In Rev. B, VME crate-
                           based readout PCBs and deeper sampling ASICs will be fabricated and evaluated in cosmic tests. In Rev. C, pre-
                           production prototypes will be assembled, using candidate final versions of all commercial and custom components, and
                           evaluated versus all final engineering specifications.
                           Successful completion of Phase C prototyping is necessary prior to commitment for production fabrication. Due to the
                           use of Ball Grid Array and other difficult to assemble parts (for space reasons), all production boards will be assembled
                           in industry and checked/debugged at Belle II member institute laboratories. Subcomponents will be individually tested
                           and characterized prior to integration into front-end integrated readout modules. These are the units that are directly
                           integrated with opto-detector front-ends to form the scintillator KLM detector instrumentation.
                           Integration of the detector front-ends and and backend readout (FINESSE/COPPER) into fully-assembled detector sub-
                1.3.02.1   modules, wherein cosmic ray calibration data can be taken, completes this WBS element.
                           Cosmic ray quadrant test, 150 channel system
              1.3.02.1.1   Electromechanical design and engineering
              1.3.02.1.2   Preamplifier cards: MPPC amplification
              1.3.02.1.3   Carrier board: 15x preamplifiers and voltage regulation
              1.3.02.1.4   TARGET daughter card: single 16 channel TARGET ASIC and services
              1.3.02.1.5   KLM motherboard: 9U VME module with 10x TARGET daughter cards and SCROD
                1.3.02.2   ASIC development (TARGET3): deep sampling readout



10/27/2011                                                    C. Scope of Work                                                                 5 of 20
               1.3.02.3   Pre-production prototyping
             1.3.02.3.1   Electromechanical design and engineering
             1.3.02.3.2   Preamplifier cards: MPPC amplification
             1.3.02.3.3   Carrier board: 15x preamplifiers and voltage regulation
             1.3.02.3.4   TARGET3 daughter card: single 16 channel TARGET3 ASIC and services
             1.3.02.3.5   KLM motherboard: 9U VME module with 10x TARGET3 daughter cards and SCROD
             1.3.02.3.6   Test Fixtures
                 1.3.03   Development (beam monitoring readout)
                    -->   Finalize specifications for production boards being fabricated for realtime beam parameter (size and collision timing)
                          monitoring, WBS element 1.3.07. First generation R&D prototypes of coded aperture imaging x-ray readout have been
                          produced. The remaining R&D/prototyping work consists of 2 more phases. In Rev. B, cPCI-based readout PCBs and
                          higher throughput sampling ASICs will be fabricated and evaluated at an ATF2 beamline. In Rev. C, pre-production
                          prototypes will be assembled, using candidate final versions of all commercial and custom components, and evaluated
                          versus all final engineering specifications.
                          Successful completion of Phase C prototyping is necessary prior to commitment for production fabrication. Due to the
                          use of Ball Grid Array and other difficult to assemble parts (for space reasons), all production boards will be assembled
                          in industry and checked/debugged at Belle II member institute laboratories. Subcomponents will be individually tested
                          and characterized prior to integration into beam diagnostic modules. These are the units that are directly integrated with
                          x-ray and optical detectors.
                          Integration of the detector front-ends and backend readout into fully-assembled beam diagnostic modules, wherein
                          verification data can be taken at the KEK Photon Factory, completes this WBS element.
               1.3.03.1   ATF2 x-ray monitor test, 64 channel system
             1.3.03.1.1   Electromechanical design and engineering
             1.3.03.1.2   Preamplifier cards: photodetector amplification
             1.3.03.1.3   STURM2 daughter card: single 8 channel STURM2 ASIC and services
             1.3.03.1.4   Beam monitor motherboard: standalone module with 8x STURM2 daughter cards and SCROD
               1.3.03.2   ASIC development (STURM3): higher throughput
               1.3.03.3   Pre-production prototyping
             1.3.03.3.1   Electromechanical design and engineering
             1.3.03.3.2   Preamplifier cards: photodetector amplification
             1.3.03.3.3   STURM3 daughter card: single 8 channel STURM3 ASIC and services
             1.3.03.3.4   Beam monitor motherboard: standalone module with 16x STURM3 daughter cards and SCROD
             1.3.03.3.5   Test Fixtures

                1.3.04 iTOP Readout System
                   --> Procurement of electronic components, assembly of boards and testing the boards prior to delivery to KEK. Integration,
                       testing and installation will occur in WBS 1.2.
              1.3.04.1 Front-end (subdetector readout module: SRM) board stack production



10/27/2011                                                   C. Scope of Work                                                                  6 of 20
             1.3.04.2   Back-end receiver and feature extraction (FINESSE DSP: DSP_FIN)
             1.3.04.3   Back-end trigger receiver and logic (FINESSE Trigger: TRIG_FIN)
               1.3.05   E-KLM Readout System
                  -->   Procurement of electronic components, assembly of boards and testing the boards prior to delivery to KEK. Integration,
                        testing and installation will occur in WBS 1.4.
             1.3.05.1   Front-end integrated readout modules
             1.3.05.2   Back-end receiver and feature extraction (FINESSE DSP: DSP_FIN)
             1.3.05.3   Back-end trigger receiver and logic (FINESSE Trigger: TRIG_FIN)
               1.3.06   B-KLM Readout System
                  -->   Procurement of electronic components, assembly of boards and testing the boards prior to delivery to KEK. Integration,
                        testing and installation will occur in WBS 1.5.
             1.3.06.1   Front-end integrated readout modules
             1.3.06.2   Back-end receiver and feature extraction (FINESSE DSP: DSP_FIN)
             1.3.06.3   Back-end trigger receiver and logic (FINESSE Trigger: TRIG_FIN)
               1.3.07   Beam Monitor Readout System
                  -->   Procurement of electronic components, assembly of boards and testing the boards prior to delivery to KEK. Integration,
                        testing and installation will occur in WBS 1.6. Not contained in estimate provided for March 15 review.

             1.3.07.1 Front-end integrated readout modules
             1.3.07.2 Back-end receiver and feature extraction (cPCI DSP: DSP_cPCI)




10/27/2011                                                C. Scope of Work                                                               7 of 20
D. Deliverables/Schedule
                               In this section, you should identify the deliverables and steps or activities that lead up to the
                               completion of the deliverable. Using the WBS as the structure, work is assigned to responsible
                               individuals or organizations. For each lower level WBS element, partition the scope into major
                               activities, and then subdivide the major activities into lower level schedule activities and events.
                               Milestones have no duration. They are established to flag the start or completion of an important
                               activity or group of activities and represent the deliverables of the WBS element.


                                                                                                                                                  Finish
                      WBS                                               Activity/Milestone                                            Start Date
                                                                                                                                                   Date
                      1.3.01 Development (iTOP)                                                                                       3/25/2011 9/1/2012
                    1.3.01.1 Cosmic ray and beam test (1/16th system): Construction and integration of a full bar readout             3/25/2011 9/15/2011

                  1.3.01.1.1   Electromechanical design and engineering                                                               3/25/2011    9/15/2011
                  1.3.01.1.2   HV board : PMT high voltage distribution                                                               3/25/2011    4/30/2011
                  1.3.01.1.3   Front board: PMT-to-ASIC electromechanical interface                                                   3/25/2011    4/30/2011
                  1.3.01.1.4   ASIC carrier: daughter card signal distribution interface for 4x ASIC daughter cards                   3/25/2011    4/15/2011
                  1.3.01.1.5   BLAB3A (first revision ASIC) daughter card: single ASIC and services                                   3/25/2011    4/15/2011
                  1.3.01.1.6   Interface board: power regulation and clock jitter cleaning                                            3/25/2011    4/15/2011
                  1.3.01.1.7   SCROD control and data collection module                                                               3/25/2011    3/25/2011
                  1.3.01.1.8   cPCI_DSP: Back-end data receiver and fast feature extraction module                                    3/25/2011    3/25/2011
                  1.3.01.1.9   Prototype clock and JTAG programming distribution                                                      3/25/2011    3/25/2011
                 1.3.01.1.10   Prototype back-end trigger receiver and logic module                                                   3/25/2011    3/25/2011
                    1.3.01.2   ASIC Development (BLAB3B) : Integration of DACs and tri-state bus output                               11/1/2011    6/1/2012
                    1.3.01.3   Pre-production prototyping                                                                             11/1/2011    9/1/2012
                  1.3.01.3.1   Electromechanical design and engineering                                                               11/1/2011    9/1/2012
                  1.3.01.3.2   HV board : PMT high voltage distribution                                                               11/1/2011    1/1/2012
                  1.3.01.3.3   Front board: PMT-to-ASIC electromechanical interface                                                   11/1/2011    1/1/2012
                  1.3.01.3.4   ASIC carrier: daughter card signal distribution interface for 4x ASIC daughter cards                   4/1/2012     5/1/2012
                  1.3.01.3.5   BLAB3B daughter card: single ASIC and services                                                         4/1/2012     5/1/2012
                  1.3.01.3.6   Interface board: power regulation and clock jitter cleaning                                            11/1/2011    2/15/2012
                  1.3.01.3.7   SCROD control and data collection module                                                               11/1/2011    2/1/2012
                  1.3.01.3.8   DSP_FIN: Back-end FINESSE data receiver and fast feature extraction module for COPPER                  11/1/2011    3/1/2012
                               system
                  1.3.01.3.9   TRIG_FIN: Back-end trigger receiver and logic module                                                   11/1/2011    3/1/2012
                 1.3.01.3.10   Test Fixtures                                                                                          11/1/2011    3/1/2012
                      1.3.02   Development (barrel KLM: B-KLM, endcap KLM: E-KLM)                                                     3/25/2011    9/1/2011
                    1.3.02.1   Cosmic ray quadrant test, 150 channel system                                                           7/1/2011     9/1/2011
                  1.3.02.1.1   Electromechanical design and engineering                                                               3/25/2011    3/25/2011


10/27/2011                                                              D. Deliverables                                                                 8 of 20
             1.3.02.1.2   Preamplifier cards: MPPC amplification                                                 3/25/2011   3/25/2011
             1.3.02.1.3   Carrier board: 15x preamplifiers and voltage regulation                                3/25/2011   3/25/2011
             1.3.02.1.4   TARGET daughter card: single 16 channel TARGET ASIC and services                       3/25/2011   3/25/2011
             1.3.02.1.5   KLM motherboard: 9U VME module with 10x TARGET daughter cards and SCROD                3/25/2011   4/30/2011
               1.3.02.2   ASIC development (TARGET3): deep sampling readout                                      1/1/2012    8/1/2012
               1.3.02.3   Pre-production prototyping                                                             9/1/2011    10/1/2012
             1.3.02.3.1   Electromechanical design and engineering                                               1/1/2012    10/1/2012
             1.3.02.3.2   Preamplifier cards: MPPC amplification                                                 9/1/2011    11/1/2011
             1.3.02.3.3   Carrier board: 15x preamplifiers and voltage regulation                                9/1/2011    11/1/2011
             1.3.02.3.4   TARGET3 daughter card: single 16 channel TARGET3 ASIC and services                     2/1/2012    5/1/2012
             1.3.02.3.5   KLM motherboard: 9U VME module with 10x TARGET3 daughter cards and SCROD               3/1/2012    6/1/2012
             1.3.02.3.6   Test Fixtures                                                                          9/1/2011    6/1/2012
                 1.3.03   Development (beam monitoring readout)                                                  3/25/2011   5/1/2012
               1.3.03.1   ATF2 x-ray monitor test, 64 channel system                                             3/25/2011   11/1/2011
             1.3.03.1.1   Electromechanical design and engineering                                               3/25/2011   8/30/2011
             1.3.03.1.2   Preamplifier cards: photodetector amplification                                        3/25/2011   5/1/2011
             1.3.03.1.3   STURM2 daughter card: single 8 channel STURM2 ASIC and services                        4/15/2011   5/15/2011
             1.3.03.1.4   Beam monitor motherboard: standalone module with 8x STURM2 daughter cards and SCROD    6/1/2011    7/15/2011

               1.3.03.2   ASIC development (STURM3): higher throughput                                           10/1/2011   5/1/2012
               1.3.03.3   Pre-production prototyping                                                             10/1/2011   5/1/2012
             1.3.03.3.1   Electromechanical design and engineering                                               12/1/2011   5/1/2012
             1.3.03.3.2   Preamplifier cards: photodetector amplification                                        10/1/2011   12/1/2011
             1.3.03.3.3   STURM3 daughter card: single 8 channel STURM3 ASIC and services                        2/1/2012    4/1/2012
             1.3.03.3.4   Beam monitor motherboard: standalone module with 16x STURM3 daughter cards and SCROD   3/1/2012    5/1/2012

             1.3.03.3.5 Test Fixtures                                                                            12/1/2011 4/1/2012

                1.3.04    iTOP Readout System                                                                    9/1/2012    10/1/2013
              1.3.04.1    Front-end (subdetector readout module: SRM) board stack production                     9/1/2012    10/1/2013
              1.3.04.2    Back-end receiver and feature extraction (FINESSE DSP: DSP_FIN)                        9/1/2012    8/1/2013
              1.3.04.3    Back-end trigger receiver and logic (FINESSE Trigger: TRIG_FIN)                        9/1/2012    8/1/2013

                1.3.05    E-KLM Readout System                                                                   10/1/2012   8/1/2013
              1.3.05.1    Front-end integrated readout modules                                                   10/1/2012   4/1/2013
              1.3.05.2    Back-end receiver and feature extraction (FINESSE DSP: DSP_FIN)                        10/1/2012   8/1/2013
              1.3.05.3    Back-end trigger receiver and logic (FINESSE Trigger: TRIG_FIN)                        10/1/2012   8/1/2013

                1.3.06 B-KLM Readout System                                                                      10/1/2012 12/1/2014


10/27/2011                                                      D. Deliverables                                                   9 of 20
             1.3.06.1 Front-end integrated readout modules                              10/1/2012 4/1/2014
             1.3.06.2 Back-end receiver and feature extraction (FINESSE DSP: DSP_FIN)   10/1/2012 12/1/2014
             1.3.06.3 Back-end trigger receiver and logic (FINESSE Trigger: TRIG_FIN)   10/1/2012 12/1/2014

               1.3.07 Beam Monitor Readout System                                       5/1/2012   11/1/2012
             1.3.07.1 Front-end integrated readout modules                              5/1/2012   11/1/2012
             1.3.07.2 Back-end receiver and feature extraction (cPCI DSP: DSP_cPCI)     5/1/2012   11/1/2012




10/27/2011                                                 D. Deliverables                             10 of 20
E. Relationships/Interfaces        In this section, you should identify the deliverables from others that this WBS element
                                   needs to complete its work (inputs)and the deliverables that this element is preparing to
                                   meet a need in another area of the project (outputs). Identify the deliverable and the WBS
                                   element it goes to or comes from.

                                                                                                                                    Date
                       Inputs                                           Deliverable/Item                                                       From WBS
                                                                                                                                  Needed
                               1 Final iTOP quartz bar box mechanics                                                            11/1/2011    1.2.03
                               2
                               3
                               4
                               5
                               6
                               7
                               8
                               9
                              10

                                                                                                                                    Date
                      Outputs                                           Deliverable/Item                                                         To WBS
                                                                                                                                 Completed
                               1   iTOP SRMs                                                                                    10/1/2013    1.2.05
                               2   Endcap KLM front-end integrated readout modules                                              8/1/2013     1.4.04
                               3   Barrel KLM scintillator-based front-end integrated readout modules                           12/1/2014    1.5.06
                               4   Beam monitoring system front-end integrated readout modules                                  11/1/2012    1.6.07
                               5
                               6
                               7
                               8
                               9
                              10




10/27/2011                                                                E. Interfaces                                                               11 of 20
F. Cost Estimate

                                                                                     Non-Labor                                               Labor
                                                                                                                                                                           Grant
    WBS                        Title                 Description of Activity     Element      Cost           Name         Institution      Function        Hours   Cost
                                                                                                                                                                          Funded?
        1.3.01 Development (iTOP)
      1.3.01.1 Cosmic ray and beam test (1/16th
               system): Construction and
               integration of a full bar readout

    1.3.01.1.1 Electromechanical design and         1) Complete first readout   Electromec 4000
               engineering                          module, validate and        hanical
                                                    produce three more.         and optical
                                                                                mounting
                                                                                hardware

                                                    2) Design                                          Marc Rosen      Hawaii           Sr. Engineer      80
                                                    3) Fabrication/Assembly                            Louis Ridley    Hawaii           Instr. Technician 120

    1.3.01.1.2 HV board : PMT high voltage          1) Design                                          TBD             Hawaii           Jr. Engineer     80
               distribution
                                                    2) Fabrication              PCB Fab     500
                                                    3) Assembly                 Pick-and-   500        Robin Caplett   Hawaii           Student Tech.    20
                                                                                Place
                                                    4) Evaluation                                      Kurtis Nishimura Hawaii          Postdoc          40

    1.3.01.1.3 Front board: PMT-to-ASIC             1) Design                                          TBD             Hawaii           Jr. Engineer     60
               electromechanical interface
                                                    2) Fabrication              PCB Fab     500
                                                    3) Assembly                 Pick-and-   500        Robin Caplett   Hawaii           Student Tech.    20
                                                                                Place
                                                    4) Evaluation                                      Kurtis Nishimura Hawaii          Postdoc          20

    1.3.01.1.4 ASIC carrier: daughter card signal   1) Design                                          Gary Varner     Hawaii           Faculty          20
               distribution interface for 4x ASIC
               daughter cards
                                                    2) Fabrication              PCB Fab     1000
                                                    3) Assembly                 Pick-and-   500        Robin Caplett   Hawaii           Student Tech.    10
                                                                                Place
                                                    4) Evaluation                                      Kurtis Nishimura Hawaii          Postdoc          10

    1.3.01.1.5 BLAB3A (first revision ASIC)         1) Design                                          Louis Ridley    Hawaii           Instr. Technician 40
               daughter card: single ASIC and
               services
                                                    2) Fabrication              PCB Fab     1500
                                                    3) Assembly                 Pick-and-   1000       Robin Caplett   Hawaii           Student Tech.    10
                                                                                Place
                                                    4) Evaluation                                      Kurtis Nishimura Hawaii          Postdoc          10




10/27/2011                                                                                   F. Cost                                                                        12 of 20
    1.3.01.1.6 Interface board: power regulation       1) Design                                    Louis Ridley    Hawaii    Instr. Technician 60
               and clock jitter cleaning
                                                       2) Fabrication        PCB Fab     1000
                                                       3) Assembly           Pick-and-   500        Robin Caplett   Hawaii    Student Tech.    20
                                                                             Place
                                                       4) Evaluation                                Kurtis Nishimura Hawaii   Postdoc          20

    1.3.01.1.7 SCROD control and data collection       1) Design                                    TBD             Hawaii    Jr. Engineer     120
               module
                                                       2) Fabrication        PCB Fab     3000
                                                       3) Assembly           Pick-and-   1500       Robin Caplett   Hawaii    Student Tech.    20
                                                                             Place
                                                       4) Firmware                                  TBD             Hawaii    Jr. Engineer     640
                                                       5) Software                                  Andrew Wong     Hawaii    Software         80
                                                                                                                              Engineer
                                                       6) Evaluation                                Kurtis Nishimura Hawaii   Postdoc          40

    1.3.01.1.8 cPCI_DSP: Back-end data receiver        1) Design                                    TBD             Hawaii    Jr. Engineer     40
               and fast feature extraction module

                                                       2) Fabrication        PCB Fab     4500
                                                       3) Assembly           Pick-and-   2000       Robin Caplett   Hawaii    Student Tech.    20
                                                                             Place
                                                       4) Firmware                                  TBD             Hawaii    Jr. Engineer     120
                                                       5) Software                                  Andrew Wong     Hawaii    Software         90
                                                                                                                              Engineer
                                                       6) Evaluation                                TBD             Hawaii    Jr. Engineer     60
    1.3.01.1.9 Prototype clock and JTAG                1) Design                                    TBD             Hawaii    Jr. Engineer     40
               programming distribution
                                                       2) Fabrication        PCB Fab     1000
                                                       3) Assembly           Pick-and-   500        Robin Caplett   Hawaii    Student Tech.    10
                                                                             Place
                                                       4) Evaluation                                Kurtis Nishimura Hawaii   Postdoc          16

   1.3.01.1.10 Prototype back-end trigger receiver     1) Design                                    TBD             Hawaii    Jr. Engineer     40
               and logic module
                                                       2) Fabrication        PCB Fab     2500
                                                       3) Assembly           Pick-and-   1500       Robin Caplett   Hawaii    Student Tech.    10
                                                                             Place
                                                       4) Firmware                                  Xin Gao         Hawaii    Grad Student     160
                                                       5) Software                                  TBD             Hawaii    Grad Student     160
                                                       6) Evaluation                                TBD             Hawaii    Postdoc          80
      1.3.01.2 ASIC Development (BLAB3B) :             1) Design                                    Gary Varner     Hawaii    Faculty          80
               Integration of DACs and tri-state bus
               output
                                                       2) Fabrication        MOSIS     50000
                                                       3) Evaluation Board   Fab/Assem 4000         TBD             Hawaii    Jr. Engineer     40
                                                                             bly




10/27/2011                                                                                F. Cost                                                    13 of 20
                                                    4) Evaluation                                   Kurtis Nishimura Hawaii   Postdoc          80

      1.3.01.3 Pre-production prototyping
    1.3.01.3.1 Electromechanical design and         1) Finalize thermal model Thermal    3000       Marc Rosen      Hawaii    Sr. Engineer     60
               engineering                          and create mockup.        model

                                                    2) Move from prototype to Model final 5000      Marc Rosen      Hawaii    Sr. Engineer     160
                                                    production-grade          assembly
                                                    fabrication.
                                                    3) Assembly of prototype                        Louis Ridley    Hawaii    Instr. Technician 80




    1.3.01.3.2 HV board : PMT high voltage          1) Design                                       TBD             Hawaii    Jr. Engineer     40
               distribution
                                                    2) Fabrication           PCB Fab     1000
                                                    3) Assembly              Pick-and-   500        Robin Caplett   Hawaii    Student Tech.    10
                                                                             Place
                                                    4) Evaluation                                   Kurtis Nishimura Hawaii   Postdoc          20

    1.3.01.3.3 Front board: PMT-to-ASIC             1) Design                                       TBD             Hawaii    Jr. Engineer     20
               electromechanical interface
                                                    2) Fabrication           PCB Fab     500
                                                    3) Assembly              Pick-and-   500        Robin Caplett   Hawaii    Student Tech.    10
                                                                             Place
                                                    4) Evaluation                                   Kurtis Nishimura Hawaii   Postdoc          10

    1.3.01.3.4 ASIC carrier: daughter card signal   1) Design                                       TBD             Hawaii    Instr. Technician 20
               distribution interface for 4x ASIC
               daughter cards
                                                    2) Fabrication           PCB Fab     1000
                                                    3) Assembly              Pick-and-   500        Robin Caplett   Hawaii    Student Tech.    10
                                                                             Place
                                                    4) Evaluation                                   Kurtis Nishimura Hawaii   Postdoc          10

    1.3.01.3.5 BLAB3B daughter card: single ASIC 1) Design                                          Louis Ridley    Hawaii    Instr. Technician 40
               and services
                                                 2) Fabrication              PCB Fab     1000
                                                 3) Assembly                 Pick-and-   500        Robin Caplett   Hawaii    Student Tech.    10
                                                                             Place
                                                    4) Evaluation                                   Kurtis Nishimura Hawaii   Postdoc          20

    1.3.01.3.6 Interface board: power regulation    1) Design                                       Louis Ridley    Hawaii    Instr. Technician 40
               and clock jitter cleaning
                                                    2) Fabrication           PCB Fab     1000
                                                    3) Assembly              Pick-and-   500        Robin Caplett   Hawaii    Student Tech.    10
                                                                             Place
                                                    4) Evaluation                                   Kurtis Nishimura Hawaii   Postdoc          20




10/27/2011                                                                                F. Cost                                                    14 of 20
    1.3.01.3.7 SCROD control and data collection   1) Design                               TBD             Hawaii    Jr. Engineer     80
               module
                                                   2) Fabrication   PCB Fab     3000
                                                   3) Assembly      Pick-and-   1500       Robin Caplett   Hawaii    Student Tech.    10
                                                                    Place
                                                   4) Firmware                             TBD             Hawaii    Jr. Engineer     80
                                                   5) Software                             Andrew Wong     Hawaii    Software         20
                                                                                                                     Engineer
                                                   6) Evaluation                           Kurtis Nishimura Hawaii   Postdoc          40

    1.3.01.3.8 DSP_FIN: Back-end FINESSE data 1) Design                                    TBD             Hawaii    Jr. Engineer     80
               receiver and fast feature extraction
               module for COPPER system

                                                   2) Fabrication   PCB Fab     2500
                                                   3) Assembly      Pick-and-   1500       Robin Caplett   Hawaii    Student Tech.    20
                                                                    Place
                                                   4) Firmware                             TBD             Hawaii    Jr. Engineer     160
                                                   5) Software                             Andrew Wong     Hawaii    Software         40
                                                                                                                     Engineer
                                                   6) DSP Code                             Lili Zhang      Hawaii    Jr. Engineer     320
                                                   7) Evaluation                           TBD             Hawaii    Postdoc          80
    1.3.01.3.9 TRIG_FIN: Back-end trigger receiver 1) Design                               TBD             Hawaii    Jr. Engineer     40
               and logic module
                                                   2) Fabrication   PCB Fab     2500
                                                   3) Assembly      Pick-and-   1000       Robin Caplett   Hawaii    Student Tech.    10
                                                                    Place
                                                   4) Firmware                             Xin Gao         Hawaii    Grad Student     160
                                                   5) Software                             TBD             Hawaii    Grad Student     160
                                                   6) Evaluation                           TBD             Hawaii    Postdoc          80
   1.3.01.3.10 Test Fixtures                       1) Design                               TBD             Hawaii    Jr. Engineer     80
                                                   2) Fabrication   PCB Fab     5000
                                                   3) Assembly      Pick-and-   1500       Robin Caplett   Hawaii    Student Tech.    40
                                                                    Place
                                                   4) Software                             Andrew Wong     Hawaii    Software         40
                                                                                                                     Engineer
                                                   5) Evaluation                           TBD             Hawaii    Postdoc          40
        1.3.02 Development (barrel KLM: B-KLM,
               endcap KLM: E-KLM)
      1.3.02.1 Cosmic ray quadrant test, 150
               channel system
    1.3.02.1.1 Electromechanical design and        1) Design                               TBD             Hawaii    Jr. Engineer     40
               engineering
                                                   2) Prototypes    Jigs/Brack 2000
                                                                    ets
    1.3.02.1.2 Preamplifier cards: MPPC            1) Design                               TBD             Hawaii    Instr. Technician 20
               amplification
                                                   2) Fabrication   PCB Fab     1000
                                                   3) Assembly                             Robin Caplett   Hawaii    Student Tech.    80



10/27/2011                                                                       F. Cost                                                    15 of 20
                                                    4) Evaluation                                Robin Caplett   Hawaii   Student Tech.     20
    1.3.02.1.3 Carrier board: 15x preamplifiers and 1) Design                                    Louis Ridley    Hawaii   Instr. Technician 40
               voltage regulation
                                                    2) Fabrication        PCB Fab     500
                                                    3) Assembly                                  Robin Caplett   Hawaii   Student Tech.     20
                                                    4) Evaluation                                Robin Caplett   Hawaii   Student Tech.     20
    1.3.02.1.4 TARGET daughter card: single 16      1) Design                                    Louis Ridley    Hawaii   Instr. Technician 40
               channel TARGET ASIC and services

                                                    2) Fabrication        PCB Fab     1000
                                                    3) Assembly                                  Travis          Hawaii   Student Tech.    40
                                                                                                 Hishinuma
                                              4) Evaluation                                      TBD             Hawaii   Postdoc           40
    1.3.02.1.5 KLM motherboard: 9U VME module 1) Design                                          Louis Ridley    Hawaii   Instr. Technician 80
               with 10x TARGET daughter cards
               and SCROD
                                              2) Fabrication              PCB Fab     2000
                                              3) Assembly                                        Robin Caplett   Hawaii   Student Tech.    40
                                              4) Firmware                                        TBD             Hawaii   Jr. Engineer     80
                                              5) Software                                        Andrew Wong     Hawaii   Software         40
                                                                                                                          Engineer
                                                    6) Evaluation                                TBD             Hawaii   Postdoc          40
      1.3.02.2 ASIC development (TARGET3):          1) Design                                    Gary Varner     Hawaii   Faculty          80
               deep sampling readout
                                                    2) Fabrication        MOSIS     50000
                                                    3) Evaluation Board   Fab/Assem 4000         TBD             Hawaii   Jr. Engineer     40
                                                                          bly
                                                    4) Evaluation                                TBD             Hawaii   Postdoc          80
      1.3.02.3 Pre-production prototyping
    1.3.02.3.1 Electromechanical design and         1) Design                                    TBD             Hawaii   Jr. Engineer     20
               engineering
                                                    2) Prototypes         Jigs/Brack 2000
                                                                          ets
    1.3.02.3.2 Preamplifier cards: MPPC             1) Design                                    TBD             Hawaii   Instr. Technician 20
               amplification
                                                    2) Fabrication        PCB Fab     1000
                                                    3) Assembly           Pick-and-   500
                                                                          Place
                                                    4) Evaluation                                Robin Caplett   Hawaii   Student Tech.     20
    1.3.02.3.3 Carrier board: 15x preamplifiers and 1) Design                                    Louis Ridley    Hawaii   Instr. Technician 20
               voltage regulation
                                                    2) Fabrication        PCB Fab     500
                                                    3) Assembly           Pick-and-   500
                                                                          Place
                                                    4) Evaluation                                Robin Caplett   Hawaii   Student Tech.     20
    1.3.02.3.4 TARGET3 daughter card: single 16     1) Design                                    Louis Ridley    Hawaii   Instr. Technician 20
               channel TARGET3 ASIC and
               services
                                                    2) Fabrication        PCB Fab     1000



10/27/2011                                                                             F. Cost                                                   16 of 20
                                                   3) Assembly                Pick-and-   500
                                                                              Place
                                               4) Evaluation                                         TBD             Hawaii   Postdoc          40
    1.3.02.3.5 KLM motherboard: 9U VME module 1) Design                                              TBD             Hawaii   Jr. Engineer     40
               with 10x TARGET3 daughter cards
               and SCROD
                                               2) Fabrication                 PCB Fab     2000
                                               3) Assembly                    Pick-and-   1000
                                                                              Place
                                                   4) Firmware                                       TBD             Hawaii   Jr. Engineer     40
                                                   5) Software                                       Andrew Wong     Hawaii   Software         20
                                                                                                                              Engineer
                                                   6) Evaluation                                     TBD             Hawaii   Postdoc          40
    1.3.02.3.6 Test Fixtures                       1) Design                                         TBD             Hawaii   Jr. Engineer     40
                                                   2) Fabrication             PCB Fab     5000
                                                   3) Assembly                Pick-and-   1500       Robin Caplett   Hawaii   Student Tech.    20
                                                                              Place
                                                   4) Software                                       Andrew Wong     Hawaii   Software         20
                                                                                                                              Engineer
                                                   5) Evaluation                                     TBD             Hawaii   Postdoc          40
        1.3.03 Development (beam monitoring
               readout)
      1.3.03.1 ATF2 x-ray monitor test, 64 channel
               system
    1.3.03.1.1 Electromechanical design and        1) Design                                         Louis Ridley    Hawaii   Instr. Technician 80
               engineering
                                                   2) Prototypes              Evaluation 5000
                                                                              Board
    1.3.03.1.2 Preamplifier cards: photodetector   1) Design                                         Xi Zhao         Hawaii   Jr. Engineer     80
               amplification
                                                   2) Fabrication             PCB Fab     500
                                                   3) Assembly                                       Travis          Hawaii   Student Tech.    40
                                                                                                     Hishinuma
                                                   4) Simulation/Evaluation                          Xi Zhao         Hawaii   Jr. Engineer     120

    1.3.03.1.3 STURM2 daughter card: single 8      1) Design                                         Louis Ridley    Hawaii   Instr. Technician 40
               channel STURM2 ASIC and
               services
                                                   2) Fabrication             PCB Fab     1000
                                                   3) Assembly                                       Travis          Hawaii   Student Tech.    40
                                                                                                     Hishinuma
                                                4) Evaluation                                        TBD             Hawaii   Postdoc           40
    1.3.03.1.4 Beam monitor motherboard:        1) Design                                            Louis Ridley    Hawaii   Instr. Technician 40
               standalone module with 8x STURM2
               daughter cards and SCROD

                                                   2) Fabrication             PCB Fab     2000
                                                   3) Assembly                                       Robin Caplett   Hawaii   Student Tech.    40
                                                   4) Firmware                                       TBD             Hawaii   Jr. Engineer     80




10/27/2011                                                                                 F. Cost                                                   17 of 20
                                                   5) Software                                       Andrew Wong     Hawaii   Software         20
                                                                                                                              Engineer
                                                   6) Evaluation                                     TBD             Hawaii   Postdoc          40
      1.3.03.2 ASIC development (STURM3):          1) Design                                         Gary Varner     Hawaii   Faculty          80
               higher throughput
                                                   2) Fabrication             MOSIS     30000
                                                   3) Evaluation Board        Fab/Assem 3000         TBD             Hawaii   Jr. Engineer     40
                                                                              bly
                                                   4) Evaluation                                     TBD             Hawaii   Postdoc          40
      1.3.03.3 Pre-production prototyping
    1.3.03.3.1 Electromechanical design and        1) Design                                         TBD             Hawaii   Jr. Engineer     40
               engineering
                                                   2) Prototypes              Carrier     5000
                                                                              PCB
    1.3.03.3.2 Preamplifier cards: photodetector   1) Design                                         Xi Zhao         Hawaii   Jr. Engineer     40
               amplification
                                                   2) Fabrication             PCB Fab     500
                                                   3) Assembly                                       Travis          Hawaii   Student Tech.    20
                                                                                                     Hishinuma
                                                   4) Simulation/Evaluation                          Xi Zhao         Hawaii   Jr. Engineer     60

    1.3.03.3.3 STURM3 daughter card: single 8      1) Design                                         Louis Ridley    Hawaii   Instr. Technician 40
               channel STURM3 ASIC and
               services
                                                   2) Fabrication             PCB Fab     1000
                                                   3) Assembly                                       Travis          Hawaii   Student Tech.    40
                                                                                                     Hishinuma
                                                   4) Evaluation                                     TBD             Hawaii   Postdoc           40
    1.3.03.3.4 Beam monitor motherboard:           1) Design                                         Louis Ridley    Hawaii   Instr. Technician 40
               standalone module with 16x
               STURM3 daughter cards and
               SCROD
                                                   2) Fabrication             PCB Fab     2000
                                                   3) Assembly                                       Robin Caplett   Hawaii   Student Tech.    40
                                                   4) Firmware                                       TBD             Hawaii   Jr. Engineer     80
                                                   5) Software                                       Andrew Wong     Hawaii   Software         20
                                                                                                                              Engineer
                                                   6) Evaluation                                     TBD             Hawaii   Postdoc          80
    1.3.03.3.5 Test Fixtures                       1) Design                                         TBD             Hawaii   Jr. Engineer     80
                                                   2) Fabrication             PCB Fab     5000
                                                   3) Assembly                Pick-and-   1500       TBD             Hawaii   Student Tech.    40
                                                                              Place
                                                   4) Software                                       TBD             Hawaii   Software         40
                                                                                                                              Engineer
                                                   5) Evaluation                                     TBD             Hawaii   Postdoc          40

       1.3.04 iTOP Readout System




10/27/2011                                                                                 F. Cost                                                   18 of 20
      1.3.04.1 Front-end (subdetector readout        1) Fabrication and        Complete       528000
               module: SRM) board stack              Assembly (PCBs and        SRMs
               production                            ASICs)
                                                     2) Production engineering                           Marc Rosen      Hawaii    Sr. Engineer   80
                                                     (mechanics)


                                                     3) Production engineering                           TBD             Hawaii    Jr. Engineer   80
                                                     (electronics)


                                                     4) Quality Control                                  TBD             Hawaii    Jr. Engineer   160

                                                     5) Verification                                     Kurtis Nishimura Hawaii   Postdoc        320

      1.3.04.2 Back-end receiver and feature         1) Fabrication and          Full back-   60800
               extraction (FINESSE DSP:              Assembly                    end
               DSP_FIN)
                                                     2) Production engineering                           TBD             Hawaii    Jr. Engineer   40

                                                     3) Quality Control                                  TBD              Hawaii   Jr. Engineer   80
                                                     4) Verification                                     Kurtis Nishimura Hawaii   Postdoc        80

      1.3.04.3 Back-end trigger receiver and logic   1) Fabrication and          Full back- 23600
               (FINESSE Trigger: TRIG_FIN)           Assembly                    end trigger

                                                     2) Production engineering                           TBD             Hawaii    Jr. Engineer   40

                                                     3) Quality Control                                  TBD             Hawaii    Jr. Engineer   80
                                                     4) Verification                                     TBD             Hawaii    Grad Student   120

        1.3.05 E-KLM Readout System
      1.3.05.1 Front-end integrated readout          1) Fabrication and          Full         156000
               modules                               Assembly (PCBs and          integrated
                                                     ASICs)                      front-end
                                                                                 modules
                                                     2) Production engineering                           TBD             Hawaii    Jr. Engineer   40

                                                     3) Quality Control                                  TBD             Hawaii    Jr. Engineer   120
                                                     4) Verification                                     TBD             Hawaii    Postdoc        120
      1.3.05.2 Back-end receiver and feature         1) Fabrication and        Full back-     53200
               extraction (FINESSE DSP:              Assembly (PCBs and        end
               DSP_FIN)                              FPGAs)
                                                     2) Production engineering                           TBD             Hawaii    Jr. Engineer   40

                                                     3) Quality Control                                  TBD             Hawaii    Jr. Engineer   40
                                                     4) Verification                                     TBD             Hawaii    Postdoc        80
      1.3.05.3 Back-end trigger receiver and logic   1) Fabrication and          Full back- 40800
               (FINESSE Trigger: TRIG_FIN)           Assembly (PCBs and          end trigger
                                                     FPGAs)



10/27/2011                                                                                     F. Cost                                                  19 of 20
                                                     2) Production engineering                           TBD   Hawaii        Jr. Engineer   40

                                                     3) Quality Control                                  TBD   Hawaii        Jr. Engineer   40
                                                     4) Verification                                     TBD   Hawaii        Postdoc        80


        1.3.06 B-KLM Readout System
      1.3.06.1 Front-end integrated readout          1) Fabrication and          Full         136000
               modules                               Assembly (PCBs and          integrated
                                                     ASICs)                      front-end
                                                                                 modules
                                                     2) Production engineering                           TBD   Hawaii        Jr. Engineer   40

                                                     3) Quality Control                                  TBD   Hawaii        Jr. Engineer   80
                                                     4) Verification                                     TBD   Hawaii        Postdoc        80
      1.3.06.2 Back-end receiver and feature         1) Fabrication and        Full back-     53200
               extraction (FINESSE DSP:              Assembly (PCBs and        end
               DSP_FIN)                              FPGAs)
                                                     2) Production engineering                           TBD   Hawaii        Jr. Engineer   40

                                                     3) Quality Control                                  TBD   Hawaii        Jr. Engineer   40
                                                     4) Verification                                     TBD   Hawaii        Postdoc        80
      1.3.06.3 Back-end trigger receiver and logic   1) Fabrication and        Full back- 40800
               (FINESSE Trigger: TRIG_FIN)           Assembly (PCBs and        end trigger
                                                     FPGAs)
                                                     2) Production engineering                           TBD   Hawaii        Jr. Engineer   40

                                                     3) Quality Control                                  TBD   Hawaii        Jr. Engineer   40
                                                     4) Verification                                     TBD   Hawaii        Postdoc        80


        1.3.07 Beam Monitor Readout System
      1.3.07.1 Front-end integrated readout          1) Fabrication and          Full         132000
               modules                               Assembly (PCBs and          integrated
                                                     ASICs)                      front-end
                                                                                 modules
                                                     2) Production engineering                           TBD   Hawaii        Jr. Engineer   40

                                                     3) Quality Control                                  TBD   Hawaii        Jr. Engineer   80
                                                     4) Verification                                     TBD   Hawaii        Postdoc        120
      1.3.07.2 Back-end receiver and feature         1) Fabrication and          Full back-   57000
               extraction (cPCI DSP: DSP_cPCI)       Assembly                    end

                                                     2) Production engineering                           TBD   Hawaii        Jr. Engineer   40

                                                     3) DSP Code                                         TBD   Hawaii        Jr. Engineer   80
                                                     4) Quality Control                                  TBD   Hawaii        Jr. Engineer   40
                                                     5) Verification                                     TBD   Wayne State   Grad Student   320




10/27/2011                                                                                     F. Cost                                            20 of 20

				
DOCUMENT INFO
Shared By:
Categories:
Tags:
Stats:
views:8
posted:10/28/2011
language:English
pages:20
xiaohuicaicai xiaohuicaicai
About