									New Hampshire Department of Transportation
Memorial Bridge Replacement Project (13678F)




                                                          SUMMARY OF TOTAL SCORE
                                                              Archer Western         Cianbro          The Middlesex
                                 Scoring Element             Contractors (AWC)   Corporation (CC)   Corporation (TMC)
                          Contract Amount
                                                                $81,420,000.00     $78,884,000.00      $79,220,000.00
                          (ITP Form N-1, Box A)

                          Schedule Adjustment No. of Days
                                                                   565                712                 715
                          (ITP Form O, Line 2a)

                          Schedule Adjustment Amount
                                                                $14,125,000.00     $17,800,000.00      $17,875,000.00
                          (ITP Form O, Line 2C)
                          Price Value
                                                                $95,545,000.00     $96,684,000.00      $97,095,000.00
                          ITP Form O, Line 3)
                          Price Score
                                                                   70.00              69.18               68.88
                          (70% per formula in ITP §5.2)

                          TPEC Technical Evaluation Score          74.25              68.50               67.30

                          Technical Score
                                                                   22.28              20.55               20.19
                          (30% per formula in ITP §5.2)
                          Total Score
                                                                   92.28              89.73               89.07
                          (Price Score + Technical Score)

                          Rank                                       1                  2                   3




RFP Evaluation                                                                                                           Date Prepared:
Summary of Total Score                                             Page 1 of 1                                          October 13, 2011

								
To top