EE status 17May04 by panniuniu

VIEWS: 3 PAGES: 16

									                                      The CMS ECAL Endcaps

                                        Crystal ECAL Endcap
                                                                    14648 EE crystals
                                            Calorimeter
                                                 (EE)




                                                       EE
Preshower

 CMS-UK Oversight Committee 17/5/04        D.J.A. Cockerill - RAL                 1
                                     CMS ECAL Endcap, EE



The UK is responsible for
               - procurement of the mechanical structures for the detector
              - completing the detailed design and systems integration


              - procurement and testing of VPTs
              - design and procurement of the VPT HV system


              - assembly of 50% of the SCs




CMS-UK Oversight Committee 17/5/04        D.J.A. Cockerill - RAL             2
                                       ECAL Crystals
                    Urgent need to secure additional crystal producers to meet
                    the CMS schedule for ECAL Barrel and Endcap
                    installation.

                    Potential mass production suppliers:
                    Shanghai Institute of Ceramics (SIC)
                    North Crystals (NC), Apatity, Murmansk
                    Pre-production full sized ECAL Endcap samples
                    SIC: 50 received Feb 2004 150 + 50 EB on order
                    NC: 7 received May 2004 3 more due soon


 Must ensure crystals meet CMS ECAL technical specifications, especially for
 radiation tolerance, before launching contracts
 UK leading the crystal appraisal work at the CERN H4 ECAL test beam
 Programme of intense test beam irradiation and monitoring with purpose built
 supercrystals mounted on E0’
CMS-UK Oversight Committee 17/5/04        D.J.A. Cockerill - RAL                 3
                                       SIC Co60 irradiation results



                                             400Gy in
                                               1.1h
                                                                          Specification limit
                                                                          1.5 m-1




                                     Induced absorption data for the SIC crystals
                                     - consistent with results from BCTP crystals

CMS-UK Oversight Committee 17/5/04               D.J.A. Cockerill - RAL                         4
                               Crystal test beam appraisal with E0’




  Supercrystal in assembly jig
 with 15 SIC Endcap crystals for
       test beam appraisal
 10 remaining pockets for BCTP
 crystals as control/comparison




CMS-UK Oversight Committee 17/5/04         D.J.A. Cockerill - RAL     5
                                     Vacuum Photo-triodes (VPTs)




                                                                      25.4 mm
     VPT Production – good progress
         7900 (51%) delivered
Concerns:
- anomalous devices, 6% of production
Observations:
- production about 4 months behind
  contracted delivery agreement.
  Not on critical path.


CMS-UK Oversight Committee 17/5/04           D.J.A. Cockerill - RAL         6
                                       EE large mechanics

Excellent progress. Large mechanics
for first Endcap finished at TM,
on schedule.

• BP flat to 0.4mm across 3.4m
• BP precision holes to within 50m to neighbour




  CMS-UK Oversight Committee 17/5/04      D.J.A. Cockerill - RAL   7
                                       EE large mechanics

                        Ring flanges                                Cooling and positional
                                                                           spacers
2 cast, machined and completed
Load tested to 12.75t (versus 8t in CMS)
Deflection: 0.4mm at 12.75t in agreement with
FEA
Holes to within 250-500 m, within request




 CMS-UK Oversight Committee 17/5/04        D.J.A. Cockerill - RAL                            8
                                     Front-End Electronics

       Conversion to 0.25 m electronics has been very successful!
        25 channels ECAL Trigger Tower
                                                                   Test Beam
                                                                   October     DE/E
                                                                   2003
                                                                               1%



                                                                               0.5%




Engineering run for DSM ASICS successful (enough for 3 SMs)
Launch full production of electronics in mid-summer.
Plan is to have a full SuperModule in beam by the end of September 2004.
CMS-UK Oversight Committee 17/5/04        D.J.A. Cockerill - RAL               9
                                     EE electronics integration

 Remaining major UK
design/procurement task
 Detailed design for the
integration of electronics
      and services
    on the back of EE
       Progress:
 Mass production of 500
  cooling bar castings
commencing Mon May 17
  Completion of castings
     End June 2004


CMS-UK Oversight Committee 17/5/04          D.J.A. Cockerill - RAL   10
                               CMS planning, main dates of CMS V34
                                           P Bloch 27.4.04

  Surface
  SX5 installation of EB+ (and as many EB- as possible)
                                   Dec 2005 until January 15th 2006

  Underground
  UX5 installation 1 (before Tracker)                                      May 2006
  UX5 installation 2 (after Tracker)                                November 2006
  CMS closed                                                               April –June 2007
  Pilot run End                                                         late Summer 2007

  ECAL Endcap
  EE/SE+ installation                 October 15th –November 15th 2007
  EE/SE- Installation                                     March 2008
  Physics run

CMS-UK Oversight Committee 17/5/04         D.J.A. Cockerill - RAL                             11
                                     Crystal Planning
                                      P Bloch 27.4.04

                                                          BCTP     2nd Supplier total
Possible delivery profiles with 2           before           24600                  24600
                                            Q1 2004            300                  24900
crystal suppliers, P Bloch 27.4.04          Q2 2004           3000                  27900
                                            Q3 2004           3000           180    31080
                                            Q4 2004           3600           360    35040
                                            Q1 2005           3600           610    39250
• Barrel crystal schedule →                 Q2 2005           3600           860    43710
                                            Q3 2005           3600         1100     48410
                                            Q4 2005           3600         1200     53210
                                            Q1 2006           3600         1260     58070
                                            Q2 2006           3070         1260     62400



                                                           BCTP        2nd supplier total
                                             before             100              150       250
                                             Q3 2006           2050              600      2900
• End Cap crystal schedule →                 Q4 2006           2900            1100       6900
                                             Q1 2007           2900            1100     10900
                                             Q2 2007           2900            1200     15000
                                              Total            10850            4150     15000




CMS-UK Oversight Committee 17/5/04    D.J.A. Cockerill - RAL                                     12
                                                         EE planning
                                                         P Bloch 27.4.04
Need highly parallel production, good planning and preparation for 2006/7
  ID    Task Name                                2003        2004          2005      2006      2007       2008       2009
                                               H1   H2     H1    H2      H1   H2   H1   H2   H1    H2   H1    H2   H1   H2
  611       De e 1
  612           Crystals delivery Dee1
  613           Crystals delivery Dee1
  614           Assembly supercrystals for Dee 1
  615           Assembly supercrystals for Dee 1
  616           De e 1 ass + te st
  620       De e 2
  621           Crystals delivery Dee 2
  622           Crystals delivery Dee 2
  623           Assembly supercrystals for Dee 2
  624           Assembly supercrystals for Dee 2
  625           De e 2 ass + te st
  629       De e 3
  630           Crystals delivery Dee 3
  631           Crystals delivery Dee 3
  632           Assembly supercrystals for Dee 3
  633           Assembly supercrystals for Dee 3
  634           De e 3 ass + te st
  638       De e 4
  639           Crystals delivery Dee 4
  640           Crystals delivery Dee 4
  641           Assembly supercrystals for Dee 4
  642           Assembly supercrystals for Dee 4
  643           De e 4 ass + te st

 CMS-UK Oversight Committee 17/5/04                      D.J.A. Cockerill - RAL                                    13
                                     CMS EE Conclusions


         UK successfully undertaking its deliverables to CMS
                 - VPT procurement, test and appraisal
                 - large mechanics design and procurement
                 - HV system design
                 - Electronics integration


                 Late EE crystal delivery THE major concern
                 - SC mass production on hold




CMS-UK Oversight Committee 17/5/04       D.J.A. Cockerill - RAL   14
                                 Additional info follows, next slide




CMS-UK Oversight Committee 17/5/04          D.J.A. Cockerill - RAL     15
                     Impact on UK programme, late crystal delivery

                Good planning, preparation and parallel production will be needed
                               for the assembly of 4 Dees in 2006/7


 Use all the resources that will become available :
 UK SC assembly laboratory
 CERN ECAL barrel assembly team and infrastructure
 Possible technicians at CERN from Rome
 The separate CERN TA1 group and CERN SC/Dee assembly laboratory



 Gain assembly experience beforehand
 • SC construction - will have ~ 250 EE crystals from this summer = 10 SCs
               - ‘SC challenge’ to show we can assemble 10 SCs per week
 • Test beam experience – integration of electronics, laser monitoring system
 • Dee pre-assembly experience of mechanical and cooling items, with CERN TA1 group
 • Dee electrical looming prepared ahead of time

CMS-UK Oversight Committee 17/5/04         D.J.A. Cockerill - RAL                     16

								